Attachment Petition to Deny

Petition to Deny

PETITION TO DENY submitted by Sprint Nextel

Petiton to Deny of Spring Nextel Corporation

2008-04-25

This document pretains to SES-AMD-20070723-00978 for Amended Filing on a Satellite Earth Station filing.

IBFS_SESAMD2007072300978_636987

                                             Before the  FILED/ACCEPTED
                                   COMMUNICATIONS
                             FEDERAL          COMMISSION     APR 2 5 2008
                                     Washington, DC 20554                            Federal Communications Commission
                                                                                            Office of the Secretary
In the Matter of                               1
                                               1
Application of TerreStar Networks Inc.         )       File Nos. SES-LIC-20061206-02 100,
for Blanket Authority for Ancillary            )       SES-AMD-20070723-00978,
Terrestrial Component Base                     1       SES-AMD-20070907-01253, and
Stations and Mobile Terminals for              )       SES-AMD-20080229-002 17
2 GHz Mobile Satellite Service                 )

                  PETITION TO DENY OF SPRINT NEXTEL CORPORATION

I.       Introduction

         TerreStar Networks Inc. (TerreStar) seeks authority to operate an Ancillary Terrestrial

Component (ATC) network in the 2 GHz band in connection with its 2 GHz Mobile Satellite

Service (MSS) system. The Commission should deny TerreStar’s ATC application. TerreStar

cannot obtain ATC authority unless it demonstrates that it will offer commercial MSS, and

TerreStar cannot offer MSS until it shows that it will either relocate 2 GHz Broadcast Auxiliary

Service (BAS) itself or pay its fair share of the relocation costs. Unless TerreStar certifies that it

will satisfy these conditions by either relocating BAS or certifying that it will reimburse Sprint

Nextel Corporation (Sprint Nextel) for TerreStar’s pro rata share of eligible BAS relocation

costs Sprint Nextel has incurred during the transition, Terrestar has failed to satisfy the minimum

criteria necessary to receive ATC authority and Terrestar’s ATC application must be denied.

11.      TerreStar Cannot Satisfy the Commission’s ATC Gating Criteria Without
         Complying with Its BAS Relocation and Reimbursement Obligations.

         The Commission established a number of gating factors that TerreStar must satisfy before

it can be authorized to provide ATC service.’ Among other things, TerreStar must show that it



’    47 C.F.R.   0 25.149.


will offer commercial MSS as a prerequisite to receiving ATC authority. The Commission’s

rules provide:

       MSS operators’ ability to offer ATC service is tied to their ability to offer satellite
       service. Specifically, section 25.149 of the Commission’s rules places several
       conditions on 2 GHz MSS systems that provide ATC services, including:
       (a) providing space segment service covering all 50 states, Puerto Rico and the
       U.S. Virgin Islands one-hundred percent of the time, unless it is not technically
       possible, and (b) offering MSS for a fee (i.e., commercially available) in
       accordance with the coverage requirements that pertain to each band as a
       prerequisite to offering ATC service.2

According to the Commission, this rule requires that “an eligible MSS licensee that wishes to

implement ATC must provide space-segment service across the entire geographic area stipulated

in our rules and policies for that operator’s particular space-station system geometry and

fi-equencyband.”3 In this case, however, TerreStar cannot provide satellite service to the entire

United States until it either relocates incumbent BAS licensees to the new 2 GHz band plan or

pays its fair share of the cost of this relocation. TerreStar has not demonstrated that it will satisfy

these BAS conditions; therefore, TerreStar has failed to demonstrate that it has satisfied the

Commission’s gating requirements for receiving ATC authority.

       MSS licensees may not commence satellite service until they have relocated all BAS

licensees in the top 30 markets and all fixed BAS links in all   market^.^   The Commission has

held that “both Sprint Nextel and 2 GHz MSS licensees have equal obligations to relocate the 2




   Improving Public Safety Communications in the 800 MHz Band; Consolidating the 800 and
900 MHz Industrial/Land Transportation and Business Pool Channels, WT Docket No. 02-55,
Memorandum Opinion and Order and Further Notice of Proposed Rulemaking, FCC OS-73,2008
FCC LEXIS lS96,15 1 (rel. March 5,2008) (BAS Extension Order);see also 47 C.F.R.
0 25.149(b).
  Flexibility for Delivery of Communications by Mobile Satellite Service Providers, Report and
Order and Notice of Proposed Rulemaking, 18 FCC Rcd. 1962,175 (2003).
  47 C.F.R. 0 74.690(e)( l)(i).


                                                 -2-


GHz BAS incumbent^."^ TerreStar, however, has done nothing to relocate BAS incumbents.

Since it received its MSS authorization in 2001, TerreStar has not inventoried a single

broadcaster television station. TerreStar has not negotiated a single relocation agreement. Nor

has TerreStar provided an incumbent with a single piece of new electronic newsgathering

equipment. TerreStar has, in fact, taken no action whatsoever to clear the spectrum it intends to

use of the electronic newsgathering operations that currently occupy the space.

       Moreover, TerreStar also has informed Sprint Nextel that it will not satisfy its obligation

to pay TerreStar’spro rata share of eligible BAS relocation costs,‘ which Sprint Nextel has

estimated at approximately $100 m i l l i ~ n .The
                                                ~ Commission must require TerreStar to meet this

obligation. First, TerreStar must pay its fair share of eligible BAS relocation expenses under

well-established cost-sharing policies that have applied to relocation projects since 1993.8 As



’ Improving Public Safety Communications in the 800 MHz Band; Consolidating the 800 and
900 MHz IndustriaULand Transportation and Business Pool Channels, Order, 23 FCC Rcd. 575,
7 2 (2008).
‘ See infra section III.
   Because TerreStar will occupy 10 megahertz of the 35 megahertz of cleared BAS spectrum,
TerreStar is liable for apro rata, two-sevenths share or 28.57% (10 MHz / 35 MHz) of Sprint
Nextel’s eligible BAS relocation costs. See, e.g., Improving Public Safety Communications in
the 800 MHz Band; Consolidating the 800 and 900 MHz IndustriaLLand Transportation and
Business Pool Channels, Memorandum Opinion and Order, 20 FCC Rcd. 16015 , l 111 (2005)
(800 MHz MO&O). On March 7,2006, Sprint Nextel provided notice of its intent to seek
reimbursement from 2 GHz MSS licensees, including TerreStar. See Letter fi-om Lawrence R.
Krevor, Sprint Nextel Corporation, to Marlene H. Dortch, Federal Communications Commission,
WT Docket No. 02-55 (March 7,2006).
*  See Redevelopment of Spectrum to Encourage Innovation in the Use of New
Telecommunications Technologies, ET Docket No. 92-9, First Report and Order and Third
Notice of Proposed Rulemaking, 7 FCC Rcd. 6886,l 24 (1 992); Third Report and Order and
Memorandum Opinion and Order, 8 FCC Rcd. 6589, T[ 2 (1993); Memorandum Opinion and
Order, 9 FCC Rcd. 1943,73 (1 994); Second Memorandum Opinion and Order, 9 FCC Rcd.
7797, 7 4 (1994), afld sub nom. Association of Public Safety Communications Oficials-
International, Inc. v. FCC, 76 F.3d 395 (D.C. Cir. 1996); see also 800 MHz MO&O, 20 FCC
Rcd. 16015,T 111; Improving Public Safety Communications in the 800 MHz Band;
Consolidating the 800 and 900 MHz IndustriaVLand Transportation and Business Pool


                                               -3-


explained in detail in Section I11 below, TerreStar’s rejection of its reimbursement obligation errs

on the facts, disregards its own delayed implementation, and fails to account for the need to

revise the 800 MHz true-up schedule.

        Second, TerreStar’s license is expressly conditioned upon TerreStar reimbursing the

parties paying for relocation a fair share of BAS relocation expenses. In 2000, the Commission

conditioned 2 GHz MSS licenses on licensees bearing their fair share of BAS relocation costs.

Specifically, the Commission stated that “[a111 MSS licensees who benefit from relocation of

BAS are responsible for contributing [to BAS relocation], as a condition of their licenses,” and

indicated further that “[s]ubsequently entering MSS licensees in Phase I spectrum will, as a

condition of their licenses, compensate the first entrant on apro rata basis, according to the

amount of spectrum the subsequently entering licensees are authorized to use.”’ This condition

remains in full force and effect. Indeed, the Commission earlier this year affirmed that “the

underlying relocation rules . . . established for MSS entrants to undertake the relocation of BAS

incumbents” remain unchanged. l o



Channels, Report and Order, Fifth Report and Order, Fourth Memorandum Opinion and Order,
and Order, 19 FCC Rcd. 14969,1261 (2004) (800 MHz R&U), as amended by Erratum, WT
Docket No. 02-55 (rel. Sep. 10, 2004); Second Erratum, 19 FCC Rcd. 19651 (2004) (subsequent
history omitted) .
’ Amendment of Section 2.106 of the Commission’s Rules to Allocate Spectrum at 2 GHzfor
Use by the Mobile-Satellite Sewice, Second Report and Order and Second Memorandum
Opinion and Order, 15 FCC Rcd. 123 15, nT 69, 71 (2000) ( 2 GHz Allocation 2d R&U) (emphasis
added); see also TMI Communications and Company, Limited Partnership, Order, 16 FCC Rcd.
13808,17 n.23 (Int’l Bur. 2001) (granting MSS license now held by TerreStar and stating that
TerreStar’s system “must be implemented” in accordance with the 2 GHz Allocation 2d R&U
establishing BAS relocation and cost-sharing policies). The Commission’s 2000 order
specifically addressed cost-sharing among MSS licensees, given that the Commission did not
contemplate Sprint Nextel’s involvement in BAS relocation until 2004. There is no basis,
however, for not applying these same cost-sharing principles and MSS license conditions to
TerreStar’s reimbursement obligation to Sprint Nextel.
lo   BASExtension Order, FCC 08-73, 7 39, citing 800MHz R&U, 19 FCC Rcd. 14969,n 250.


                                                -4-


          TerreStar cannot shirk both its relocation obligations and its obligation to reimburse

Sprint Nextel, while at the same time certify that it will commence MSS to satisfy the

Commission’s ATC gating factors. Under the Commission’s rules and the terms of its license,

TerreStar may not offer commercial MSS service if it fails to comply with its BAS

relocatiodreimbursement obligations. Until it demonstrates that it will comply with these

obligations, it cannot be granted ATC authority.

          Aside from TerreStar’s failure to satisfy the ATC gating requirements, granting TerreStar

ATC authority without requiring it to adhere to its BAS relocation obligations would undermine

the Commission’s competition policies. TerreStar indicates that it will use its MSS ATC

network to provide mobile telecommunications services throughout the United States across the

government, commercial, and consumer segments, and it has acknowledged it will be competing

against Sprint Nextel and other existing wireless operators.’ Allowing TerreStar to escape its

BAS reimbursement obligations would artificially and unfairly lower its costs of deploying its

terrestrial services by at least $100 million and at the same time improperly impose at least a

$100 million surcharge on Sprint Nextel’s ability to provide competing terrestrial wireless

services. Significantly, the Commission has found that later entrants that benefit from the

clearance of spectrum by a first entrant would receive a “significant competitive advantage” if

they were not required to reimburse the first entrant for a share of the relocation costs.12 In order

to ensure a level playing field and prevent TerreStar from gaining an unfair competitive

advantage contrary to the Commission’s cost-sharing and competition policies, the Commission



11
     TerreStar Corp., Annual Report (Form 10-K), at 2-4, 11,29 (March 3 1,2008).
I 2 Amendment to the Commission’s Rules Regarding a Plan for Sharing the Costs of Microwave
Relocation, Memorandum Opinion and Order on Reconsideration, 15 FCC Rcd. 13999,l 16
(2000).


                                                  -5-


should deny TerreStar’s ATC authority unless and until TerreStar satisfies its pro rata payment

obligation for BAS rel~cation.’~

111.   TerreStar Has No Basis for Avoiding Its BAS Reimbursement Obligations.

       On February 4,2008, Sprint Nextel sent a letter to TerreStar regarding itspro rata share

of BAS relocation expenses. In this letter, Sprint Nextel provided TerreStar with an initial

interim billing estimate for TerreStar’s pro rata reimbursement obligation, and in good faith

proposed a meeting between the companies’ respective business and finance teams to ensure a

timely payment. In a February 11, 2008 letter to Sprint Nextel, however, TerreStar claimed that

it is not required to pay its fair share of BAS relocation costs because it allegedly will not enter

the 2 GHz band by June 26,2008, the previously projected date for the end of 800 MHz band

reconfiguration and the commencement of the 800 MHz true-up process.

       The Commission should not allow TerreStar to avoid both its obligation to relocate BAS

licensees and its obligation to bear its fair share of the cost of BAS relocation. TerreStar’s

refusal to pay its share of BAS relocation costs is wrong on the facts, ignores its own delays in

implementing its satellite operations, disregards the need to adjust the 800 MHz true-up schedule,

and is contrary to the Commission’s well-settled cost-sharing principles.

l 3 Like New IC0 Satellite Services G.P. (ICO), TerreStar seeks various technical rule waivcrs to
operate ATC. Unlike the sweeping rule changes that IC0 seeks, however, the technical
deviations that TerreStar has sought to implement thus f a r appear unlikely to materially increase
the risk of interference to adjacent channel licensees. To take but one example, TerreStar has
requested a 5 dB increase in base station power, but would measure signal strength over the full
bandwidth of the five-megahertz-wide UMTS/WCDMA signal that it intends to use. By
comparison, IC0 has sought both a 5 dB increase in power and a narrower measurement
bandwidth. Whereas Terrestar’s technical deviations would not make the status quo any worse,
ICO’s proposal would result in a four-fold increase of approximately 5.9 dB in overall power and
a corresponding increase in potential overload for adjacent-channel base station receivers. See
Petition to Deny of Sprint Nextel Corporation, File Nos. SES-LIC-20071203-01646, SES-AMD-
200801 18-00075, and SES-AMD-20080219-00172, at 5 n. 9 (Apr. 4,2006). Sprint Nextel,
therefore, has opposed ICO’s multiple technical rule waiver requests, but does not contest the
technical rule waivers proposed by Terrestar to date.


                                                 -6-


         TerreStar ’s Commencement ofATC Testing. Contrary to its claims, TerreStar has already

triggered its pro rata BAS reimbursement obligation. In its 2005 800 MHz MO&O, the

Commission stated that Sprint Nextel can seek pro rata reimbursement from MSS licensees that

“commence operation” anytime prior to the 800 MHz true-up.14 Over the past six months,

TerreStar has apparently undertaken build-out and testing of ATC facilities pursuant to section

25.143Cj) of the Commission’s ruled5 Just as the Commission recently ruled that the

“occurrence of transmissions” between a 2 GHz MSS satellite and an authorized earth station

constitutes an MSS licensee’s “operations,”” TerreStar’s ATC test transmissions represent

TerreStar’s “commencement of operation[ SI’’ and the triggering event for its pro rata payment

requirement.

         TerreStar ’sDelavs in Implementinn MSS Operations. Even if TerreStar had not already

commenced ATC testing and operations, the Commission should not allow TerreStar to escape

its BAS reimbursement obligation - at Sprint Nextel’s expense - based simply on TerreStar’s

delays in implementing its MSS system. The Commission originally required that this system be

launched by July 2006 and operational by July 2007, but TMI, TerreStar’s predecessor, failed to




l4   800MHz MO&O, 20 FCC Rcd. 16015,1109 (emphasis added).
l5  Under section 25.143(j), the holder of a 2 GHz MSS satellite license may engage in pre-
operational build-out and equipment tests to ensure compliance with the technical provisions of
its MSS authorization, ATC operational requirements, Part 25 rules and regulations, and
applicable engineering standards. 47 C.F.R. 0 25.143Cj); Flexibility for Delivery of
Communications by Mobile Satellite Service Providers, Order on Reconsideration, 18 FCC Rcd.
13590,T 13 (2003). On September 7,2007, TerreStar filed its required notice regarding these
ATC operations, indicating its intent to move forward with this construction and testing on or
after September 15, 2007. Letter from Joseph Godles, Counsel for TerreStar Networks Inc., to
Marlene Dortch, Secretary, FCC, File Nos. SAT-LOI- 19970926-0016 1, SAT-ASG-2002 1211-
00238, SAT-AMD-20061127-00143, and SAT-MOD-20070529-00075 (Sep. 7,2007).
l6   BAS Extension Order, FCC 08-73, T[ 48.


                                              -7-


meet its July 2002 construction contract mile~tone.’~
                                                   The Commission subsequently waived the

2002 milestone, reinstated TMI’s license, and established new launch and operational milestones

of November 2007 and November 2008, respectively.18 In October 2007, the Commission

granted yet another extension, providing TerreStar an extra ten months to launch its satellite. l 9

Had TMUTerreStar complied with either the original or even the extended milestones, TerreStar

would by now have “commenced operations” and it would have had to comply with its

relocation obligations by either clearing BAS licensees itself or fulfilling its BAS reimbursement

obligation. Allowing TerreStar to use its extensive delays in implementing its satellite

operations as an excuse to avoid paying its fair share of BAS relocation costs would be arbitrary,

unfair, and legally unsustainable.

         The True- Up Schedule and the Commission ’s Cost-Sharing Principles. Putting aside

Terrestar’s ongoing ATC operations and its delays in implementing its mobile-satellite service,

circumstances have changed since the Commission established the original June 26,2008 cut-off

date for MSS reimbursement obligations. As the Commission recently recognized, BAS

relocation has proven to be far more complex than originally anticipated and, for reasons beyond

Sprint Nextel’s control, the BAS transition will take longer to complete, with a large portion of

the relocation costs incurred after June 26, 2008, which was the original date for a true-up

accounting of 800 MHz expenses. Based on this finding, the Commission extended Sprint




l7 TMI Communications and Company, Limited Partnership, Order, 16 FCC Rcd. 13808,l 24
(Int’l Bur. 200 1); TMI Communications and Company, Limited Partnership, Memorandum
Opinion and Order, 18 FCC Rcd. 1725,l 1 (Int’l Bur. 2003).
     TMI Communications and Company, Limited Partnership, Memorandum Opinion and Order,
19 FCC Rcd. 12603,7l57,59 (2004).
l9 TerreStar Networks, Inc. Request for Milestone Extension, Memorandum Opinion and Order,
22 FCC Rcd. 17698,l 1 (Int’l Bur. 2007).


                                                 -8-


Nextel’s deadline for relocating BAS licensees to March 5, 2009.20 The Commission

consequently will need to adjust the current 800 MHz/BAS retuning true-up and reimbursement

schedule to be consistent with the BAS Extension Order as well as developments in the 800 MHz

reconfiguration process.21 Though TerreStar might prefer never to have to bear its pro rata share

of eligible BAS relocation costs through the completion of the BAS relocation process,

readjusting the date for reconciling expenses simply accounts for the reality of an inordinately

complex BAS relocation process.

         The Commission established a June 26,2008 cut-off date for MSS reimbursement

obligations not to award an enormous economic windfall to the 2 GHz MSS licensees, but to

promote “administrative efficiency” related to the true-up “accounting process” and avoid any

possible double-counting of reimbursement payments.22 The obligation of the MSS licensees to

reimburse Sprint Nextel for their fair share of BAS relocation expenses is based on the bedrock

principle that new entrants into reallocated spectrum must share the cost of relocating incumbent

licensees.23 Adhering to a June 26,2008 cut-off date when circumstances have changed would

violate this well-settled principle and arbitrarily grant TerreStar a windfall at Sprint Nextel’s

expense. TerreStar’s predecessor, TMI, recognized that “equity requires” that entities that

benefit from the clearing of BAS licensees “should . . . share in the financial burdens of the




2o   BAS Extension Order, FCC 08-73,129.
21 In addition, more than five hundred 800 MHz public safety incumbents are seeking waivers of
the original June 26,2008 deadline for completing this project. Assuming the Commission
grants these waiver requests in whole or in part, revision of the true-up process will be required.
Sprint Nextel will file a letter with the Commission describing several adjustments that will need
to be made to the true-up and other reconfiguration processes.
22   800 MHz MO&O, 20 FCC Rcd. 16015,1113.
23   See supra note 8.


                                                 -9-


relocation of [these]   licensee^."^^ These same principles of equity require TerreStar to pay its
fair share of BAS relocation costs.

IV.    Conclusion

       The Commission should deny TerreStar’s ATC application because TerreStar cannot and

will not offer a nationwide commercial mobile-satellite service unless it relocates the nation’s

BAS licensees or reimburses Sprint Nextel for the cost of doing so.

                                        Respectfully submitted,

                                        SPRINT NEXTEL CORPORATION

                                                                     4/ddnwhL!!
                                       Iatvrence R. a e v o r
                                         Vice President, Government Affairs - Spectrum
                                        Trey Hanbury
                                         Director, Government Affairs
                                        2001 Edmund Halley Drive
                                        Reston, VA 201 91
                                        (703) 433-4141

Regina M. Keeney
Charles W. Logan
Stephen J. Berman
Lawler, Metzger, Milkman & Keeney, LLC
2001 K Street NW, Suite 802
Washington, DC 20006
(202) 777-7700
Counsel to Sprint Nextel Corporation


April 25,2008




24Comments of TMI Communications and Company, L.P., ET Docket No. 95-18, at 2, 7 (Feb. 3,
1999).


                                                 - 10-


                                           Declaration

       I declare under penalty of perjury that the information contained in the foregoing Petition
to Deny of Sprint Nextel Corporation is true and correct to the best of my personal knowledge
and belief.


Executed on April 25,2008
                                                                  /

                                                          d
                                             TreyHanbufy
                                             Director, Government Affairs
                                             Sprint Nextel Corporation


                                       Certificate of Service

         I, Ruth E. Holder, hereby certify that on this 25th day of April, 2008, I caused true and
correct copies of the foregoing Petition to Deny of Sprint Nextel Corporation to be mailed by
first class U.S. mail, postage prepaid, to:

                       Joseph A. Godles
                       Goldberg, Godles, Wiener & Wright
                       1229 19th Street NW
                       Washington, DC 20036

                       Douglas I. Brandon
                       Vice President, Regulatory Affairs
                       TerreStar Networks Inc.
                       12010 Sunset Hills Road, 9th Floor
                       Reston, VA 20190




                                              Ruth E. Holder
                                                                    &dlk



Document Created: 2008-04-28 13:10:57
Document Modified: 2008-04-28 13:10:57

© 2024 FCC.report
This site is not affiliated with or endorsed by the FCC