Attachment Something

This document pretains to SAT-L/A-19980105-00001 for Launch Authority on a Satellite Space Stations filing.

IBFS_SATLA1998010500001_289177

                                                                                         July 24, 2002


                    IBFS APPORTIONED & 11 SUBSYSTEMS
                              ACTION PLAN
TASK ITEM                               LEAD         START     DONE STATUS/COMMENTS
Hold Kickoff Meeting                    MJ Solomon   7/17/02   7/17/02   Done
Determine time line for completing      MJ Solomon   7/17/02   7/17/02   Done
subsystems 2 & 3 tasks (apportioned &                                       - Apportioned
11 subsystems, respectively)                                                  Requirements (6
                                                                              weeks) – 7/17/02 –
                                                                              8/27/02
                                                                            - 11 Subsystems
                                                                              Requirements ( 9
                                                                              weeks) – 9/3 – 11/5/02




11/12/02 10:38 AM   Page -1-


Determine high-level strategy for        MJ Solomon    7/17/02   7/17/02   Done
incorporating ongoing changes to the                                          - Revise change order
existing IBFS system                                                              language for subtask 4
                                                                                  (everything not
                                                                                  covered in
                                                                                  requirements to date)
                                                                                  to reflect the
                                                                                  following:
                                                                              1. known requirements
                                                                              (e.g. Bill Howden’s
                                                                              documents);
                                                                              2. collaboration with
                                                                              maintenance staff re:
                                                                              ongoing changes to the
                                                                              IBFS System and all new
                                                                              work tickets, etc;
                                                                              3. conduct IBFS system
                                                                              review sessions with
                                                                              internal and external
                                                                              constituents to ensure
                                                                              needed existing system
                                                                              functionality is
                                                                              incorporated into
                                                                              requirements; and
                                                                              4. at a point in time,
                                                                              freeze major changes to
                                                                              IBFS.
Send out thank you e-mail to IB          MJ Solomon    7/18/02   7/24/02
Schedule S Contributors
Send out E-mail to internal IBFS users   Jacki Ponti   7/18/02   7/24/02   MJ will draft an e-mail for
notifying them of new funding & start                                      Jacki’s approval and
up of the next phase of requirements                                       distribution.
gathering
Review apportioned requirements &        Michele       7/17/02   7/24/02
take 1st cut at identifying which are    Lamptey/Fre
clear, ambiguous, and out & which        nchi Mack
ones apply to internal vs external
customers.
Hold meeting with MJ Solomon &           Michele       7/23/02   7/24/02
Jacki Ponti to review/approve            Lamptey
categorizations
Schedule meetings & meet with            Michele       7/26/02   8/02/02
internal IB staff to clarify ambiguous   Lamptey
requirements
Schedule meetings & meet with            Michele       8/5/02    8/9/02
internal IB staff to drill down on all   Lamptey
clear internal requirements
Verify drilled down internal             Michele       8/12/02   8/16/02
requirements with internal IB staff      Lamptey


11/12/02 10:38 AM   Page -2-


Develop & distribute draft                 Michele       8/12/02    8/19/02
requirements document to internal IB       Lamptey
staff for review before final validation
session
Hold final validation session on           Michele       8/21/02    8/22/02
apportioned requirements with internal     Lamptey
IB staff.
Develop & issue PN to the public           MJ Solomon    7/17/02    7/30/02
providing a list of external apportioned
topics & asking them provide input
electronically.
Develop & send e-mail to our 25 Part       Michele       7/17/02    7/30/02
25 external customers providing a list     Lamptey
of external apportioned topics & asking
them to provide input electronically
Comments due back                          Public        7/30/02    8/8/02
Develop draft PowerPoint presentation      Michele       8/8/02     8/13/02
of specific requirements for approval      Lamptey
by MJ & Jacki
Issue PowerPoint presentation to both      Michele       8/14/02    8/14/02
public & 25 Part 25 customers              Lamptey
requesting feedback electronically
Comments due back                          Public        8/14/02    8/23/02
Incorporate both internal and external     Michele       8/12/02    8/27/02
constituents’ requirements into RD &       Lamptey
provides RD deliverable to COTR
COTR reviews & provides feedback           MJ Solomon    8/27/02    9/4/02
RD is revised to reflect COTR changes      Michele       9/4/02     9/5/02
& delivered back to COTR for               Lamptey
acceptance
Identify 11 subsystem internal &           MJ            9/3/02     9/6/02
external stakeholders                      Solomon/Jac
                                           ki Ponti
Schedule meetings                          Michele       9/9/02     9/11/02
                                           Lamptey
Hold requirements gathering sessions       Michele       9/12/02    10/10/02
                                           Lamptey
Verification requirements                  Michele       9/12/02    10/10/02
                                           Lamptey
Hold validation sessions                   Michele       10/11/02   10/25/02
                                           Lamptey
Incorporate both internal and external     Michele       10/28/02   11/05/02
constituents’ requirements into RD &       Lamptey
provides RD deliverable to COTR
COTR reviews & provides feedback           MJ Solomon    11/05/02   11/12/02
RD is revised to reflect COTR changes      Michele       11/12/02   11/13/02
& delivered back to COTR for               Lamptey
acceptance



11/12/02 10:38 AM   Page -3-



Document Created: 2002-11-12 10:38:39
Document Modified: 2002-11-12 10:38:39