Attachment ComplianceRequest

ComplianceRequest

REQUEST submitted by DigitalGlobe, Inc.

Compliance Request

2005-10-24

This document pretains to SAT-MOD-20040728-00151 for Modification on a Satellite Space Stations filing.

IBFS_SATMOD2004072800151_462430

                                            Before The
                      Federal Communications Commission
                                     Washington, D.C. 20554




                                                      No No Ne Ne Ne Nt Nes Nuuet Nu!
In The Matter of

DigitalGlobe, Inc.
                                                                                        File No. SAT—MOD—20040728—00151
Modification of Authorization to Construct,                                             Call Sign: $2129
Launch and Operate a Remote—Sensing Satellite
System


To:    Chief, International Bureau

                   REQUEST FOR DETERMINATION OF
        COMPLIANCE WITH SATELLITE IMPLEMENTATION MILESTONES

       DigitalGlobe, Inc. ("DigitalGlobe"), by counsel and pursuant to Section 25.164 of the

Commission‘s rules, hereby notifies the Commission that it has met the first three milestones set

forth in the Order and Authorization DA 05—2640 (hereinafter, "Order") issued on September 30,

2005 granting authority to modify DigitalGlobe‘s Non—Geostationary Satellite Orbit ("NGSO")

satellite system. Specifically, within the Order, the Commission authorized DigitalGlobe to

construct, launch and operate three (3) new satellites within DigitalGlobe‘s EESS space system

and to operate the three satellites in the entire allocated portion of the X—band (i.e., 8025 MHz to

8400 MHz). That is, the Commission has authorized DigitalGlobe to increase its allocation lof

8025 MHz to 8345 MHz by 55 MHz per new satellite, such that the three new DigitalGlobe

satellites will be able to operate up to 8400 MHz.

       Within the Order, the Commission required DigitalGlobe to fulfill certain milestones for

constructing the authorized satellites and modifying its space segment (Order, Paragraph 11).

Also, the Commission required that DigitalGlobe post a bond by October 30, 2005 in the amount


required by the Commission‘s rules for the construction and operation of an NGSO satellite

system: five million dollars ($5,000,000) (Order, Paragraphs 12 & 13). The bond requirement

was imposed in order to ensure that DigitalGlobe uses the entire spectrum that the Commission

has authorized DigitalGlobe to use. The Commission‘s stated purpose for the bond was to

brevent DigitalGlobe from " ‘warehousing‘ the spectrum to use in the unlikely event that ‘best

case‘ demand scenarios materialize or to delay competitors from using it" (Order, Paragraph 13).

       In particular, DigitalGlobe demonstrates herein that it: (i) has contracted for construction

of the DigitalGlobe next—generation EESS satellite system; (ii) has completed its Critical Design

Review; and (iii) has already commenced construction of the spacecraft. As a result of these

showings, DigitalGlobe respectfully requests that the International Bureau determine that

DigitalGlobe has satisfied the first three milestone requirements set forth in the Order. The

determination that DigitalGlobe has satisfied the first three of the required milestones will allow

DigitalGlobe to reduce the $5 million bond that it is required to post by October 30, 2005

pursuant to the Order to $2 million.

       In addition, DigitalGlobe notes that it intends to file, prior to October 30, 2005, a Petition

for Reconsideration of the Bond Requirement Provided in FCC Order and Authorization DA 05—

2640 ("Petition for Reconsideration"). DigitalGlobe contends that the bond requirement

imposed in the Order is wholly unnecessary inthe instant case because, among other reasons,

DigitalGlobe is contractually bound to the U.S. government—specifically, the National

Geospatial—Intelligence Agency ("NGA")—to construct the satellites covered by the Order and


to bring the satellites into service using the bandwidth allocated by the Commission in the

Order.‘

          The imposition of the bond requirement in the instant case would result in duplicative

regulatory requirements being imposed on DigitalGlobe: one from NGA and the other from the

Commission. As the Commission has commented in various regulatory proceedings in the past,

the imposition of duplicative regulatory requirements is contrary to public policy." Accordingly,

DigitalGlobe hereby requests that the Commission, on its own motion pursuant to 47 C.F.R. §

1.108, set aside the bond requirement imposed by the Order.

          Despite DigitalGlobe‘s contention that the bond requirement is duplicative and

unnecessary in the instant case, DigitalGlobe is prepared to file a bond as required by

Commission rules. In advance of filing this bond, however, DigitalGlobe herein and through

attachments provides evidence required to demonstrate DigitalGlobe‘s current fulfillment of

three (3) of the five (5) milestones required by Paragraph 30 of the Order.




‘ In the event that the Commission desires to understand the full nature of DigitalGlobe‘s
contractual commitments to NGA (the "NextView Contract"), we direct you to discuss salient
matters with Ms. Cyndi Wright, the NextView Program Manager at NGA, at (301) 227—6645, or
wrightc@nga.mil. Unfortunately, we are not at liberty to submit a copy of the NextView
Contract, as there are significant portions of the NextView Contract that are classified.

* See, for example, the Commission‘s statements made in the Second Report and Order In the
Matter ofMitigation ofOrbital Debris, FCC 04—130 ("Second Orbital Debris Mitigation Order"),
in relation to the imposition of orbital debris mitigation requirements on operators of remote
sensing satellite operators who have already submitted orbital debris mitigation plans to the
National Oceanic and Atmospheric Administration ("NOAA") as part of their authorizations to
operate remote sensing systems pursuant to the Land Remote Sensing Act, 15 U.S.C. § 5601 et
seq. Therein, the Commuission found that requiring remote sensing operators to submit orbital
debris mitigation plans to the Comumission would result in duplicative regulatory burdens that are
contrary to public policy. See, Second Orbital Debris Mitigation Order, at Paragraphs 102—104.


Milestone 1: Entry into a Binding, Non—Contingent Construction Contract — Satisfied
February 2004

        On February 23, 2004, DigitalGlobe entered into a binding, non—contingent contract with

Eastman Kodak Company ("Kodak") for the construction of the Imaging Sensors for

DigitalGlobe‘s next—generation EESS satellite system. That contract ("the Kodak/ ITT

Contract") was subsequently assigned to ITT in connection with ITT‘s purchase of Kodak‘s

Space Systems Division. On April 29, 2004, DigitalGlobe entered into a binding, non—

contingent contract with Ball Aerospace & Technologies Corp. ("Ball") for the construction of

satellite bus for DigitalGlobe‘s next—generation EESS satellite system, including the integration

of the Imaging Sensors to be built by Kodak,/ ITT ("the Ball Contract"). Because of the unique

confidentiality and national security concerns that exist in ;:onnection with its next—generation

EESS satellite system, DigitalGlobe cannot provide copies of either the Kodak/ITT Contract or

the Ball Contract.

       The FCC‘s intent in generally requesting that licensees submit unredacted copies of the

construction contracts for a licensed system appears to be one of ensuring that all preliminary

steps have been taken so that each such contract "is one that allows neither significant delays

between the execution of the contract and the actual commencement of construction, nor

conditions precedent to construction" (Paragraph 184 of the "First Space Station Licensing

Reform Order‘"). As demonstrated below, however, CDR for the system was completed well

over a year ago, and satellite construction has begun. There is, therefore, no doubt that either the

Kodak/ITT Contract or the Ball Contract permits any significant delays or conditions precedent

to construction, because satellite construction is well underway.



> Amendment of the Commission‘s Space Station Licensing Rules and Policies, First Report and
Order, IB Docket No. 02—34, 18 FCC Red 10760 (2003).


       In addition to the foregoing, DigitalGlobe notes that the NextView Contract with NGA

also obligates DigitalGlobe to meet certain clearly defined milestones with regard to satellite

construction, launch, and operation. For specific information regarding the NextView Contract,

please contact Cyndi Wright at NGA.

Milestone 2: Completion of Critical Design Review — Satisfied July 2004

       Pursuant to Paragraphs 188 to 191 of the First Space Station Licensing Reform Order,

and footnotes thereto, licensees bear the burden of demonstrating that they have performed the

Critical Design Review ("CDR"), thereby completing Milestone 2.

       The Commission has not developed a specific rule or other guidance regarding how much

information/ documentation is required to be presented in order to demonstrate compliance with

this milestone. Therefore, DigitalGlobe offers as evidence of CDR completion a copy of

correspondence from the NGA, together with the applicable supporting milestone checklist,

submitted herewith as Enclosure A. The correspondence constitutes formal approval from

NGA‘s Commercial Imagery Program Manager that in July 2004, DigitalGlobe completed the

Satellite CDR and System Summary CDR pursuant to DigitalGlobe‘s contractual obligations to

NGA. If you require additional information, please contact Cyndi Wright at NGA. The

arguments as to why Enclosure A should not be made available for public inspection are

provided in Enclosure D.

Milestone 3: Commencement of Physical Construction — Satisfied December 2004

       Pursuant to the First Space Station Licensing Reform Order, at Paragraphs 192 and 193

and footnotes thereto, licensees bear the burden of demonstrating that the physical construction

of the satellite has commenced, thereby completing Milestone 3. There is no specific test for

compliance with this milestone. Rather, the Commission requires licensees "to provide


sufficient information to demonstrate to a reasonable person that they have commenced physical

construction of their licensed spacecraft" (First Space Station Licensing Reform Order,

Paragraph 193).

       DigitalGlobe offers, as evidence that the physical construction of the spacecraft has

commenced, copies of correspondence from NGA, together with the applicable supporting

milestone checklists, submitted herewith as Enclosures B and C. The correspondence constitutes

formal approval from NGA‘s Commercial Imagery Program Manager that in December 2004,

DigitalGlobe completed the "Telescope Assembly Started, Bus Integration Started part 2" and

"Telescope Test Readiness review" milestones pursuant to DigitalGlobe‘s contractual

obligations to NGA. These approvals conclusively demonstrate that construction of the Satellite

has begun. If you require additional information, please contact Cyndi Wright at NGA. The

arguments as to why Enclosures B and C should not be made available for public inspection are

provided in Enclosure D.

Request for Determination of Milestone Compliance

       Notwithstanding the foregoing, DigitalGlobe is prepared to file a full $5,000,000 bond as

required by the Order. However, as evidenced by this letter and the information contained in

enclosures hereto, DigitalGlobe has already completed three (3) of the five (5) milestones set

forth in the Order. Accordingly, in accordance with the FCC‘s August 6, 2003 Guidance for

Filing Bonds (Report No. SPB—187, DA 03—2602) and the First Space Station Licensing Reform

Order, DigitalGlobe requests that the Commission: (1) certify that DigitalGlobe has fulfilled

Milestones 1—3 and (2) reduce the bond required to be paid by DigitalGlobe.


                                        *k    o   ko    o#



       Should you have any questions regarding the enclosed documents, please contact the

undersigned at (703) 563—3090, x. 205 or DigitalGlobe‘s General Counsel, Ms. Bettina Eckerle

at (303) 684—4312.

                                                       Respectfully submitted,

                                                       DIGITALGLOBE, INC.




                                                       By:     '_ _ /,.«-
                                                              Keil J.   Ritferpase
                                                              Mark J.    Fieckers

                                                              Pierson & Ritterpusch, LLP
                                                              2121 Cooperative Way, Suite 200
                                                              Herndon, Virginia 20171
                                                              (703) 563—3090, x. 205

                                                              COUNSEL TO DIGITALGLOBE, INC.

Bettina Eckerle
General Counsel
DigitalGlobe, Inc.
1601 Dry Creek Drive
Longmont, Colorado 80503

ENCLOSURES


October 24, 2005


                             ENCLOSURE A




 Correspondence from the National Geospatial—Intelligence Agency ("NGA")
       to DigitalGlobe on July 6, 2004 regarding Completion of CDR

                                   and
  [DigitalGlobe Internal Checklist Regarding Milestone Completion for NGA,
Pursuant to Request for CONFIDENTIAL Treatment, dated October 24, 2005]


                                                                        mome
L. ?.20G4   4: 279M                                                —   No.6?70   P.2/2


                      NATIONAL GEOSPATIAL—INTELLIGENCE AGENCY
                                       4600 Sangamore Road
                                   Bathesds, Maryland 20815—5009




                                                                       July 6, 2004
  Herbert F. Satterlee,     IILI
  DigitalGlobe, Inc.
  1900 Pike Road
  Longmont, Colorado 80501


  Dear Mr. Satterlee,

  The purpose of this letter is to notify you of the National
  Geospatial—Intelligence Agency (NGA) Commercial Imagery Program
  Manager‘s approval of the NextView Milestone 6: Satellite
  Critical Desiqgn Review (CDR) held June 22—25, 2004, at Ball
  Aerospace, Boulder, Colorado, and System Summary CDR held on
  June 28—30, 2004, at DigitalGlobe in Longmont, Colorado.

  The criteria identified in the Statement of wWork, Appendix C
  ware met, so you are authorized to proceed as planned.   This
  lTetter serves as your authorization to submit an invoice for
  payment for Milestone 6.

                                   Sincerely,




                                   ,A;”bduflg . g}bcxim,a
                                   Sandra S., Jacks
                                   NGA Commercial Imagery Program Manager


                             ENCLOSURE B




 Correspondence from the National Geospatial—Intelligence Agency ("NGA")
              to DigitalGlobe on December 6, 2004 regarding
       Commencement of Telescope Construction and Bus Integration

                                   and
  [DigitalGlobe Internal Checklist Regarding Milestone Completion for NGA,
Pursuant to Request for CONFIDENTIAL Treatment, dated October 24, 2005]




                                    10


                              NATIONAL GEOSPATIAL—INTELLIGENCE AGENCY

                                                                                   .                bo    39
                                                                                   December/l}           2004

       Herbert F. Satterlee, III
        DigitalGlobe, Inc.
        1601 Dry Creek Road, Suite 260
       Longmont, Colorado 80503



       Dear Mr.     Satterlee,

        The purpose of this letter is to notify you of the National
        Geospatial—Intelligence Agency (NGA) Commercial Imagery Program
        Manager‘s approval of the NextView Milestone 7b: WV60 Telescope
        Assembly Started,           Bus Integration Started part 2.

        The criteria identified in the Statement of Work, Appendix C
        were met, so you are authorized to proceed as planned.  This
       ‘letter serves as your authorization to submit an invoice for
       ‘payment for Milestone 7b.




                                                     Sandra S. Jacks
                                                     NGA Commercial Remote Sensing
                                                         Management Authority




              [] 4600 SANGAMORE ROAD                               [] sa3e voGgEL Roap
                 BETHESDA, MARYLAND 20816—5003                        ARNOLD, MISSOURI e3010—6238
rgety ro ue                                [J 12310 SUNAISE vALLEY DRrive                     [ 1200 Finst stheet, se
rouowing:                                     RESTON, VIRGINIA 20191—3449                       WASHINGTON, DC 20303—0001


                             ENCLOSURE C




 Correspondence from the National Geospatial—Intelligence Agency ("NGA")
 to DigitalGlobe on July 6, 2004 regarding Telescope Test Readiness Review

                                   and
 [DigitalGlobe Internal Checklist Regarding Milestone Completion for NGA,
Pursuant to Request for CONFIDENTIAL Treatment, dated October 24, 2005]




                                    12


                               NATIONAL GEOSPATIAL—INTELLIGENCE AGENCY

                                                                                                                      t
                                                                                        3Q.M6vember 2004
         Herbert F.      Satterlee,         III
         DigitalGlobe,        Inc.
         1601 Dry Creek Road, Suite 260
         Longmont, Colorado 80503



         Dear Mr.    Satterlee,

        The purpose of this letter is to notify you of the National
        Geospatial—Intelligence Agency {(NGA) Commercial Imagery Program
        Manager‘s approval of the NextView Milestone 8: WV6O0 Telescope
        Test Readiness Review.

        The criteria identified in the Statement of Work, Appendix C
        were met, so you are authorized to proceed as planned.  This
       ‘letter serves as your authorization to submit an invoice for
        payment for Milestone 8.




                                                  Sandra 5. Jacks
                                                  NGA Commercial Remote Sensing
                                                      Management Authority




               [] 4600 SANGAMORE ROAD                                   {] 3838 vOGEL ROAD
                  BETHESDA, MARYLAND 20816—5003                            ARNOLD, MISSOURI 63010—6238

AEPLY TO ThE                                [7J 12310 SUNRISE VALLEY DRIVE                         [] 1200 FIRST STREET, SE
rouowine                                          RESTON, VIRGINIA 20191—3449                            WASHINGTON, DC 203030001


                                ENCLOSURE D




             [DigitalGlobe Request for CONFIDENTIAL Treatment of
         DigitalGlobe Internal Checklists within Enclosures A, B, and C of
Request for Determination of Compliance with Satellite Implementation Milestones,
                              dated October 24, 2005]




                                       14



Document Created: 2019-04-15 01:20:53
Document Modified: 2019-04-15 01:20:53

© 2024 FCC.report
This site is not affiliated with or endorsed by the FCC