Attachment Narrative Exhibit

This document pretains to SES-STA-20120626-00616 for Special Temporal Authority on a Satellite Earth Station filing.

IBFS_SESSTA2012062600616_957737

                                                                                 HNS License Sub, LLC
                                                                                  FCC Form 312 – STA
                                                                                     Narrative Exhibit
                                                                                             June 2012

                   REQUEST FOR SPECIAL TEMPORARY AUTHORITY
                                 Call Sign: E110149


         HNS License Sub, LLC (“Hughes”) hereby requests Special Temporary Authority

(“STA”) beginning on July 21, 2012, and continuing for 60 days thereafter (to September 19,

2012), to utilize one of the 8.1 meter earth station antennas authorized under Call Sign E110149,

and proposed in pending modification application File No. SES-MFS-20120426-00395, to

operate with the U.S.-licensed EchoStar XVII satellite at the 107.1º W.L. orbital location for in-

orbit testing (“IOT”) purposes. All operations under the requested STA will be conducted from a

single site in North Platte, Nebraska,1 and will be within the technical parameters specified for

the blanket-licensed 8.1 meter antennas on Hughes’s license under Call Sign E110149.

         Hughes has on file with the FCC a pending application for permanent authority to utilize

the antennas under Call Sign E110149 to communicate with EchoStar XVII (as licensed by the

Commission on June 12, 2012 in File No. SAT-LOA-20120422-00075). There are unresolved

interference issues with respect only to the 29.25-29.3 GHz frequency segment to be used at

various continental U.S. (“CONUS”) locations, as the frequency segment overlaps with spectrum

utilized by the Iridium mobile-satellite service system from a Tempe, Arizona earth station.

However, as the North Platte, Nebraska site for the earth station providing gateway service for

EchoStar XVII IOT is located 1309 kilometers away from the Tempe site, interference to Iridium

1
  In the event of a catastrophic failure at the North Platte earth station, Hughes would re-locate test
equipment and staff so as to conduct the IOT instead from the Amarillo, Texas (35° 12’ 18” North
latitude, 101 49’ 56” West longitude) station, which is 950 km from the Iridium hub in Tempe, Arizona.
If such were to occur, transmission would be discontinued entirely at the North Platte station. All
technical parameters for the IOT would remain the same, other than the change in testing location.
Authority is also sought for use of the Amarillo, Texas station in the event of such a catastrophic failure.


308258


is expected to be minimal.2 In any event, Hughes recognizes that its proposed operation under

this STA request is on a non-interfering basis. In the unlikely event that interference issues are

raised during IOT operations, Hughes is designating as a contact point Bill McHargue at its

Network Management Center in Germantown (Telephone: 301-428-7205). Mr. McHargue will

be available on a 24/7 basis to field any interference complaints and address any other technical

issues that may arise with the IOT operation.

         The underlying issue raised by Iridium will need to be addressed in one way or another

before Hughes can begin permanent use of the 29.25-29.3 GHz segment for its gateway

operations, but not for the limited operation from the single earth station that is requested here.

The Commission has determined that in-orbit testing of a newly-launched satellite constitutes

extraordinary circumstances that require temporary operations in the public interest. See

DirecTV Enterprises, LLC, DA 10-113, slip op. at 4 (Sat. Div., released January 21, 2010). IOT

authority is all that Hughes requests for the North Platte gateway earth station, and denying such

authority because of a pending objection that is inapposite to the proposed use would clearly be

contrary to the public interest. Moreover, the requested STA will serve the public interest by

ensuring that Hughes’ EchoStar XVII satellite, as launched, is tested to ensure that it fully

complies with the Commission grant and can begin to make productive use of the valuable

spectrum and orbital resources as soon as possible. Adding new Ka-band fixed-satellite service

capacity for the provision of commercial services to customers in the United States is very much

in the public interest.




2
  See ITU-R Recommendation S.1419, “Interference Mitigation Techniques to Facilitate Coordination
Between Non-GSO MSS Feeder Links and GSO FSS Networks in the bands 19.3-19.7 GHz and 29.1-
29.5 GHz” (recommending a separation distance of 225 km between typical transmitting earth stations
associated with the two services in order to avoid harmful interference).


308258


         Given the sensitivity of this proposed use of 29.25-29.3 GHz by one of the earth stations

authorized under Call Sign E110149, Hughes is submitting this STA request more than three

business days in advance of the date of requested first use. Because Hughes has not only a

pending application to access EchoStar XVII from the same antenna as a U.S.-licensed satellite,

but a license to use the very same type of earth station antenna to communicate with the exact

same satellite under a different flag for service to the United States, a 60-day term is appropriate.

See 47 C.F.R. § 25.120(b)(3).

         To avoid ex parte issues that result from the reference to the Iridium issues in File No.

SES-MFS-20120426-00395, Hughes will provide an electronic copy of the instant STA request

to Iridium.

         In sum, and in the event that the Commission has not resolved the pending issue of

potential interference to Iridium from the use of Hughes’s licensed gateway earth stations to

communicate with EchoStar XVII as a U.S.-licensed satellite prior to July 21, 2012, Hughes

respectfully requests authority to operate an 8.1 meter gateway antenna from North Platte,

Nebraska using all proposed frequencies on the licensed station – including the 29.25-29.3 GHz

band segment – for 60 days starting July 21, 2012 and ending on September 19, 2012.




308258