QUESTION 4 STATEMENT REGARDING GOVERNMENT CONTRACT

0391-EX-CN-2018 Text Documents

General Dynamics Land Systems

2018-05-17ELS_209811

                       ABRAMS FAMILY OF VEHICLES (FOV)
                    SYSTEMS TECHNICAL SUPPORT (STS) AND
                SUSTAINMENT SYSTEMS TECHNICAL SUPPORT (SSTS)
                              WORK DIRECTIVE
                              W56HZV-17-C-0067


Contractor:                                    Work Directive (WD) No: 2023
General Dynamics Land Systems, Inc.            Date Original WD Issued: 28-Sep-17
                                               WD Supplement No: 12
                                               Date Supplement Issued: 26-Oct-17
Category: Engineering




WD Description: US Army Trophy HV Vehicle Protection System (VPS) Support For
Fielding under an Urgent Material Release (UMR)
Performance Completion Date: Date of WD award through 29-Mar-19
Relevant Statement of Work Sections: C.1.1, C.1.5, C.2.1, C.2.2, C.4.3, C.6.1, C.6.2,
C.8.2, C.11.11, C.11.12, C.19.1
CLIN Number: 2023AA
Type: Completion form in accordance with FAR 16.306(d)(1)



                  Element               Prior Balance   This Revision   Current Balance
 Estimated Cost                          $9,083,957                       $9,083,957
 Fixed Fee                                $816,038                         $816,038

 Total Estimated CPFF                    $9,899,995                       $9,899,995


1.0 Objective


    1.1    The objective of this effort is to support an Urgent Materiel Release (UMR)
           and have First Unit Equipped of Trophy installed on an Armor Brigade
           Combat Teams M1A2 SEPv2. The United States Government (USG)
           schedule is the current baseline/reference for overarching project and is
           provided as Government Furnished Information (GFI).


    1.2    This WD provides engineering technical services, problem resolution during
           integration of a Vehicle Protection System (VPS) onto an Abrams platform,
           and test site support during USG testing. The effort takes the initial A-kit
                                                                            Page 1 of 18


                                                                              WD#: 2023
                                US Army Trophy HV VPS Support for Fielding under an UMR

           design (developed under WD 2008 on contract W56HZV-17-C-0067) and
           refines it to include additional integration, fabrication of A-kits to support
           USG testing, logistic products development, and increased capability of the
           Trophy integrated software.


   1.3     Background: The USG has a Government-to-Government agreement with
           Israel. The agreement allows direct interaction with the Israeli Ministry of
           Defense whom provide the support from the Trophy system OEM (Rafael).
           Rafael support provides the technical expertise to operate the Trophy
           system, measure overall Trophy performance, and provide/collect test data.
           The awarded WD with GDLS allows for engineering services, problem
           resolution for the A-kit, and test site support during the USG UMR phase.


2.0 Applicable Documents


   2.1     Previous Contract Deliverables


         2.1.1      Final (Release 2) A-kit models and Level 2 Drawings


         2.1.2      Final Overall Vehicle Analysis Report


         2.1.3      Weight and CG Report


         2.1.4      Installation Instructions


         2.1.5      A-Kit SAR


         2.1.6      Characterization test data


   2.2     Requirements Documents


         2.2.1      Abrams SEPv2 2004 System Specification SA-SA00001D 04 April
                    2004


         2.2.2      Updated Trophy HV VPS ICD (Interface Control Document)
                    Models



                                                                              Page 2 of 18


                                                                         WD#: 2023
                           US Army Trophy HV VPS Support for Fielding under an UMR

2.3     Government Furnished Information or Material


      2.3.1      Abrams APS Phase 2 and 3 Schedule – see supplemental
                 information                                                            Commented [SMA1]: Suggest both require updating



      2.3.2      Abrams Security Classification Guide Dated 2 Feb 2017                  Commented [SMA2]: Update needed?



      2.3.3      Updated Trophy HV VPS Security Classification Guide (to be
                 delivered Nov Jan 17)


      2.3.4      Updated Trophy Program Security Information Document
                 (to be delivered Nov Jan 17)


      2.3.5      TARDEC Characterization Report (to be delivered Nov Feb 17)


      2.3.6      TARDEC Scan (CAD) of SEPv2 turret (Tank used during Camp
                 Grayling Tuning)


      2.3.7      Installation Red Lines, user evaluation notes and lessons learned
                 from TARDEC, RTC and YTC


      2.3.8      One (1) Trophy System without countermeasures (live or inert;
                 includes B-kit, and harnesses)


      2.3.9      Four (4) Energy Storage Units (ESUs)


      2.3.10     Abrams M1A2 SEPv2 (SN: LS12012M)


      2.3.11     Translated B-Kit Supporting Documentation (i.e. Operators
                 Manuals, Maintenance Manuals, Training Material)                       Commented [SMA3]: Suggest removal of the items
                                                                                        we will not be getting as it has been indicated we will
                                                                                        only receive the operators manual
      2.3.12     Monolith bracket from the 1st A-kit fabricated by USG


      2.3.13     Updated Trophy HV VPS ICD (Interface Control Document)
                 Models (to be delivered 30 days after award of the Project             Commented [SMA4]: Assumption is being made here
                 Agreement with the Israeli Ministry of Defense, January 2018)          that since this is beyond the design window (all
                                                                                        drawings will be released before this), any updates to
                                                                                        the ICD will not be expected to be incorporated for May
                                                                                        delivery. This includes the hydraulic reloader.
                                                                         Page 3 of 18


                                                                             WD#: 2023
                               US Army Trophy HV VPS Support for Fielding under an UMR

         2.3.14    Updated Trophy HV VPS Computer Aided Design (CAD) Models
                   (to be delivered 60 days after award of the Project Agreement with
                   the Israeli Ministry of Defense, January 2018)                        Commented [SMA5]: See above comment



3.0 Requirements Engineering


   3.1     Start of Work Meeting (SOWM)


         3.1.1     The contractor shall host and conduct a Start of Work Meeting to
                   introduce and align the Government and contractor teams. The
                   SOWM shall consist of a Scope of Work review and schedule
                   review. The contractor shall deliver Meeting Minutes, IAW Contract
                   Data Requirements List (CDRL) A001 and Presentation Materials,        Commented [SMA6]: Request removal of the
                   IAW CDRL A002.                                                        presentation materials CDRL if possible, and to instead
                                                                                         deliver the presentation material the day before the
                                                                                         SEIT meetings as was done on CLIN 2008.
         3.1.1
                                                                                         Formatted: List Paragraph, Right: 0.11", Outline
   3.2     Systems Engineering Integration Team (SEIT) Meetings                          numbered + Level: 3 + Numbering Style: 1, 2, 3, … +
                                                                                         Start at: 1 + Alignment: Left + Aligned at: 0.77" +
                                                                                         Indent at: 1.62", Tab stops: 1.62", Left + 1.62", Left
         3.2.1     The contractor shall conduct Government-contractor Trophy VPS
                   HV SEIT meetings with the contractor’s technical team starting two
                   weeks after contract award. The purpose of these meetings are to
                   present updates to Logistics products and Technical Data
                   Package/Engineering Change Proposal (TDP/ECP) development,
                   identify technical issues and corrective actions, and identify
                   program and technical risks. Identified risks shall follow the
                   contractor’s processes for risk management. The Trophy VPS HV
                   SEIT shall not be combined with the STS OAIPT. The contractor
                   shall deliver Meeting Minutes, IAW Contract Data Requirements
                   List (CDRL) A001 and Presentation Materials, IAW CDRL A002.


   3.3     APS A-Kit Requirements Meeting


         3.3.1     The contractor shall host one APS A-Kit Requirements Meeting.
                   At the meeting, all stakeholders shall define current kit
                   deficiencies, Energy Storage Unit (ESU) modifications, SW
                   requirements, user inputs and changes to kit required for first
                   brigade fielding design. The Requirements Meeting may be held in
                   place of one SEIT meeting. The contractor shall deliver Meeting
                   Minutes, IAW CDRL A001 and Presentation Materials, IAW CDRL
                   A002.



                                                                          Page 4 of 18


                                                                             WD#: 2023
                               US Army Trophy HV VPS Support for Fielding under an UMR

   3.4     Interim Program Review (IPR)


         3.4.1      The contractor shall host one Interim Program Review (IPR). The
                    contractor shall provide and brief the COR on the findings up to the
                    date at the IPR. The IPR shall cover TDP, ESU, software (SW),
                    Logistics products updates, and status on A-kit fabrication. The
                    IPR date in the milestone schedule may be moved with COR
                    approval. The IPR may occur in the place of one of the SEIT
                    meetings. The contractor shall deliver Meeting Minutes, IAW
                    CDRL A001 and Presentation Materials, IAW CDRL A002.


4.0 Design and Integration


   4.1     The M1A2 SEPv2 provided as GFE shall be used to support all aspects of
           this WD. The vehicle shall be returned to the USG via shipment to Camp
           Grayling to meet Camp Grayling need dates.


   4.2     Technical Data Package (TDP) Finalization


         4.2.1      Drawing Refinement


                             The contractor shall refine and update drawings based on
                             the APS Requirements Meeting and SEIT meetings, as
                             approved by the COR. The contractor shall use lessons
                             learned from A-Kit hardware installation on the M1A2
                             SEPv2 and from trial fit activities, user evaluations, and
                             field testing at Camp Grayling, MI, Redstone Test Center
                             (RTC), Alabama, and Yuma Test Center (YTC), Arizona.
                             The drawings shall be converted to full Level 3 production
                             drawings that can be provisioned using normal USG
                             standards and deliver the drawings with the ECP (WD
                             paragraph 8.1).


                             The contractor shall incorporate the recommended
                             revisions from Tank Automotive Research, Development
                             and Engineering Center (TARDEC) that will be provided
                             as GFI and deliver the drawings with the ECP (WD
                             paragraph 8.1).




                                                                            Page 5 of 18


                                                                         WD#: 2023
                           US Army Trophy HV VPS Support for Fielding under an UMR

                         The contractor shall incorporate kit updates, which at a
                         minimum shall include: removal of Experimental
                         Operating Box (EOB) and Explosive Ordnance (EOD)
                         box, imbalance related kit modifications, ESU diagnostics
                         related drawings and cable redesign, and harness
                         drawing modifications and deliver the drawings with the
                         ECP (WD paragraph 8.1).


4.3     Energy Storage Unit (ESU)


      4.3.1     The contractor shall refine the ESU design to provide the usage
                hours on the Trophy APS software user interface. The refined
                design requires software modification to provide the usage hours.
                The modification is to be implemented into the ESUs provided as
                GFE and the six new units to be delivered IAW section 3.6.3. The
                contractor shall update the ESU and cables to include diagnostics
                including voltage level over RS422 serial communications to
                include circuit board redesign. The changes shall be incorporated
                into the integrated Trophy software that is part of the Abrams
                M1A2 SEPv2 SW version 4.6.1.


      4.3.2     The contractor shall update and deliver the four GFE provided
                ESUs to the latest configuration (WD paragraph 4.3.1). The
                delivery schedule of these upgraded ESUs is in WD paragraph 7.0.


      4.3.3     The contractor shall build two ESUs to be used for qualification
                testing. The ESUs shall be considered end of life (EOL) at the
                completion of qualification testing. The contractor shall deliver the
                EOL ESUs to the USG no later than 30 calendar days after
                completion of qualification testing.


      4.3.4     ESU Qualification Test Plan and Report


                         The contractor shall develop an ESU Qualification Test
                         Plan and deliver it IAW CDRL A003 for COR approval
                         prior to entering into qualification testing (WD paragraph
                         4.3.4.2). The contractor shall conduct an ESU
                         Qualification Readiness Review during a SEIT meeting.


                         ESU Qualification Testing: The contractor shall conduct
                         Qualification testing on the ESU in accordance with the

                                                                          Page 6 of 18


                                                                           WD#: 2023
                             US Army Trophy HV VPS Support for Fielding under an UMR

                           contractor developed Critical Item Development
                           Specification (CIDS) and the COR approved Test Plan.


                           ESU Qualification Test Report: After testing is completed,
                           the contractor shall develop and deliver an ESU
                           Qualification Test Report IAW CDRL A061.


4.4     Engineering Trial Fit: The contractor shall conduct an engineering trial fit.
        The trial fit shall verify the fabrication and install against the developed A-kit
        TDP. Any issues found during the trial fit shall be corrected and updated in
        the A-kit TDP. The USG shall witness the engineering trial fit. The COR
        shall approve the engineering trial fit and, if any, corrections need to occur to
        be updated in the A-kit TDP. The contractor shall provide a summary of all
        discovered issues, if any, during a SEIT meeting.


4.5     APS Supplier B-kit Development


      4.5.1       B-kit cable length: GDLS shall provide the APS vendor with the B-
                  kit cable lengths to account for Abrams unique integration. APS B-
                  kit cable development results shall be presented at the SEIT for
                  COR approval.


      4.5.2       B-kit calibration requirements: The contractor shall develop a
                  process to provide turret angle and gun tube elevation to the APS
                  vendor to be used for calibration of the Trophy system once
                  installed on the M1A2 SEPv2. The contractor’s identified process
                  shall be presented at the IPR for COR approval.


4.6     Appurtenance Fixtures - Development for A-kit installation


      4.6.1       The contractor shall develop and build one (1) each fixtures to
                  install the APS A-Kit Monolith bracket to the left and right side of
                  the M1A2 SEPv2 vehicle.


4.7     Investigations/Resolution into Main Electronics Box (MEB) Power Issue


      4.7.1       The contractor shall jointly conduct a RCCA by providing technical
                  expertise to the Trophy OEM to determine the cause of MEB
                  power issues observed during 2017 USG characterization testing.


                                                                             Page 7 of 18


                                                                                WD#: 2023
                                  US Army Trophy HV VPS Support for Fielding under an UMR

          4.7.2      The contractor shall design a mechanical solution if required to
                     mitigate MEB shock issues and incorporate into the A-kit design.


    4.8     Resolve Imbalance Issue participate


          4.8.1      The contractor shall support the USG in developing a near-term
                     mitigation path for turret imbalance. This shall include building and
                     delivering one (1) CREW II environmental cover (replacing
                     armored cover); one (1) TMS environmental cover (replacing
                     armored cover); and delivering (during a SEIT meeting as part of
                     the presentation materials) a stowage plan for movement of
                     stowage from the extended bustle rack to the tank hull and hull
                     ammo compartment.


5.0 Logistics


    5.1     APS A-Kit Logistics


          5.1.1      A-Kit Draft Operator Technical Manual (TM) pages: The contractor
                     shall develop draft A-kit Operator Technical Manual pages in
                     support of test. The contractor shall train USG test personnel on
                     draft APS A-Kit Operator pages prior to test, providing 5 paper
                     copies of draft APS A-Kit operator manual pages at the time
                     training is conducted.


          5.1.2      A-Kit Technical Manual Development: The contractor shall develop
                     and validate the A-Kit Technical Manual. The contractor shall
                     attend and provide technical expertise to the USG’s verification
                     activities of the A-kit (to include SW 4.6.1 integration) 13&P
                     Operator, Maintainer, and Repair Parts and Special Tools List
                     (RPSTL) Technical Manuals. The contractor shall include APS A-
                     kit installation and removal instructions in the A-kit 13&P TM. The
                     contractor shall deliver the 13&P Technical Manual in accordance
                     with CDRLs A069, A071, and A072, according to the following
                     schedule: PTM 1 shall be due no later than 30 days after
                     Validation. PTM 2 shall be due no later than 30 calendar days prior
                     to Verification. PTM 3 shall be due no later than 30 calendar days
                     after Verification.


          5.1.3      A-Kit Operator Training: The contractor shall develop and deliver
                     Training Program of Instruction (POI) for A-kit Operator TM

                                                                              Page 8 of 18


                                                                         WD#: 2023
                           US Army Trophy HV VPS Support for Fielding under an UMR

                (including SW 4.6.1 integration) in accordance with CDRL A003
                and conduct Instructor and Key Personnel Training (I&KPT) for
                government Operator’s New Equipment Training (OPNET) Team
                for A-kit Operator TM and Trophy B-Kit Operator TM (using
                translated Trophy POI's). The contractor shall conduct two
                calendar day operator trainings to 10 USG personnel at each of
                the test sites (Aberdeen Test Center (ATC), RTC, and YTC) using
                draft APS A-Kit Operator TMs.


      5.1.4     A-Kit Field Maintenance Manual Training: The contractor shall
                develop and deliver Training POI for A-kit Maintenance TM
                (including SW 4.6.1 integration) in accordance with CDRL A003
                and conduct I&KPT for government Field Level Maintenance New
                Equipment Training (FLMNET) Team for A-kit Maintenance TM
                and Trophy B-kit Maintenance TM (using translated Trophy POI's).
                The contractor shall conduct five calendar day maintenance
                trainings to 10 USG test personnel at each of the test sites (ATC,
                RTC, and YTC) using draft APS A-Kit Field Maintenance TMs.


      5.1.5     A-Kit Long Life Reusable Container: The contractor shall develop a
                Long Life Reusable Container (LLRC) for A-kits (to support
                install/de-install/accountability). Pre-modification hardware shall
                be segregated within the container. The contractor shall deliver
                LLRC drawings to the USG in accordance with CDRL A066 and
                the milestone schedule in 7.0 (not the delivery dates in CDRL
                A066).


      5.1.6     A-Kit Provisioning: The contractor shall provision and deliver all
                field level replaceable parts and A-kit packaging data per the
                Engineering Data For Provisioning (EDFP) CDRL A088 and
                Provisioning Parts List CDRL A089. The contractor shall deliver
                CDRL A088 IAW the milestone schedule in 7.0 (not the delivery
                dates in the CDRL).


5.2     APS B-Kit MIL STD Logistics Wrap Around


      5.2.1     Operator TM: The contractor shall develop, validate, and deliver
                MIL STD wrapper around translated Trophy B-kit Operator TM and
                support verification of the MIL STD wrapped B-Kit Operator TM
                IAW CDRL A069. The contractor shall deliver the Operator Manual
                in accordance with CDRL A069, according to the following
                schedule: PTM 1 shall be due no later than 30 days after
                Validation. PTM 2 shall be due no later than 30 calendar days prior

                                                                         Page 9 of 18


                                                                              WD#: 2023
                                US Army Trophy HV VPS Support for Fielding under an UMR

                    to Verification. PTM 3 shall be due no later than 30 calendar days
                    after Verification.


         5.2.2      Maintenance TM: The contractor shall develop, validate, and
                    deliver MIL STD wrapper around translated Trophy B-kit
                    Maintenance TM and support verification of the MIL STD wrapped
                    B-Kit Maintenance TM IAW CDRL A072. The contractor shall
                    deliver the Operator Manual in accordance with CDRL A069,
                    according to the following schedule: PTM 1 shall be due no later
                    than 30 days after Validation. PTM 2 shall be due no later than 30
                    calendar days prior to Verification. PTM 3 shall be due no later
                    than 30 calendar days after Verification.


   5.3     APS A-Kit and B-Kit Installation Instructions


         5.3.1      The contractor shall develop, validate, and support the verification
                    of the installation kit application. The contractor shall deliver draft
                    modification instructions to support A-kit and B-kit installation at the
                    test sites. The standard Abrams Reactive Armor Tile (ARAT) 2
                    weldments do not need to be included in the installation
                    instructions, as they are covered in a separate TM and
                    Modification Work Order (MWO). The installation kit and final
                    modification instructions shall be included in the A-Kit13&P TM.
                    The installation instructions shall follow the same documentation
                    requirements as a MWO. The draft instructions shall be due no
                    later than 30 calendar days prior to the Engineering Trial Fit (WD
                    paragraph 4.4).


6.0 UMR Testing:


   6.1     Test sites: The tests sites that require support for UMR testing are:
           Aberdeen Test Center (ATC), White Sands Missile Range (WSMR), Camp
           Grayling, RTC and YTC. Testing will take up to one year, starting as early
           as November 2017. USG testing will occur concurrently at the test sites.


   6.2     APS A-Kit and B-Kit Installation Support: The contractor shall provide full
           time Field Engineering Representatives (FER) support to the USG
           installation and checkout of APS A-Kit and B-Kit in support of UMR testing at
           each test location. Each installation will to take a maximum of two weeks to
           install the A-kit and B-kit. The contractor shall provide on-call reach back
           support from contractor design engineers in the event of any test related
           issues.

                                                                              Page 10 of 18


                                                                              WD#: 2023
                                US Army Trophy HV VPS Support for Fielding under an UMR

   6.3     UMR Testing Engineering Support: The contractor shall support USG UMR
           testing with FERs. The contractor shall plan for six months of on call
           support at each of the following test sites WSMR, ATC, YTC and RTC, for a
           total of 18 months of testing. The engineering support shall include
           assessment, root-cause analysis, and mitigation of any A-Kit findings found
           during testing. The FER shall maintain daily an Engineering Logistics and
           Status report that the USG can access if requested. The contractor shall
           provide on-call reach back design engineering support throughout testing for
           any issues that require assistance to the USG test centers and FER.


   6.4     Camp Grayling Testing:


         6.4.1      The contractor shall ship the GFE vehicle from GDLS Sterling
                    Heights to Camp Grayling to support APS Original Equipment
                    Manufacturer (OEM) SW checkout. The contractor shall remove
                    the components applicable for shipping operations according to the
                    Trophy Security Classification Guide prior to shipping the vehicle.
                    The vehicle shall be shipped with the A-kit installed and the
                    remaining GFE B-kit. The contractor shall re-install the B-kit
                    components at Camp Grayling that were removed prior to
                    shipping. Upon completion of testing at Camp Grayling, the
                    contractor shall coordinate for shipping the vehicle back to GDLS
                    Sterling Heights.


         6.4.2      The contractor shall provide one FER for the complete period of
                    testing at Camp Grayling, which is planned for five (5) weeks. The
                    USG will notify the contractor 90 calendar days prior to the planned
                    start of testing.


   6.5     Safety Assessment Report (SAR): The contractor shall update an A-Kit
           Safety Assessment Report (SAR) which was delivered under the STS
           contract CLIN 1022. The A-Kit SAR shall be updated prior to the start of
           USG testing (Initial) and upon completion (Final) of the Engineering Trial Fit.
           The SARs shall be delivered in accordance with CDRL A040.


   6.6     Army Board Review Support: The contractor shall support the Army Fuze
           and Safety Review Board (AFSRB), Insensitive Munition Board and
           Software Safety Boards. The support shall include coordination with the
           USG and preparation of presentation materials for to the review boards IAW
           CDRL A002.


7.0 Hardware Delivery

                                                                             Page 11 of 18


                                                                          WD#: 2023
                            US Army Trophy HV VPS Support for Fielding under an UMR

7.1     Hardware to be delivered to the test site locations for UMR testing includes:


7.2     The contractor shall deliver eight ESUs to support UMR testing.


      7.2.1      Four GFE ESUs shall be updated to the configuration specified in
                 WD paragraph 4.3.1.


                          Two ESUs will be delivered by the USG to the contractor
                          as GFE no later than 30 calendar days after WD award.
                          The contractor shall deliver the updated ESUs to the USG
                          no later than 4 months after GFE delivery.


                          Two ESUs will be delivered to the contractor as GFE no
                          later than 6 months after WD award. The contractor shall
                          deliver the updated ESUs to the USG no later than 30
                          calendar days after ESU qualification testing is complete.


      7.2.2      Four ESUs shall be built to the new configuration as specified in
                 WD paragraph 4.3.1.


                          Two ESUs shall be delivered 4 months after WD award.


                          Two ESUs shall be delivered to the USG no later than 30
                          calendar days after ESU qualification testing is complete.


      7.2.3      The ESUs used in qualification testing are not counted as part of
                 these eight ESUs.


7.3     The contractor shall deliver six (6) complete APS A-Kits to the USG. The
        complete A-kit consists of wiring harnesses, cable guards, monolith
        brackets, weldments, bosses, and any other material required for installing
        the A-kit and hosting the B-kit. The contractor shall develop and present an
        A-Kit delivery plan at a SEIT Meeting that best matches USG test plan. One
        (1) A-kit shall include modified CREW II and TMS (non-armored)
        enclosures.


7.4     A-Kit System Support Package (SSP)



                                                                          Page 12 of 18


                                                                                WD#: 2023
                                  US Army Trophy HV VPS Support for Fielding under an UMR

            7.4.1      The contractor shall develop lists of recommended SSP items for
                       each test site (ATC, WSMR, Camp Grayling, RTC and YTC),
                       including rationale, and present at a SEIT Meeting.


            7.4.2      The contractor shall provide one (1) A-Kit SSP at each test site.


8.0     Engineering Change Proposal (ECP) and Engineering Release Record (ERR)


      8.1     Upon successful completion of the Engineering Trial Fit and incorporation of
              discovered issues, the contractor shall deliver an ECP releasing the APS A-
              kit to the M1A2 SEPv2 TDP to the COR for approval. The contractor shall
              treat ECP routing in the “urgent” status as defined in CDRL A123. The
              contractor shall deliver the ECP in accordance with CDRL A123.


      8.2     The contractor shall process an ERR upon the USG approval of the ECP.
              The contractor shall deliver the ERR in accordance with CDRL A122.


9.0 Contract Data Requirements List (CDRL) Deliverables


      9.1     A001 – Record of Meeting Minutes, Report


      9.2     A002 – Presentation Material


      9.3     A003 – Technical Report


      9.4     A006 – Engineering, Logistics, and Program Management Work Directive
              Performance & Cost Report (PCR) shall be submitted for this WD under the
              Program Management WD #1000


      9.5     A040 – Safety Assessment Report


      9.6     A061 – Test/Inspection Program Report


      9.7     A066 – Long Life Reusable Container


      9.8     A069 – A-Kit Draft Operator Technical Manual (TM) pages


                                                                              Page 13 of 18


                                                                              WD#: 2023
                                US Army Trophy HV VPS Support for Fielding under an UMR

   9.9     A071 - Field Maintenance Technical Manual for Abrams Tanks


   9.10    A072 – A-Kit Technical Manual Development


   9.11    A078 – Installation Instructions


   9.12    A088 – A-kit Provisioning


   9.13    A089 – Provisioning Parts List


   9.14    A122 – Engineering Release Record


   9.15    A123 – Engineering Change Proposal


10.0   Delivery Schedule


                                                     Delivery Date (Calendar Days)
GFI & Vehicle provided to contractor          30 days after Work Directive Award (WDA)
2 ESUs provided to contractor                 30 days after WDA
2 ESUs provided to contractor                 6 months after WDA
1 Trophy B-Kit to contractor                  4 months after WDA
Start of Work Meeting (SOWM)                  7 days after WDA
First SEIT Meeting                            7 days after SOWM, and then Bi-weekly
APS A-kit Requirements Meeting                2 weeks after SOWM
                                              Presented a SEIT 2 weeks after the
SW Development Plan
                                              Requirements Meeting
                                              30 days prior to the start of Qualification
ESU Qualification Test Plan
                                              testing
                                              1 week after COR approved ESU
ESU Qualification Readiness Review            Qualification Test Plan
B-kit Cable Length                            90 days after WDA
IPR                                           90 days after SOWM
                                              Initial – 60 days prior to the start of USG
                                              testing
A-Kit Safety Assessment Report
                                              Final – 60 days prior to the start of USG
                                              OT

                                                                              Page 14 of 18


                                                                               WD#: 2023
                                 US Army Trophy HV VPS Support for Fielding under an UMR

 A-Kit Operator Training                     No later than 15 days prior to the start of
                                             testing
 A-Kit Field Maintenance Manual Training     No later than 15 days prior to the start of
                                             testing
 Engineering Data For Provisioning           Draft – Due at the start of USG testing
 (EDFP) CDRL A088                            Final – Due at the end of USG OT testing
 Engineering Trial Fit                       60 days after IPR
                                             60 days after the completion of
 ESU Qualification Test Report
                                             Qualification testing
                                             30 days after Completion of the
 Engineering Change Proposal
                                             Engineering Trial Fit
 Engineering Release Record (ERR)            30 days after the ECP



11.0   Exit Criteria


   11.1     The completion of UMR test site support and submission of the ECP and
            Installation Instructions for USG approval.


12.0   Schedule




                                                                            Page 15 of 18


                                              WD#: 2023
US Army Trophy HV VPS Support for Fielding under an UMR




                                          Page 16 of 18


                                                                                  WD#: 2023
                                    US Army Trophy HV VPS Support for Fielding under an UMR




13.0   Supplemental Information


   13.1    Supplement 1 fixes an administrative error in WD paragraphs 9.5 and 6.5.
           The SAR is changed from A031 to the correct CDRL number A040.




                           Government Concurrence / Approval




PCO           X                                        Approval
                                                       Date:
                                                                     27 October 2107
              Lisa Behnke
              Contracting Officer




                                                                              Page 17 of 18


                                              WD#: 2023
US Army Trophy HV VPS Support for Fielding under an UMR




                                          Page 18 of 18



Document Created: 2018-05-14 13:04:26
Document Modified: 2018-05-14 13:04:26