Attachment Presentation to NOAA

This document pretains to SAT-STA-20101202-00250 for Special Temporal Authority on a Satellite Space Stations filing.

IBFS_SATSTA2010120200250_854478

OrbView‐3 De‐Orbit

       November 1, 2010

          Bill Schuster
 Chief Operating Officer, GeoEye




                1


                         Agenda
•   Briefing Overview
•   Regulatory Approvals
•   OrbView‐3 Spacecraft Status
•   Timing
•   Execution and Verification Team
•   De‐Orbit Plan
•   Risks and Mitigation Approach
•   Summary




                              2


                              Overview
• OrbView‐3 is no longer capable of performing its mission
• GeoEye’s License to Operate a Private Remote Sensing
  Space System from NOAA includes requirement for
  proper vehicle disposal
   – Paragraph 11 states
      “…The Licensee will deorbit the spacecraft by means of either a Licensee‐
        controlled de‐orbit and re‐entry over a broad ocean area, or a natural
        orbital decay and uncontrolled atmospheric re‐entry.”
• GeoEye has chosen to complete a controlled deorbit to
  ensure we remove OV‐3 as potential source of orbital
  debris


                                       3


               Overview (continued)
• Regulatory Approvals: OrbView‐3 satellite (OV‐3) de‐
  orbit requires NOAA/FCC regulatory approvals
• OV‐3 is Non‐Operational: No imaging operations since
  2007; decision has been made to de‐orbit
• Timing: By January 2011; no space for OV‐3 flight
  operations in GeoEye’s new HQ facilities
• De‐Orbit Plan: Developed by expert team with de‐orbit
  and flight dynamics experience
• Risk Mitigation: Risks identified and mitigated




                            4


                   Regulatory Approvals
• OV‐3 licensed by NOAA in 1994
   – Regulations require that satellite disposal be in a manner
     satisfactory to the President and de‐orbit plans be approved
     by NOAA
   – NOAA license requires either controlled de‐orbit over broad
     ocean area or natural orbital decay/uncontrolled atmospheric
     reentry
• OV‐3 licensed by FCC in 1999
   – Regulations require special temporary authority if de‐orbit
     changes the satellite orbital parameters originally authorized




                                  5


                 OV‐3 Spacecraft Status
• OV‐3 was launched June 26, 2003
  – Normal imaging operations until Spring 2007
     • Anomaly experienced and reported March 2007
     • Total loss of camera operations; unrecoverable
  – Satellite attitude and control is fully functional
  – Current altitude approximately 438 km (271 miles)
  – Remaining usable propellant 22.98 kg
     • 150% of calculated amount necessary for deorbit
• Insurance
  – On‐orbit insurance claim was paid in 2008
  – GeoEye holds $22M of third party general commercial liability
    insurance for property damage and personal injury

                                    6


                              OV‐3 Spacecraft Status cont.
     Subsystem                           Key Parameters
Mission                Commercial Imaging
                       5 Year Mission
Mass:                  670 lb launch weight (303.9 kg)
Size:                  104 x 75 x 45 inch (deployed)
                       Cylindrical Structure: 40” dia. x 75 “ long
                       Solar Array: 104” x 66”, body mounted
Attitude Control       3-axis controlled, zero momentum control system
                         Fiber Optic IRU
                         2 x Star Trackers
                         Coarse Sun Senors
                         3-Axis Magnetometer
                         GPS receiver
                         Magnetic Torque Rods
                         4 Reaction Wheels (3 axes + skew)
Payload                1m panchromatic, 4m Multispectral Camera
                       32 Gigabit Solid State Recorder
                       X-band transmiter for payload data downlink
                       2-axis gimbal High Gain X-band antenna
                       Dedicated Payload Interface Processor
TT&C                   UHF Telemetry and Encrypted Command link
                       Backdoor receiver for limited commanding
C&DH                   Distributed Architecture
                       Dedicated CDH, ACS, and Payload 80C186 Processors
Propulsion System      Monopropellant Blowdown
                       Four x 1.0 lbf thrusters
Electric Power         Bus Voltage: 22-34 Vdc
                       22 Cell Nickel Hydrogen Battery (11 CPV’s)
                       625 Watt Solar Array (EOL)




                                                                            ADS Proprietary
                                                                7


                            Timing
• January 2011: GeoEye moving to new HQ building
   – No space planned for OV‐3 flight operations


• [December 15, 2010]: Begin implementation of OV‐3
  de‐orbit plan; complete de‐orbit around December 31,
  2010
   – Assumes NOAA/FCC de‐orbit regulatory approvals obtained


• [January 4, 2011]: Latest start date to complete OV‐3
  de‐orbit before GeoEye HQ move


                                 8


                                           Execution Team
•   GeoEye selected experienced de‐orbit contractor
•   Applied Defense Solutions (ADS) to perform the OV‐3 de‐orbit analysis and operations
•   Based on experience in de‐orbit precision analysis/planning and operations work
     – NASA COTS – International Space Station (ISS) Resupply
          •   Re‐entry flight dynamics software
          •   Re‐entry analysis – verified and validated by NASA/JSC
          •   Monte Carlo analysis tools development
          •   Re‐entry documentation
     – NASA’s Compton Gamma Ray Observatory
          • Re‐Entry Trajectory Analysis
          • Re‐entry performed by NASA/GSFC June 4, 2000
     – NASA’s Tropical Rainfall Measuring Mission (TRMM) – Feasibility Study
          • Re‐Entry Trajectory Analysis
          • Monte Carlo footprint analysis
     – Mir Reentry
          • Re‐entry analysis
     – NASA LCROSS Lunar Impact Planning
          •   Maneuvering calibration
          •   Precision impact targeting
     – Debris Assessment Software



                                                         9


                        Verification Team
• Lockheed‐Martin Space Systems Company
  • Independent review by orbit / mission experts
     – Mr. R. Tanner – BS/MS Aerospace Engineering
          » 29 years experience as orbital analyst / mission analyst
          » Areas of Expertise: orbit adjust planning, orbit adjust modeling, engine
            performance modeling, orbital mechanics, operational timelines and
            space vehicle operations.
      – Mr. E. Meek – BS/MS Electrical Engineering / Computer Science
          » 10 years experience as orbital analyst / mission analyst
          » Areas of Expertise: satellite GN&C, collision avoidance, maneuver
            planning, proximity operations, and orbital analysis.
• Independent Auditor
      – Col. J. Lopez (Ret.)– BS/MS Aerospace Engineering
          » 35 years experience in orbital mechanics
          » Areas of Expertise: Orbital mechanics, space modeling, satellite tool kit



                                        10


DE‐ORBIT PLAN


                11


            De‐Orbit Planning & Execution Process
•   Conceptual Planning – Completed
     –   Development of a conceptual scenario to showcase
         how OV‐3 will be de‐orbited
           •   Understand how lowering could occur
           •   Identify potential issues and start addressing them
•   Analysis – In Progress
     –   Design Trajectory Plan
     –   Orbit Determination Error Analysis
     –   Run Monte Carlo algorithm against Trajectory Plan
•   Operations
     –   Maneuver & Trajectory Planning
     –   Verification of impact footprint after each
         maneuver
     –   Orbit Determination
     –   Conjunction Assessment
           •   All burns will be coordinated with JSpOC prior to
               execution
     –   Reporting and notification




                                                                   12


                                      OV‐3 Final Orbit




                Impact
               Footprint


•   Impact occurs quickly after last maneuver
•   Impact location chosen to be near center of potential zone area
     –   If maneuver under burns or over burns, the impact point is still within potential area
•   Monte Carlo analysis will provide definition of splash down footprint
     –   Much smaller than the potential zone area
•   Total duration from the first maneuver execution is approximately 17 days and 2 hours


                                                        13


                            De‐Orbit Plan
• The de‐orbit plan contains a iterative process that includes
  analysis of each step prior to proceeding
   – Ensures operations follow the plan
• 2 to 3 day maneuver execution cycle
   – Plan maneuver and upload commands
   – Spacecraft performs commanded maneuver
   – Ground station contacts the spacecraft and retrieves data
       • May happen more than once depending on time duration post maneuver
   – Maneuver analysis is performed, and orbit solution is determined
   – Verify analyses of executed vs. planned maneuver
       • Details below
   – Subsequent maneuver planned and/or overall sequence plan updated as
     needed
   – Repeat



                                      14


                          De‐Orbit Plan
                               (continued)

• Two phase de‐orbit plan
   – Phase 1: Safely lower orbit below the International Space
     Station (ISS)
   – Phase 2: Continue lowering orbit to atmospheric entry point
• Total of 11 maneuvers are expected to be performed
   – One calibration burn
      • Additional calibration maneuvers added as necessary
      • May be performed at any time prior to de‐orbit
   – Ten orbit lowering burns
• Controlled, Measured, and Verifiable
   – Burn plan adjusted to account for prior event actual
     performance

                                    15


                     De‐Orbit Plan – Phase 1
• Phase 1 consists of 5 maneuvers
   – 1 Calibration maneuver
       • Additional calibration maneuvers may be needed based on results
   – 4 Orbit lowering maneuvers
• GeoEye will coordinate with NASA on ISS operations prior to plan
  commencement and prior to each Phase 1 maneuver
• Fail‐safe de‐orbit strategy
   – Maintain and verify safe distances away from other space objects
       • Primarily the ISS, due to the risk of human life
       • All other space objects contained in the space catalog
   – Provide significant amount of time to recover if a contingency occurs
       • Guarantees recovery time from contingencies without interfering with the ISS
   – Each maneuver contributes to de‐orbiting OV‐3



                                          16


                    De‐Orbit Plan – Phase 2
• 6 maneuvers
   – Maneuvers lowers orbit to atmospheric entry interface
• Eccentric orbit provides steep reentry angle
   – Increases impact location predictability
   – Eliminates risk of atmospheric skip
   • Pacific Ocean is the largest broad ocean impact area
       • Deorbit area is 700 km away from any land mass
       • Exceeds 370 km requirement
   – Exact location dependent on time and duration of maneuvers
• Reporting and notification for atmospheric entry to ground
  propagation
   – Notify FAA and other proper authorities
   – NOAA’s assistance coordinating with outer agencies involved in deorbit
     requested


                                        17


                           Risks & Risk Mitigation
• Risk: Calendar time remaining before the GeoEye move from Dulles, VA to
  Herndon, VA
• Mitigation: Plan in work for over a year.
    – Solicited NOAA’s input
    – Plan submittal within sufficient time for USG approval. Pre‐de‐orbit tasks such as calibration
      burn, to create margin.


• Risk: To de‐orbit OV‐3 must pass through the ISS orbital radius
    – OV‐3 orbital radius higher than ISS’s, inclination is different
• Mitigation: Passing through the ISS orbital radius has been addressed in the
  technical approach
    – OV‐3/ISS proximity avoided with proper maneuver timing and phasing
    – Plan keeps OV‐3 and ISS significantly separated at the orbit crossing points
    – This approach also allows for significant time to respond to a contingency event without risk
      to the ISS
        • Interim OV‐3 orbits calculated to provide at least 240 days until next ISS close approach



                                                   18


                       Risks & Risk Mitigation Cont.
• Risk: Last orbit adjust maneuver for OV‐3 was July 25, 2006
•   Mitigation: Incorporate lessons learned from similar case this past summer (OV‐2)
     –   Fully understand the current state of the spacecraft and what has changed since last maneuver
     –   Same ADS personnel working both missions
•   Mitigation: Planning on performing a calibration burn to test the engines, ensuring
    that:
     –   The engines fire as commanded
     –   Allows for the validation of the maneuver plan and adjust as necessary
     –   Verifies spacecraft pointing accuracy and stability


• Risk: Limited amount of fuel remaining
•   Mitigation: Fuel usage has been modeled and will be monitored throughout trajectory
    planning process
     –   Sufficient fuel for re‐entry
     –   Reserve for additional maneuvers if required




                                                        19


                   Risks & Risk Mitigation Cont.
• Risk: Modeling uncertainties
     – Maneuver plan verses maneuver performance
     – Desired impact location verses actual impact location
     – Orbit decay
• Mitigation: Uncertainties in impact location will be analyzed in a Monte Carlo
  analysis
     – Monte Carlo analysis will vary maneuver performance for each maneuver as well
        as propagation properties
     – Bounds debris impact ellipse
•   Mitigation: Planning on performing a calibration burn to test the engines, ensuring
    that:
     – The engines fire as commanded
     – Allows for the validation of the modeling of maneuver plan and adjust as necessary
     – Verifies spacecraft attitude control system performance




                                            20


                        Risk Mitigation Cont.
• Risk: The possible loss of attitude control authority as the altitude is decreased
• Mitigation: The control torques can be assessed as the altitude is lowered and
  a minimum altitude for positive control can be estimated based on the max
  torque available from the wheels

• Risk: The ability to contact the spacecraft as the altitude decreases and
  contact durations become shorter
• Mitigation: Impact location has also been chosen so that if the actual impact
  trajectory is long or short the debris will still be within the impact parameters




                                         21


                Addressing NASA‐STD 8719.14
• Atmospheric Skip
   – Req 56580 – The final maneuver lowers periapsis altitude into the Earth’s
     atmosphere
       • The design will be verified in a Monte Carlo analysis, with perturbed maneuvers and
         various atmospheric conditions
• Impact Area
   – Req 56627 – For controlled reentry, the selected trajectory shall ensure that no
     surviving debris impact with a kinetic energy greater than 15 joules is closer than
     370 km from foreign landmasses, 50 km from continental U.S., U.S territories, or
     Antarctica
       • The design chooses an impact location in the center in the potential impact zone
       • Potential impact zone meets or exceeds all distance requirements
   – Req 56628 – For controlled reentries, the product of the probability of failure of
     the reentry burn and the risk of human casualty assuming uncontrolled reentry
     shall not exceed 0.0001
       • Further analysis required, but related to the distance requirement




                                              22


                        Summary
• GeoEye has developed a prudent plan for the de‐orbit
  of OV‐3 with ample safeguards and verification
• Risks are clearly identified and mitigated
• NOAA’s assistance requested to ensure GeoEye notifies
  and coordinates with all appropriate agencies
• GeoEye is ready to execute upon USG approval




                             23