Attachment Attachment 1

This document pretains to SES-STA-20190604-00724 for Special Temporal Authority on a Satellite Earth Station filing.

IBFS_SESSTA2019060400724_1716800

Telesat Canada                                                                                      Attachment 1


                      REQUEST FOR SPECIAL TEMPORARY AUTHORITY


         Telesat Canada (“Telesat”), pursuant to Section 25.120 of the Commission’s rules,
hereby requests Special Temporary Authority (“STA”) to operate two earth stations - one located
in Pompano Beach, Florida and the other located in Melbourne, Florida - to conduct loop-back
tests with Telesat’s non-geostationary orbit (“NGSO”) low earth orbit satellite, LEO 1. Telesat
seeks an STA for the 30-day period beginning on August 6, 2019. The technical specifications
for these operations are set forth in Attachment 2a and 2b hereto, which provides the information
that would be appear in Schedule B of FCC Form 312, if regular authority were being sought.
         LEO 1 was launched in January 2018 and is currently in its final mission orbit of 99.5°
(circular) at an altitude of 1000 km. Telesat will operate LEO 1 pursuant to the requested STA
in accordance with the technical parameters that were specified in Telesat’s Petition for
Declaratory Ruling to Grant Access to the U.S. Market for Telesat’s NGSO Constellation
(“PDR”), including Schedule S thereto, which was granted by the Commission by Order and
Declaratory Ruling, released November 3, 2017.1 STA operations will be limited to two of the
bands covered by the PDR, i.e., 28.6-29.1 GHz (Earth-to-space) and 18.8-19.3 GHz (space-to-
Earth), which the Commission’s Ka-band plan allocates on a primary basis to NGSO operations.
         In accordance with Section 25.120, the earth stations will operate on a non-interference
basis. The communications to be made under the STA will be used to test, validate, and
demonstrate certain design features of LEO-1, including antenna tracking, RF performance, and
end-to-end network performance. These operations will set the stage for providing highly
innovative broadband services in the United States. Grant of Telesat’s STA request, therefore, is
in the public interest.
         Telesat is submitting, as Attachment 3 to this STA request, a detailed orbital debris
assessment report prepared by NXTRAC for LEO 1, confirming compliance with U.S.
government orbit lifetime and orbital debris mitigation regulations.2 A radiation hazard study for
each earth station is provided in Attachment 2a and 2b hereto.

1
  FCC 17-147. Telesat’s PDR and the associated grant are hereby incorporated by reference.
2
  In addition, Telesat’s orbital debris plan for LEO 1 has been reviewed by the Canadian licensing authority for the
satellite, Innovation, Science and Economic Development Canada, for compliance with the guidelines issued by the
Inter-Agency Space Debris Coordination Committee and Telesat is required, by condition of license, to comply with
these guidelines.




285099.00005/104109405.1


Telesat Canada                                                                                        Attachment 1


         As indicated above, operations will be limited to the portions of the Ka-band in which
NGSO operations have primary status. Accordingly, EPFD limits are inapplicable. Telesat will
coordinate its STA operations with the U.S. federal government under footnote US3343 of the
United States Table of Frequency Allocations.4 Telesat will share ephemeris data in accordance
with Section 25.146(e) of the Commission’s rules. With regard to matters of physical
coordination, there are no operators using similar orbits.
         Accordingly, for good cause as shown herein, Telesat requests that the Commission grant
Telesat’s STA request.




3
  Telesat has been having discussions with the Commission as to the applicability of US334 and is coordinating with
the federal government out of an abundance of caution.
4
  Telesat notes that it answered question E18 in the Schedule B that is provided in Attachment 2a and 2b as “No”
(i.e., that frequency coordination is not required) based on its understanding that the question relates to non-federal
government coordination requirements, if any.


285099.00005/104109405.1



Document Created: 2019-06-04 08:17:16