DRB1 Milestone Supp

SUPPLEMENT submitted by DIRECTV Enterprises, LLC

DRB1 Milestone Supp

2012-02-29

This document pretains to SAT-LOA-20060908-00099 for Application to Launch and Operate on a Satellite Space Stations filing.

IBFS_SATLOA2006090800099_941116

                                       February 29, 2012


BY ELECTRONIC FILING

Marlene H. Dortch
Secretary
Federal Communications Commission
445 Twelfth Street, S.W.
Washington, DC 20554

       Re:     DIRECTV Enterprises, LLC
               IBFS File Nos. SAT-LOA-20060908-00099, SAT-AMD-20080114-00013, and
               SAT-AMD-20080321-00076 (Call Sign S2711)

Dear Ms. Dortch:

        DIRECTV Enterprises, LLC (“DIRECTV”) hereby submits additional information to
facilitate the staff’s review of DIRECTV’s compliance with its milestone requirements to
execute a non-contingent satellite contract and to complete the critical design review (“CDR”)
for the DIRECTV RB-1 satellite. DIRECTV previously submitted its construction contract with
Space Systems/Loral (“SS/L”) on July 26, 2010, and materials demonstrating completion of
CDR on July 28, 2011.

         The SS/L contract contemplates a satellite with both a 17/24 GHz BSS payload and a Ka-
band payload. Although DIRECTV currently operates two Ka-band satellites at the nominal 99°
W.L. orbital location, it has not yet sought authorization for the Ka-band payload on this
satellite. DIRECTV is in the process of finalizing various design and operational details, and
intends to file an appropriate application with the Commission for such authority in the next few
months. Accordingly, DIRECTV recognizes that, as contemplated under Section 25.113(f) of
the Commission’s rules, it is proceeding with construction of the satellite at its own risk. In
addition, DIRECTV recognizes that any favorable finding with respect to the contracting and
CDR milestones would not be tantamount to approval of any technical specifications in addition
to or not consistent with DIRECTV’s existing authorization. DIRECTV also accepts the risk
that design changes might be required in light of any future Commission action with respect to
an application for authorization of the Ka-band payload on this satellite.

       Lastly, this is to confirm that to date, DIRECTV has paid SS/L all amounts due under the
Milestone Payment Plan attached as Exhibit E to the contract through Payment Milestone 14b.


WILTSHIRE & GRANNIS LLP

Marlene H. Dortch
February 29, 2012
Page 2 of 2

      Should you have any questions, please do not hesitate to contact me.

                                           Respectfully submitted,

                                            /s/

                                           William M. Wiltshire
                                           Counsel for DIRECTV



cc:   Andrea Kelly



Document Created: 2012-02-29 16:39:25
Document Modified: 2012-02-29 16:39:25