SCOPE
This document captures the LTE network specific elements of the Cubic Balboa Campus Demo for development and demonstration. License request is based on previous
experimental license WJ2XIN effective MAR 13 2018 to NOV 13 2018. We lowered our level of radiated power compared to our previous license to facilitate operation with
other licensees in the band.


DEMO OBJECTIVE
Develop Cubic’s LTE capability and integrate into Cubic’s products and systems. Demonstrate LTE capability for internal and external customers.

TECHNICAL REQUIRMENTS

Shall = objective

Should = target

Requirement       Description:                                                                                        Comments:
CD1               The demonstration shall comprise 4 x ‘4G network in the box’ using BlackWolf and Attocore or        Attocore is work in progress. Quortus does crash.
                  Quortus embedded EPC                                                                                Blackwolf still in development, B28 variant does not
                                                                                                                      yet exist
CD2               Each 4G ‘network in the box’ shall be linked to each other using either Cambium point to point
                  units or ubiquity point to point WiFi units.
CD3               The deployment shall support inter network handover.                                                Complete.
CD4               The 4G network shall radiate in the spectrum band designated as B28.                                FFC application submitted

CD5               Each 4G network shall radiate on a specific and unique EARFCN.                                      FFC application submitted.

CD6               2 of the ‘4G network in the box’ shall be mounted to a tethered drone at a height of no more than   Integration in progress.
                  100m and using omni-directional antennas
CD7               2 of the ‘4G network in the box’ shall be mounted to a mast at a height of no more than TBDm        Mast height and type information is not yet available
CD8               For the 2 mast mounted ‘4G network in the box’ systems, the antenna shall be: LNX-8513DS-VTM        Ordered


CD9                The antenna feeder cables shall be: https://www.fairviewmicrowave.com/n-male-7-16-female-        Ordered
                   cable-0.250-formable-low-pim-coax-fmc0136925-100cm-p.aspx

DEMO PLANNING

The drone/mast shall be located at location: 34 49’ 17” N, 117 7’ 43” W (Cubic’s Balboa Campus) with operational range within the boundaries of Cubic’s property
(~0.25km radius).

Antenna is omni directional. We intend to transmit at 63mW for our base station and at 20mW for our mobile units.

The BWB281W antenna will be deployed at a height of 7.32m in the areas designated in Figure 1 in blue. These areas will be used for testing and demonstration. Buildings
and trees in the area that will shield the antenna from aircraft are designated in Figure 1.




Figure 1: Demo Areas (Blue) and Shielding from Aircraft


LTE EQUIPEMNT
DE1             2 of B28 BlackWolf with integrated EPC plus 2 spare (mast mount)    B28 BlackWolf needs to be built                      TBC
DE2             2 of B28 BlackWolf with integrated EPC plus 2 spare (drone mount)   B28 BlackWolf needs to be built – lightweight
                                                                                    enclosure for drone
DE3             4 of LNX-8513DS-VTM plus 2 spare                                    Antenna order (for 6 antennas) to be placed by       TBC
                                                                                    9/Feb/18
DE4             Drone antenna set                                                   Antenna order (for 4 antenna sets) to be placed by
                                                                                    9/Feb/18
DE5             https://www.fairviewmicrowave.com/n-male-7-16-female-cable-0.250-   Order to be placed by 9/Feb/18                       TBC
                formable-low-pim-coax-fmc0136925-100cm-p.aspx
DE6             BlackWolf GPS antenna                                               Order to be placed by 9/Feb/18




ROLES AND RESPONSIBI LITIES

      -   Network Setup: Cubic
      -   Network Operation: Cubic
      -   Equipment: Cubic



Document Created: 2019-04-30 11:34:25