Attachment 2003TMI TerreStar-up

This document pretains to SAT-AMD-20001103-00158 for Amended Filing on a Satellite Space Stations filing.

IBFS_SATAMD2000110300158_819596

        SQ\/Q—% \[e/bj nston                                                    September 26, 2003
Mr—BDonald=*belson—C
International Bureau
Federal Communications Commission
445 Twelfth Street, SW
Washington, DC 20554

       Re:     File No :       189—SAT—LOI—97
               IBFS Nos.       SAT—LOI—19970926—00161
                               SAT—AMD—20001103—60158

Dear Mr. Abelson:

               On September 3, 2003, following a meeting with you, Bryan Tramont, Chief of
Staff, and John Rogovin, General Counsel, we included as part of our ex parte submission a chart
that TMI and TerreStar had used in the meeting the day before. It shows that in every case
where a satellite authorization has been cancelled on milestone grounds there was no outstanding
non—contingent satellite construction contract that conformed to the authorization and that, in
several cases, licenses remained in good standing, even when such a contract did not exist. This
submission encloses an updated chart that incorporates the most recent decision on this point.

                Last week the Commission issued the Conste/lation decision (FCC 03—217), in
which it affirmed the Bureau‘s earlier cancellation of Constellation‘s satellite authorization
because of its failure to meet milestone requirements. The Commission held this to be the case
with respect to the second and subsequent milestone requirements, though it noted, n. 12, that it
had not ruled whether even the initial milestone had been met by a non—contingent construction
contract. It also held (para. 18) that as to 44 of the 46 satellites in question, Constellation had
provided no "evidence that it has entered into a non—contingent contract for . . . construction."

                This is the critical distinction —— whether there is a non—contingent satellite
construction contract that conforms to the authorization. Such a contract existed in our case; it
did not exist in the Constellation case. Constellation argued for a waiver because it alleged that
economic conditions beyond its control and rapidly changing technology had caused the delay.
In our case the issue was not whether excuses for delay were sufficient, because there was no
delay in entering the required contract. In the Constellation case (para. 20) the Commission
cited the objective of making spectrum "available to parties that appear able and willing to use it
to bring service rapidly to the public." TMI/TerreStar met that test as well. Moreover, in the
words of last week‘s Constellation decision, TMI and TerreStar were "diligently proceeding with
the implementation of its system."

               The Bureau‘s February 10 Order cited seven milestone cases in connection with
the cancellation of the TMI/TerreStar authorization, not all of which are covered by our chart.
Accordingly, we thought it would be useful briefly to summarize all of the cited cases, thereby
documenting that none of them supports the result which the Bureau reached in the
TMI/TerreStar case.


                                            e


               Columbia: The Bureau‘s Opinion singled out Columbia as being "in many
respects, analogous" to the situation in our case. The facts of Columbia are completely different
from the facts in our case, however. In Columbia a transfer of the authorization was
contemplated by the parties, as was the case here, but unlike here, the parties in Columbia chose
to use the pendency of the deal as an excuse not to enter into a conforming, non—contingent
construction contract. In contrast, there is no dispute that a conforming, non—contingent
construction contract was entered into here.

               Motorola and Teledesic: In this case, no conforming, non—contingent satellite
construction contact had been entered into by the milestone deadline. The parties argued that
this was infeasible because an assignment application was pending. The Bureau concluded:

       "what actually thwarted Motorola from complying with the construction—commencement
       requirement prior to the milestone deadline was that it could not reach agreement with
       Teledesic regarding apportionment of cost burdens that would arise under a construction
       contract executed while the Assignment Application was pending. The Applicants‘
       failure to reach agreement with each other concerning reimbursement was not a
       circumstance beyond their control and cannot be deemed good cause for waiving the
       milestone rule."

In contrast, TMI and TerreStar reached agreement, the basic structure of which had been
hammered out in January 2001, and pursuant to that agreement a conforming, non—contingent
construction contract had been entered into by the milestone deadline.

               PanAmSat: This case, decided by the full Commission, also involved a transfer of
a satellite authorization via a merger, and the parties tried to use the pendency of the merger and
certain modification proposals that flowed from the merger as an excuse for not having entered
into a conforming, non—contingent satellite construction contract. Here, of course, TMI and
TerreStar not only did not use the pending transfer as an excuse but in fact entered into a
construction contract by the milestone deadline.

               AMSC: This case is particularly relevant because the Commission found that
adequate grounds existed to extend AMSC‘s construction completion and satellite launch
milestones based on AMSC‘s construction contract with Hughes, a satellite vendor, and TMI, a
then unrelated third party, for the joint procurement of AMSC‘s and TMI‘s satellites. Although
several parties protested the resulting construction delay, the Commission found that, based upon
AMSC‘s ongoing efforts to implement its project (e.g., by seeking to finalize the system‘s
technical parameters and complete coordination with Canada), even if the joint procurement was
not a cirecumstance beyond AMSC‘s control, a milestone extension was consistent with its anti—
warehousing policy and would advance the public interest by allowing new and needed mobile
satellite voice services to reach the public. The Commission (para. 13) stated: "Significantly ...
in every instance where the Commission has denied an extension request construction of the
satellite either had not begun or was not continuing, raising questions regarding the licensee‘s
intention to proceed."

              Far from supporting cancellation of a satellite authorization for failure to execute
a conforming, non—contingent construction contract, the AMSC case, therefore, provides a clear


                                            Mele


statement of the Commission‘s policy of preserving satellite authorizations (and granting
milestone extensions, if warranted) where a valid construction contract exists and the grantee‘s
actions show that construction is continuing. Further, in the 4MSC case, the Commission
reached that conclusion even though AMSC relied, in part, on a procurement agreement with an
unrelated third party. Therefore, the 4MSC case stands for a policy exactly opposite to the
Bureau‘s February 10 Order.

               MCI This 1987 Common Carrier Bureau case was cited solely to evidence the
FCC‘s long—standing policy of imposing construction milestones on satellite licensees which
TMI and TerreStar fully accept. There, the Bureau decided to extend by 11 months MCI‘s initial
construction milestone for one of its satellites even though no manufacturing contract had been
executed and no timely extension request had been filed. Here, by contrast, no extension was
asked for or needed, because a conforming, non—contingent satellite manufacturing contract was
executed. The MCI case thus provides no support whatsoever for license cancellation in these
circumstances.

                Norris: This was a very straightforward case in which the authorization holder
failed to make a down payment necessary to qualify its construction contract as non—contingent.
Norris did not challenge that finding of fact. Instead, it argued that regulatory delay and
uncertainties justified its failure to make the payments necessary to make the contract non—
contingent. But the Commission rejected this as a ground for waiver or extension. Payment to
Loral under the construction contract was not in arrears here and, therefore, Norris is inapposite.

                Tempo: This similarly straightforward case also does not support cancellation of
TMI‘s authorization. It involved the review of a one—year construction contract milestone for a
DBS license. Upon looking at the particulars of the contract, the Commission found that they
were specific enough to satisfy the initial milestone and there were no unresolved contingencies.
The Commission (para. 11) also noted: "We have acted adversely to applicants that were not
prepared to commit themselves to going forward with construction of a DBS system. That is not
the case here. Tempo has executed its contract and is willing to proceed." The same is also true
in the current case where a conforming, non—contingent construction contract indisputably
existed as of the milestone deadline (and continues in existence), and TMI and TerreStar are
willing and determined to proceed.

              We appreciate your careful review of the TMI/TerreStar case and are available as
needed to answer any further questions that might arise.

                                              Respectfully submitted,


Gregofi// C. S’taple                                          /Jonathan D. Blake
R. Edward Price                                          /   Gerard J. Waldron
VINSON & ELKINS L.L.P.                                       COVINGTON & BURLING
1455 Pennsylvania Avenue, N.W.                                1201 Pennsylvania Avenue, N.W.
Washington, DC 20004                                         Washington, DC 20004
Telephone: (202) 639—6500                                    Telephone: (202) 662—6000
Counselfor TMI                                               Counselfor TerreStar


Enclosure

CC.   Mr.   Bryan Tramont
      Mr.   John Rogovin
      Mr.   Roderick Porter
      Ms.   Jacquelynn Ruff
      Mr.   Karl Kensinger
      Ms.   Jennifer Manner
      Mr.   Barry Ohlson
      Mr.   Paul Margie
      Mr.   Sam Feder


                                                                            Sept. 23, 2003

                           SATELLITE MILESTONE ORDERS

A.       Revocation Cases Involving First Milestone

                             First Milestone: Non—
                            Contingent Construction
           Grantee          Contract in Compliance               Reasons for Revocation
                               with Authorization
TMI                                                    TMI, as the authorization holder, "did not
(GHz License, Feb. 10,                YES              enter into a satellite manufacturing
2003) DA 03—385                                        agreement," though it contracted with
                                                       TerreStar to do so and it did. In addition,
                                                      TMI did not "demonstrat[e] an investment
                                                      and commitment."
Commission Decisions|..‘ ... ; |                      t tt t
PanAmSat                                              PanAmSat did not enter into a non—
(Ka—band License, June   No                           contingent construction contract and failed
26, 2000)                                             to provide adequate justification for seeking
FCC 01—178                                            to extend its construction commencement
                                                      milestone.
Morning Star                                          Morning Star‘s contract (lacking any
Satellite Company                      No             construction or payment schedules) failed to
(Ka—band License,                                     meet the Commission‘s minimum
June 26, 2000)                                        requirements for a non—contingent contract.
FCC 01—179
Norris Satellite                                       Norris failed to make a critical installment
Communications                         No              payment to make its contract non—
(Ka—band License,                                      contingent. Norris‘s failure to make this
March 14, 1996)                                        payment prevented satellite construction
FCC 97—377                                             from commencing by the extended
                                                       authorization deadline.
BureauDecisions|__ ...                                 to
Globalstar                                             Globalstar‘s manufacturing contract
(2 GHz License, Jan. 30,               No              provided for construction pursuant to an
2003)                                                  implementation schedule at variance with
DA 03—328                                              the milestones in its license grant.
Motorola                                               Motorola did not enter into a non—contingent
(Ka—band License,                      No              contract and did not commence construction
Sept. 4, 2002)                                         of its Ka—band satellite system by the first
DA 02—416                                              milestone deadline.
Columbia                                               Despite grant of a seven month extension of
Communications                         No              the first milestone, Columbia failed to sign a
Corporation (C—band                                    manufacturing contract because of the
license, April 5, 2000)                                pendency of a merger with GE Americom.
DA 00—702




DC: 966300—1


                                                                            Sept. 23, 2003


Constellation                                           The "sharing agreement" that CCHI entered
Communications                         No               into with ICO was not a satellite
Holdings, Inc.                                          manufacturing contract. It was merely a
(2 GHz License, Jan. 30,                                contract for purchase of capacity if and
2003)                                                   when the satellites have been constructed,
DA 03—285                                               launched, and made ready for operation
                                                        pursuant to a separate contract over which
                                                        CCHI has no control.
Mobile Communications                                   The "sharing agreement" MCHI entered
Holdings, Inc.                         No               into with ICO was not a satellite
(2 GHz License, Jan. 30,                                manufacturing contract. It was merely a
2003)                                                   contract for purchase of capacity if and
DA 03—285                                               when the satellites have been constructed,
                                                        launched, and made ready for operation
                                                        pursuant to a separate contract over which
                                                        MCHI has no control.

B.       Reinstatement and Waiver Cases Involving First Milestone (selective)

mnavona ty
                              First Milestone: Non—
                             Contingent Construction
           Grantee                     .        .                   Reasons For Action
                             Contract in Compliance
                                with Authorization
The Boeing Company                                      The Bureau held that, Inter—organizational
(2 GHz MSS License,                    No               Work Authorization (IWA) between Boeing
June 24, 2003) DA 03—                                   IDS, a division of licensee, and Boeing
2073                                                    Satellite System met the first milestone.
                                                        Bureau also found there was compliance
                                                        although the IWA was for a GSO system
                                                        rather than a NGSO system, as originally
                                                        authorized.
EchoStar Satellite                                      License reinstated, on reconsideration,
Corporation (Ka—band                    No              based on additional evidence, as of the
license, November 8,                                    milestone date, as to the payload and power
2002) DA 02—3085                                        budget for the hybrid Ku/C/Ka band
                                                        satellites. Thus, Bureau finds that
                                                        construction contract did in fact cover the
                                                        authorized system.
Volunteers In Technical                                 Licensee was permitted to rely upon
Assistance ("Little LEO"                No              construction of a third party‘s satellite to
License, March 7, 1997)                                 meet milestone applicable to replacement
DA 97—501                                               satellite.




DC: 966300—1


Bureau Orders _           [                 :
                          First Milestone: Non—
       Grantee             Contmgen't Constru.ctlon                 Reasons For Action
                           Contract in Compliance
                              with Authorization
NetSat 28 Company LLC                                  Bureau waived construction milestone
(Ka—band License,                      No              granted and reinstated license even though
May 25, 2001) DA 01—                                   construction contract post—dated milestone
1284                                                   by approximately 18 months because
                                                       contract provided for timely completion of
                                                       satellite and launch and licensee had
                                                       expended over $10 million on system
                                                       development.
United States Satellite                                Construction contract milestone was held to
Broadcasting Company,                  No              be satisfied by licensee‘s having entered
Inc. (DBS License,                                     contract to purchase for 5 transponder
October 22, 1992) [Mass                                payload on third party‘s satellite (%.e.,
Media Bureau] DA 92—                                   without a separate manufacturing contract)
1462                                                   because the licensee had met payment
                                                       schedule to date under purchase contract.

C.     Bureau Orders Canceling Licenses after the First Milestone

        Grantee             First Milestone: Non—               Reasons for Revocation
                           Contingent Construction
                           Contract in Compliance
                              with Authorization
Mobile Communications                                  The Bureau concluded that MCHI failed to
Holdings, Inc. (Big LEO          Not Applicable        contract for all of its May 31, 2001
License, May 31, 2001)                                 authorized satellites by the milestone
DA 01—1315                                             deadline and thus violated its second
                                                       milestone requirement.
Constellation                                          Constellation did not certify completion of
Communications                   Not Applicable        its second and third construction milestones.
Holdings, Inc. (Big LEO                                The Bureau found that Constellation did not
License, Nov. 8, 2002)                                 provide sufficient grounds to justify an
DA 02—3086                                             extension of those milestone deadlines.
          *# kok                      * % *                                *# oo
Affirmed by full          Not Applicable, but FCC      Full Commission confirmed the Bureau‘s
Commission on             points out that it had not   findings and noted that as to 44 of 46 of
Reconsideration           concluded that a non—        Constellation‘s satellites, there was no
(September 17, 2003)      contingent construction      construction contract.
FCC 03—217                contract existed that
                          conformed with
                          Constellation‘s
                          authorization


E—SAT, Inc.                                          The Bureau concluded that E—SAT had not
(Little LEO License,            Not Applicable       demonstrated that it faced unforeseeable
April 23, 2003)                                      circumstances beyond its control requiring
DA 03—1113                                           an extension; nor were there unique and
                                                     overriding public interest concerns.
Loral                                                Loral did not complete construction of its
(Ka—band License,               Not Applicable       Orion satellites by the requisite milestone
April 1, 2003)                                       and the Bureau found no reason to extend
DA 03—1045                                           Loral‘s milestone schedule.




D.     Waiver Case after the First Milestone

        Grantee             First Milestone: Non—             Reasons for Revocation
                           Contingent Construction
                           Contract in Compliance
                              with Authorization
GE American                                          Bureau waived milestones on its own
Communications (Ka—             Not Applicable       motion based on facts showing licensee‘s
band License, May 25,                                "intent to proceed," noting that milestone
2001) DA 01—1286                                     waivers have been denied and licenses
                                                     cancelled only "where construction of the
                                                     satellite either had not begun or was not
                                                     continuing . .."



Document Created: 2019-04-11 20:25:59
Document Modified: 2019-04-11 20:25:59

© 2024 FCC.report
This site is not affiliated with or endorsed by the FCC