Attachment Petition to Deny

Petition to Deny

PETITION TO DENY submitted by Sprint Nextel

Petition to Deny

2008-04-04

This document pretains to SES-LIC-20071203-01646 for License on a Satellite Earth Station filing.

IBFS_SESLIC2007120301646_635795

In the Matter of                           )

Application of New IC0 Satellite           )      File Nos. SES-LIC-20071203-01646,
Services G.P. for Blanket Authority for    )      SES-AMD-20080118-00075, and
Ancillary Terrestrial Component Base       1      SES-AMD-200802 19-00172
Stations and Mobile Terminals for          )
2 GHz Mobile Satellite Service             1



               PETITION TO DENY OF SPRINT NEXTEL CORPORATION



                                     SPRINT NEXTEL CORPORATION

                                     Lawrence R. Krevor
                                     Vice President, Government Affairs - Spectrum

                                     Trey Hanbury
                                     Director, Government Affairs

                                     2001 Edmund Halley Drive
                                     Reston, VA 20 191
                                     (703) 433-4141



April 4,2008


                                            SUMMARY

       New I C 0 Satellite Services G.P. (ICO) seeks authority to operate an Ancillary Terrestrial

Component (ATC) network in the 2 GHz band in connection with its 2 GHz Mobile Satellite

Service (MSS) system. The Commission should deny ICO’s ATC application.

       I C 0 has failed to meet crucial gating criteria that are a prerequisite for ATC authorization

and has taken no steps to ensure that it will complete this requirement. If the MSS spectrum is

not cleared for MSS use, I C 0 cannot provide the national coverage it must offer as a prerequisite

to ATC authority. I C 0 will not have access to this spectrum unless it either relocates the

Broadcast Auxiliary Service (BAS) licensees from this band, or pays the debt it owes to Sprint

Nextel to perform this activity on its behalf as the Commission’s rules and policies require. I C 0

is seeking to evade both obligations, however. By failing to satisfy its band clearing obligations,

I C 0 is in no position to certify that it has the right to obtain lucrative ATC authority from the

Commission.

       The Commission should also deny ICO’s request for ATC authority because it will cause

a significant risk of interference to other licensees. I C 0 seeks a number of waivers of the

Commission’s technical rules. Its waiver requests would rewrite these rules entirely to

accommodate a service the Commission never considered at the time of the MSS ATC decision.

ICO’s proposed ATC authorization seems quite likely to interfere with scores of millions of

current cellular phone users. IC0 does not propose any interference-mitigation measures that

might protect incumbent operators against harmful interference, but instead proposes

significantly higher power operations and higher levels of out-of-band emissions than ever

contemplated by any of the current CMRS users that I C 0 uses as its benchmark for interference

protection. ICO’s proposed changes would significantly raise the levels of interference that


could be caused by MSS/ATC transmissions to a variety of Advanced Wireless Services and

Personal Communications Services that operate in neighboring bands. Therefore, the

Commission should deny ICO’s application for ATC authority.




                                              a .

                                              11


                                                    Table of Contents

I.     Introduction   .......................................................................................................................            1

11.    I C 0 Has Failed to Meet its Nationwide Coverage Gating Criteria and Has
       Taken No Steps to Ensure that this Obligation is Complete.                                          ........................................      2

111.   I C 0 Proposes Deviations from the Rules so Numerous and Extensive that
       They Will Greatly Increase the Likelihood of Harmful Interference                                                   ...........................   5

IV.    Grant of ICO’s ATC Application Will Cause Harmful Interference to Licensed
       and Operational Services and Diminish the Utility of Terrestrial Bands Slated
       for Competitive Bidding            ....................................................................................................           7

V.     Conclusion   ........................................................................................................................             10


                                              Before the
                        FEDERALCOMMUNICATIONS
                                          COMMISSION
                                      Washington, DC 20554


In the Matter of                                )
                                                )
Application of New IC0 Satellite                )       File Nos. SES-LIC-2007 1203-01646,
Services G.P. for Blanket Authority for         )       SES-AMD-20080118-00075, and
Ancillary Terrestrial Component Base            1       SES-AMD-200802 19-00172
Stations and Mobile Terminals for               1
2 GHz Mobile Satellite Service                  )


               PETITION TO DENY OF SPRINT NEXTEL CORPORATION

I.      Introduction

       New IC0 Satellite Services G.P. (ICO) seeks authority to operate an Ancillary Terrestrial

Component (ATC) network in the 2 GHz band in connection with its 2 GHz Mobile Satellite

Service (MSS) system. The Commission should deny ICO’s ATC application. First, IC0 has

failed to meet crucial gating criteria that are a prerequisite for ATC authorization and has taken

no steps to ensure that this requirement will be complete. Specifically, if the MSS spectrum is

not cleared for MSS use, IC0 cannot provide the national MSS coverage it must offer. Yet, IC0

has attempted to evade its band-clearing obligations by failing to relocate Broadcast Auxiliary

Service (BAS) licensees itself and also by seeking to avoid reimbursing Sprint Nextel

Corporation (Sprint Nextel) for ICO’s pro rata share of BAS relocation costs. By failing to

satisfy its band clearing obligations, IC0 is in no position to certify that it has the right to obtain

lucrative ATC authority from the Commission. Second, IC0 does not seek mere deviations from

the rules, but wants to rewrite the technical rules entirely to accommodate a service the

Commission never considered at the time of the MSS ATC decision. Third, ICO’s ATC

authorization seems quite likely to interfere with scores of millions of current cellular phone


users. I C 0 does not propose any interference-mitigation measures that might protect incumbent

operators against harmful interference, but instead proposes significantly higher power

operations than ever contemplated by any of the current CMRS users that I C 0 uses as its

benchmark for interference protection. Therefore, the Commission should deny ICO’s

application for ATC authority.

11.     I C 0 Has Failed to Meet its Nationwide Coverage Gating Criteria and Has Taken
        No Steps to Ensure that this Obligation is Complete.

        I C 0 cannot offer nationwide MSS coverage and has failed to take any steps to ensure that

it will be able to meet this gating criterion any time in the foreseeable future. Under Section

25.149 of the Commission’s rules, I C 0 cannot offer MSS ATC until it first demonstrates that its

“mobile-satellite service [is] commercially available . , . in accordance with the coverage

requirements that pertain to each band.”’ Licensees in the 2 GHz mobile-satellite service must

offer continuous nationwide service, including Puerto Rico and the Virgin Islands. To obtain

ATC authority, I C 0 need not demonstrate that its satellite is currently capable of operating

nationally, but it must - at a minimum - “demonstrate that r i g . . . will comply” with the

nationwide coverage requirement through certification or other means.2 I C 0 has wholly failed to

demonstrate how it will comply with a nationwide coverage requirement because the spectrum in

which it seeks to operate its satellite is not available nationally. I C 0 will not have access to the 2

GHz MSS spectrum unless it either relocates the BAS licensees from the spectrum its satellites

will occupy, or pays the debt it owes to Sprint Nextel to perform this activity on its behalf as the

Commission’s rules and policies require.




’ 47 C.F.R. 25.149(b).
 Id.


                                                   2


       ICO’s BAS relocation obligation is not subject to debate: IC0 bears an obligation to

either relocate eligible BAS facilities or reimburse Sprint Nextel for a portion of the cost of

doing so. The Commission has repeatedly stated that “both Sprint Nextel and 2 GHz MSS

licensees have equal obligations to relocate the 2 GHz BAS incumbent~.”~
                                                                       The Commission has

also affirmed that “the underlying relocation rules . . . established for MSS entrants to undertake

the relocation of BAS incumbents” remain ~nchanged.~
                                                  ICO, however, apparently has no

intention of itself performing any portion of the work associated with BAS relocation. IC0 has

done nothing to relocate BAS licensees - not a single relocation agreement signed, not a single

piece of equipment ordered, not a single BAS licensee relocated. Sprint Nextel has offered IC0

numerous ways in which it could participate in the BAS relocation already underway; however,

IC0 has refused. Most recently, Sprint Nextel proposed to enter a contractual agreement with




  See, e.g., Improving Public Safety Communications in the 800 MHz Band; Consolidating the
800 and 900 MHz IndustriaVLand Transportation and Business Pool Channels, Order, 23 FCC
Rcd. 575,12 (2008).
  Improving Public Safety Communications in the 800 MHz Band; Consolidating the 800 and
900 MHz IndustriaULand Transportation and Business Pool Channels, WT Docket No. 02-55,
Memorandum Opinion and Order and Further Notice of Proposed Rulemaking, FCC OS-73,2008
FCC LEXIS 1896,139 (rel. March 5,2008) (BAS Extension Order), citing Improving Public
Safety Communications in the 800 MHz Band; Consolidating the 800 and 900 MHz
Industrial/Land Transportation and Business Pool Channels, Report and Order, Fifth Report and
Order, Fourth Memorandum Opinion and Order, and Order, 19 FCC Rcd. 14969,T 250 (2004)
(800 MHz R&O), as amended by Erratum, WT Docket No. 02-55 (rel. Sep. 10,2004); Second
Erratum, 19 FCC Rcd. 19651 (2004) (subsequent history omitted). Specifically, prior to
beginning operations, IC0 must relocate (i) the BAS incumbents in the top thirty markets and (ii)
all fixed BAS links, regardless of market size. 47 C.F.R. 8 74.690(e)(l)(i). The Commission
recently stated that:
       As we noted in the 800 MHz R&O, ‘except as discussed below, those rules will
       remain in effect.’ At no place in our rules, the 800 MHz R&O, or subsequent
       orders have we stated that MSS was no longer obligated to relocate BAS in the
       top 30 markets and all fixed BAS prior to beginning operations.
BAS Extension Order 139 n. 118 (citations omitted).


                                                  3


IC0 that would have allowed the company to directly participate in the BAS relocation

framework that Sprint Nextel has established. IC0 has not responded.

       Given its failure to engage in any element of the BAS relocation process, ICO’s

certification under section 25.149 that ICO’s MSS satellite will offer nationwide coverage is not

credible. The Commission cannot accept ICO’s certification that it will meet its gating criteria in

this proceeding for the simple reason that I C 0 has clearly indicated that it will not comply with

its obligations to relocate BAS licensees - either by relocating them itselfor by paying itsfair

share of the relocation C O S ~ S .IC0
                                    ~  is not carrying its fair share of the burden of clearing BAS

incumbents, which is a prerequisite before it can offer nationwide MSS service. IC0 therefore is

in no position to certify that it is taking the steps necessary to satisfy its ATC gating criteria. The

band in which IC0 seeks to operate is not cleared and IC0 has done nothing to clear it.6

        Quite apart from the glaring inconsistencies in ICO’s own statements, allowing IC0 to

avoid its reimbursement obligations to Sprint Nextel has a direct bearing on the merits of ICO’s

application for ATC authority and its associated waiver requests. IC0 will use ATC services to

offer a variety of mass-market, wireless narrowband and broadband services and in doing so will

compete directly against Sprint Nextel for subscribers and revenue. Allowing IC0 to escape its

BAS reimbursement obligations would artificially and unfairly lower its costs of deploying its


  On February 4,2008, Sprint Nextel sent a letter to IC0 regarding its pro rata share of BAS
relocation expenses. In this letter, Sprint Nextel provided IC0 with an initial interim billing
estimate for ICO’s pro rata reimbursement obligation, and in good faith proposed a meeting
between the companies’ respective business and finance teams to ensure a timely payment. In a
February 12, 2008 letter to Sprint Nextel, however, IC0 stated that it is “impossible to know’’
whether or when MSS licensees must reimburse Sprint Nextel, notwithstanding the clear
findings to the contrary in the Commission’s orders.
 IC0 suggests in a footnote it may seek a waiver of this crucial gating requirement “at a later
date” if the BAS transition is not complete. See “Description of IC0 MSS/ATC Services and
Public Interest Benefits,” attached as Exhibit 1 to IBFS File No. SES-AMD-20080118-00075, at
8 n. 17 (Jan. 18, 2008) (“IC0 Application Description”).


                                                  4


terrestrial services by at least $100 million and at the same time improperly impose at least a

$100 million surcharge on Sprint Nextel’s ability to provide competing terrestrial wireless

services. The Commission has previously recognized that allowing a late-entering carrier to

avoid reimbursing the earlier-entering spectrum clearing carrier would create an unfair and

impermissible competitive ad~antage.~
                                   The Commission can prevent this anti-competitive

outcome by denying ICO’s ATC authority unless and until IC0 meet its pro rata payment

obligation for BAS relocation.

111.   I C 0 Proposes Deviations from the Rules so Numerous and Extensive that They Will
       Greatly Increase the Likelihood of Harmful Interference.

       IC0 does not seek minor changes or deviations from the complex and inter-related

interference protections, but instead wants to rewrite the rules in their entirety. For example,

ICO’s proposed change section 25.252(a)( 1) represents a 33.6 dB relaxation from the current

rule, and would permit out-of-band emissions from ATC base stations 2290 times stronger than

is currently permitted.* IC0 also proposes an almost four-fold increase in base station power.’

In addition, IC0 proposes a doubling of the mobile power, and a five-fold or more increase in




  Amendment to the Commission’s Rules Regarding a Plan for Sharing the Costs of Microwave
Relocation, Memorandum Opinion and Order on Reconsideration, 15 FCC Rcd. 13999,l 16
(2000) (finding that later-entrants that benefit from the clearance of spectrum by a first entrant
would receive a “significant competitive advantage” if they were not required to reimburse the
first entrant for a share of the relocation costs).
‘Section 25.252(a)(l) limits ATC base station out-of-channel emissions to -100.6 dBW/4 kHz.
When adjusted to the one megahertz measurement bandwidth IC0 is requesting, the current limit
is equivalent to -76.6 dBW/l MHz.
’Section 25.252(a)(2) limits ATC base station power to a peak EIRP of 27 dBW in a 1.23 MHz
bandwidth. When adjusted to the one megahertz measurement bandwidth IC0 is requesting, the
current limit is equivalent to 26.1 dBW/l MHz. ICO’s request for a base station power limit of
32 dBW/l MHz is a 5.9 dB, or almost four-fold, increase to the current limit.


                                                 5


power for non-mobile user devices. l o Furthermore, I C 0 proposes to relax the out-of-band

emissions from both base stations and users devices by as much as 13 dB in the first 1 MHz

                               ’
outside their frequency block.’ ICO’ s proposed system architecture represents a radical

departure from the cdma2000 architecture on which the Commission sought and received public

comment and for which the Commission conducted extensive interference analysis when it

adopted the ATC rules.

       The changes that I C 0 has sought produce significantly greater potential interference that

the current rules allow. Although the Commission’s rules permit applicants to apply for systems

other than cdma2000, the Commission’s rules stipulate that any proposed changes must “produce

no greater potential interference” than permitted under the current rules.12 Each of ICO’s

proposed changes - permitting 2290 times as much out-of-band emissions, relaxing emissions by



lo Section 25.252(b)(l) limits the power of mobile terminals to 1.O dBW in a 1.23 MHz
bandwidth. When adjusted to the one megahertz measurement bandwidth I C 0 is requesting, the
current limit is equivalent to 0.1 dBW/l MHz. The 2 watt limit (3 dBW/l MHz) power limit
proposed by I C 0 is 2.9 dB, or 1.95 times, higher than the current limit. ICO’s proposed 2 watt
transmitter power limit for non-mobile devices would result in a 7.9 dB (or 6.2 times) increase in
power if a 5 dB gain antenna is used, assuming no loss in the antenna feeder line. If an even
higher gain antenna were used, the increase in power would be even more significant.
’’ Section 25.252(~)(4)currently specifies that measurements be made using measurement
instrumentation employing a resolution bandwidth of one megahertz or greater. I C 0 requests
that “in the 1 MHz bands immediately outside and adjacent to the frequency block a resolution
bandwidth of at least one percent of the emission bandwidth of the fundamental emission of the
transmitter may be employed. A narrower resolution bandwidth is permitted in all cases to
improve measurement accuracy provided the measured power is integrated over the full required
measurement bandwidth ( i e . 1 MHz or 1 percent of emission bandwidth, as specified).” I C 0
Application Description at 18,27. If I C 0 were to employ a five megahertz wide signal, then
compliance would need to be demonstrated in a 50 kHz bandwidth. This would result in a 13 dB
(or twenty-fold) relaxation in the out-of-band limits in this adjacent spectrum.
l 2 47 CFR 25.252, Note 1 (“The preceding rules of 525.252 are based on cdma2000 system
architecture. To the extent that a 2 GHz MSS licensee is able to demonstrate that the use of a
different system architecture would produce no greater potential interference than that produced
as a result of implementing the rules of this section, an MSS licensee is permitted to apply for
ATC authorization based on another system architecture.”).


                                                6


33.6 dB, increasing base station power by four-fold, and more - greatly increases the likelihood

of harmful interference. Therefore, ICO’s request does not comply with the express language of

section 25.252 and is inappropriate for waiver.

1V.    Grant of ICO’s ATC Application Will Cause Harmful Interference to Licensed and
       Operational Services and Diminish the Utility of Terrestrial Bands Slated for
       Competitive Bidding.

       IC0 proposes a number of changes that would increase the permitted power and out-of-

band emissions from MSS ATC devices. These changes would significantly raise the levels of

interference that could be caused by MSS/ATC transmissions to a variety of Advanced Wireless

Services (AWS) and Personal Communications Services (PCS) that operate in neighboring bands.

Of particular concern in this regard is ICO’s proposal to permit non-mobile user stations to

transmit with transmitter power levels of 2 watts, without a limit on the antenna gain or EIRP of

those stations. Neither the PCS nor AWS rules currently permit higher power levels for non-

mobile user stations. l 3 Furthermore, this increased limit would result in widespread interference

to mobile receivers operating in the H-block (1995-2000 MHz), G-block (1990- 1995 MHz), and

PCS (1930-1990 MHz) bands. The proximity of the frequencies used by MSS/ATC mobile

transmitters (2000-2020 MHz) to these other services - combined with a large installed base of

equipment that can tolerate little unpredicted interference - is critical. There is a significant

record in several proceedings about the consequences that can occur when user transmitters are




l 3 Section 24.232(c), as modified in 2008, limits mobile/portable broadband PCS stations to 2
watts EIRP power. See Biennial Regulatory Review -Amendment of Parts 1, 22, 24, 27 and 90
to Streamline and Harmonize Various Rules Affecting Wireless Radio Services, WT Docket No.
03-264, FCC 08-85 (rel. Mar. 21, 2008). Section 27.50(d)(4) limits fixed, mobile, and portable
(hand-held) stations operating in the AWS-1 (1710-1755 MHz band) to 1 watt EIRP. A power
limit for non-mobile user stations similar to that proposed by IC0 is contained in the BRS/EBS
rules, Section 27SO(h)(2); however, this applies in a band much higher in frequency and with
many different characteristics and service requirements.


                                                  7


located in spectrum near to that being used by mobile    receiver^.'^   Without appropriate

safeguards that Sprint Nextel and others have proposed to protect against harmful interference in

other bands, such as tighter out-of-band emissions, or reductions in the transmitter power,

interference can occur when user transmitters are located near other mobile receivers. This

interference can occur in two ways: as a result of out-of-band emissions from the user devices

into the mobile receivers, and as a result of receiver overload of mobile receivers simply because

of the presence of strong signals in an adjacent band.

       ICO’s proposed power increase for non-mobile devices threatens to cause widespread

receiver overload interference to H-block, G-block, and PCS mobile receivers. The distances at

which such receiver overload can occur has been the matter of significant debate; however, in no

case has a party in those proceedings proposed to permit the user devices to transmit with more

than the 2 watts specified in current broadband PCS ruled5 ICO’s proposal, however, would

permit potentially one million user terminals to operate with EIRP power levels many times in

excess of the two watt limit contemplated - and hotly debated - in other bands. ICO’s pursuit of

a greater than 2 watt EIRP means that the distance at which mobile receiver overload could occur,

and the frequency at which it would occur, is significantly greater than any of that predicted in




l 4 See, e.g., Service Rules for Advanced Wireless Services in the 2155-21 75 MHz Band, Notice of
Proposed Rulemaking, 22 FCC Rcd. 17035,yfi 16-20,60, 66 (considering technical rules for
operations in AWS-3 band); Advanced Wireless Services in the 1915-1920 MHz, 1995-2000
MHz, 2020-2025 MHz and 21 75-2180 MHz Bands, Notice of Proposed Rulemaking, 19 FCC
Rcd. 19263,T[fi89-92 (2004) (considering technical rules for operations in the “H block” at
1915-1920 MHdl995-2000 MHz); Spectrum and Service Rules for Ancillary Terrestrial
Components in the 1.6i2.4 GHz Big LEO Bands; Review of the Spectrum Sharing Plan Among
Non-Geostationary Satellite Orbit Mobile Satellite Service Systems in the 1.6i2.4 GHz Bands, IB
Docket Nos. 07-253 and 02-364, RM-11339, Second Order on Reconsideration, Second Report
and Order, and Notice of Proposed Rulemaking, 22 FCC Rcd. 19733 (2007).
  In many cases, parties have proposed power limits significantly less than 2 watts.


                                                 8


the other proceedings. At risk are scores of millions of PCS consumers with handsets not

designed to expect such high-powered signals in the adjacent frequency bands.

       ICO’s interference study suggesting that these sweeping changes are of no moment is

flawed in several material ways. I C 0 ignores the increase in interference its proposed changes

would cause to the tens or hundreds of millions of consumers that occupy adjacent bands, and

instead compares the interference its proposed operations will create with the interference that is

permitted between other services not yet deployed. I C 0 sets the bar artificially low, which is

neither appropriate nor accurate. For example, I C 0 - in analyzing the impact of its user device

transmissions at 2000-2020 MHz towards the H-block, G-block, and PCS mobile receivers - has

completely ignored the issue of mobile receiver overload that can occur when these devices are

located nearby. I C 0 has compared the interference its out-of-band emissions would cause to

those caused under the Commission’s rules between PCS devices; however, the PCS industry has

recognized that those rules are not sufficient to avoid interference and has imposed much tighter

out-of-band emissions limits on a voluntary basis. As a result, ICO’s assumption that no

interference would occur if they comply with rules similar to PCS and AWS is faulty.




                                                 9


V.     Conclusion

       To protect competition, ensure compliance with the Commission’s cost sharing policies

and prevent harmful interference to existing and planned terrestrial operations, the Commission

should deny ICO’s ATC application and its associated waiver requests.

                                     Respectfully submitted,

                                     SPRINT NEXTEL CORPORATION

                                                      82
                                     Lawrence R. Krevor
                                      Vice President, Government Affairs - Spectrum
                                     Trey Hanbury
                                      Director, Government Affairs
                                     2001 Edmund Halley Drive
                                     Reston, VA 20 191
                                     (703) 433-4141

April 4,2008




                                               10


                                           Declaration

        I declare under penalty of perjury that the technical and engineering information
contained in the foregoing Petition to Deny of Sprint Nextel Corporation is true and correct to
the best of my personal knowledge and belief.


Executed on April 4,2008                             /I




                                             Richard B. Engelman
                                             Director, Speckurn Resources
                                             Government Affairs
                                             Sprint Nextel Corporation


                                       Certificate of Service

         I, Ruth E. Holder, hereby certify that on this 4th day of April, 2008, I caused true and
correct copies of the foregoing Petition to Deny of Sprint Nextel Corporation to be mailed by
first class U.S. mail, postage prepaid, to:

                       Cheryl A. Tritt
                       Morrison & Foerster
                       2000 Pennsylvania Ave. NW, Suite 500
                       Washington, DC 20006

                       Dennis Schmitt
                       New IC0 Satellite Services G.P
                       2300 Carillon Point
                       Kirkland, WA 98033




                                                                     I

                                              Ruth E. Holder



Document Created: 2008-04-16 12:36:25
Document Modified: 2008-04-16 12:36:25

© 2024 FCC.report
This site is not affiliated with or endorsed by the FCC