Sikorsky, A Lockheed Martin Company

1608-EX-ST-2020

Status: Pending

N/A
2020-10-15

Documents and Communications: [refresh]

DescriptionCategoryDate
E-Mail generated [Oct 15 2020]Correspondence2020-10-15
AFTRCC coordinationPre Coordination Document2020-10-15
Grant E-mail Notification generated [Oct 16 2020]Correspondence2020-10-16
Description of ExperimentationText Documents2020-10-15
Application Form:
OET Special Temporary Authority Report
FEDERAL COMMUNICATIONS COMMISSION
APPLICATION FOR SPECIAL TEMPORARY AUTHORITY

Applicant Name
Name of Applicant:  Sikorsky, A Lockheed Martin Company

Address
Attention: Ryan N. Terry
Street Address: 2121 Crystal Drive, Suite 100
P.O. Box:
City: Arlington
State: VA
Zip Code: 22202
Country:
E-Mail Address: [email protected]

Best Contact
Give the following information of person who can best handle inquiries pertaining to this application:  
Last Name: Terry
First Name: Ryan
Title: Director, Regulatory Licensing & Policy
Phone Number: 703-413-5747

Explanation
Please explain in the area below why an STA is necessary:
Applicant hereby seeks Special Temporary Authority (STA) under Part 5 of the Commission's rules for a period of six months to permit it to conduct flight testing operations of the Combat Rescue Helicopter in and around Eglin AFB. These operations support U.S. Air Force contract number FA8629-14-C-2403. The program requirement will expire with the end of this STA.

Purpose of Operation
Please explain the purpose of operation:  Flight test of the Combat Rescue Helicopter in and around Eglin AFB. Operations are intended to flight test the Combat Rescue Helicopter in and around Eglin AFB. Applicant has secured coordination from AFRTCC (attached). The term of this STA mirrors the AFTRCC coordination. The radius of operations is limited to 50 miles and 15000 feet AGL.

Information
Callsign: WR9XEK
Class of Station: MO
Nature of Service: Experimental

Requested Period of Operation
Operation Start Date: 10/30/2020
Operation End Date: 04/30/2021

Manufacturer
List below transmitting equipment to be installed (if experimental, so state) if additional rows are required, please submit equipment list as an exhibit:  
Manufacturer Model Number No. Of Units Experimental
Quasonix nanoPuck 5 No

Certification
Neither the applicant nor any other party to the application is subject to a denial of Federal benefits that includes FCC benefits pursuant to Section 5301 of the Anti-Drug Abuse Act of 1988, 21 U.S.C. Section 862, because of a conviction for possession or distribution of a controlled substance. The applicant hereby waives any claim to the use of any particular frequency or electromagnetic spectrum as against the regulatory power of the United States because of the prvious use of the same, whether by license or otherwise, and requests authorization in accordance with this application. (See Section 304 of the Communications Act of 1934, as amended.) The applicant acknowledges that all statements made in this application and attached exhibits are considered material representations, and that all the exhibits part hereof and are incorporated herein as if set out in full in this application; undersigned certifies that all statements in this application are true, complete and correct to the best of his/her knowledge and belief and are made in good faith. Applicant certifies that construction of the station would NOT be an action which is likely to have a significant environmental effect. See the Commission's Rules, 47 CFR1.1301-1.1319.
Signature of Applicant (Authorized person filing form): Ryan Neels Terry
Title of Applicant (if any): Director, Regulatory Licensing & Policy
Date: 2020-10-15 00:00:00.0

Station Location
City State Latitude Longitude Mobile Radius of Operation
Eglin AFB Florida North  30  39  15 West  86  31  33 Eglin AFB, FL: Airborne 15,000 ft. AGL 81.00
Datum:  NAD 83
Is a directional antenna (other than radar) used?   No
Exhibit submitted:   No
(a) Width of beam in degrees at the half-power point:  
(b) Orientation in horizontal plane:  
(c) Orientation in vertical plane:  
Will the antenna extend more than 6 meters above the ground, or if mounted on an existing building, will it extend more than 6 meters above the building, or will the proposed antenna be mounted on an existing structure other than a building?   No
(a) Overall height above ground to tip of antenna in meters:  
(b) Elevation of ground at antenna site above mean sea level in meters:  
(c) Distance to nearest aircraft landing area in kilometers:  
(d) List any natural formations of existing man-made structures (hills, trees, water tanks, towers, etc.) which, in the opinion of the applicant, would tend to shield the antenna from aircraft:
Action Frequency Station Class Output Power/ERP Mean Peak Frequency Tolerance (+/-) Emission Designator Modulating Signal
New 2373.50000000- MHz MO 5.000000 W 5.000000 W P 10M0F9D
Action Frequency Station Class Output Power/ERP Mean Peak Frequency Tolerance (+/-) Emission Designator Modulating Signal
New 2384.50000000- MHz MO 5.000000 W 5.000000 W P 10M0F9D

16159

© 2024 FCC.report