Attachment Waiver request

This document pretains to SES-STA-20100601-00665 for Special Temporal Authority on a Satellite Earth Station filing.

IBFS_SESSTA2010060100665_819927

                                      Exhibit C
              PETITION FOR WAIVER OF SECTION 25.137 AND 25.114 AND OF
                    THE U.S. TABLE OF FREQUENCY ALLOCATIONS

I.         TO THE EXTENT THEY APPLY, GOOD CAUSE EXISTS FOR A WAIVER OF
           CERTAIN PORTIONS OF SECTIONS 25.137 AND 25.114

       Universal Space Network, Inc. (USN) is provided limited legal and technical information
for the COMS-1 Satellite.1 Pursuant to Section 25.137 of the Federal Communications
Commission’s (“Commission” or “FCC”) rules, the same technical information required by
Section 25.114 for U.S.-licensed space station, and certain legal information, must be submitted
by earth station applicants “requesting authority to operate with a non-U.S. licensed space station
to serve the United States…”2 USN seeks authority to support the needed Telemetry, Tracking,
and Control (“TT&C”) during launch and early orbit support (“LEOP”) of the COMS-1
spacecraft from launch to geostationary parking , not commercial service to the United States,
and thus believes that Section 25.137 does not apply.

        To the extent the Commission determines, however, that USN’s request for authority to
provide LEOP on a special temporary basis is a request to serve the United States with a non-
U.S-licensed satellite, USN respectfully requests a waiver of Sections 25.137 and 25.114 of the
Commission’s rules, to the extent that USN has not herein provided the information required by
these rules. 3 The Commission may grant a waiver for good cause shown.4 A waiver is therefore
appropriate if special circumstances warrant a deviation from the general rule, and such a
deviation will serve the public interest.

        In this case, good cause for a waiver of portions of Section 25.114 exists. USN seeks
authority only to conduct LEOP support for COMS-1. Thus, any information sought by Section
25.114 that is not relevant to the LEOP – e.g., antenna patterns, energy and propulsion and
orbital debris - USN does not have. In addition, USN would not easily be able to obtain such
information because USN is not the operator of the COMS-1 satellite, nor is USN in contractual
privity with that operator. Rather, USN has contracted with the Swedish Space Corporation to
support the launch and early orbit. The spacecraft is owned and operated by the Korea
Aerospace and Research Institute (KARI), and is launched by CNES from French Guiana, to
support the GEO transfer portion in S-Band of the satellite prior to its commercial operation.

       As evidenced by the Comsearch report attached to this request, USN has coordinated the
LEOP of the COMS-1 satellite with potentially affected terrestrial operators. Moreover, as with
any STA, USN will conduct the LEOP on an unprotected, non-interference basis to government
operations.

________________________
1
    FCC Form 312 Section B
2
    47 C.F.R. § 25.137(a)
3
    47 C.F.R. §§25.137 and 25.114
4
    47 C.F.R. §1.3


Because it is not relevant to the service for which USN seeks authorization, and because
obtaining the information would be a hardship, USN seeks a waiver of all the technical and legal
information required by Section 25.114, to the extent it is not provided herein. As noted above,
USN has provided the required information to the extent that it is relevant to the LEOP service
for which USN seeks authorization.

        Good cause also exists to waive portions of Section 25.137, to the extent the information
required is not herein provided. Section 25.137 is designed to ensure that “U.S.-licensed satellite
systems have effective competitive opportunities to provide analogous services” in other
countries. Here, there is no service being provided by the satellite; USN is providing TT&C
while the satellite is on the way to it’s geosynchronous parking orbit. Thus, the purpose of the
information required by Section 25.137 is not implicated here. For example, Section 25.137(d)
requires earth station applicants requesting authority to operate with a non-U.S.-licensed space
station that is not in orbit and operating to post a bond. 5 The underlying purpose in having to
post a bond – i.e., to prevent warehousing of orbital locations by operators seeking to serve the
United States – would not be served by requiring USN to post a bond in order to conduct 10 days
of LEOP support of the COMS-1 satellite.

        It is USN’s understanding that COMS-1 is licensed by KARI. COMS-1 is a
communications and meteorological satellite, and is not intended to serve the United States.
Thus, the purpose of Section 25.137 – to ensure that U.S. satellite operators enjoy “effective
competitive opportunities” to serve foreign markets and to prevent warehousing of orbital
locations service the United States – will not be undermined by grant of this waiver request.

       Finally, USN notes that it expects to communicate with the COMS-1 satellite using its
U.S. earth station for a period of only 10 days. Requiring USN to obtain technical and legal
information from an unrelated party, where there is no risk of interference and the operation will
cease within 10 days would pose undue hardship without serving underlying policy objectives.
Given these particular facts, the waiver sought herein is appropriate.




____________________________________
5
    47 C.F.R. §25.137(d)(4)


      II.      GOOD CAUSE EXISTS FOR A WAIVER OF THE UNITED STATES
               TABLE OF FREQUENCY ALLOCATIONS

        USN further requests a waiver of the United States Table of Frequency Allocations
("U.S. Table") as described in section 2.106 of the rules for the frequency bands 2025 – 2110
MHz (Earth-to-Space) and 2200 – 2290 MHz (Space-to-Earth).6 Section footnotes allow for
non-federal Government use of these bands in the United States on a case-by-case non-
interference basis. Such use by USN necessitates a waiver of the U.S. Table.

        Good cause exists to grant USN a limited waiver of the U.S. Table to allow LEOP of the
COMS-1 satellite. In considering request for case-by-case spectrum uses, the Commission has
indicated that is would generally grant such waivers “where there is little potential for
interference into any service authorized under the Table of Frequency Allocations and when the
case-by-case operator accepts any interference from authorized services.” 7 USN will coordinate
with other parties operating communication systems in compliance with the Table of Frequency
Allocations to ensure that no harmful interference is caused. USN seeks to operate only pursuant
to special temporary authorization and thus agrees to accept any interference from authorized
services. In summary, USN’s operation on a non-interference, non-protected basis support
waiver of the U.S. Table.




_______________________
6
    47 C.F.R. §2.106
7
 Previously approved STA’s for Universal Space Network SES-STA-20020725-01174; SES-STA-20021112-
02008; SES-STA-20040315-00475


USN support of COMS-1 from Hawaii

COMS-1 launches from the Centre Spatial Guyanais (CSG), Kourou in French Guyana
on the ARIANE 5 launch vehicle. Nominal lift-off time schedule is: June 23rd , 2010 at
21:44:00 UTC. USN will only support the Launch and Early Orbit (LEOP) phase of the
mission.


Sequence of events for support of COMS-1 from USN-Hawaii:
Event                               Date          Time
Launch                              23-June       21:44:00 UTC
Separation                          23-June       22:16:43 UTC
Hawaii AOS (pass#1)                 24- June      19:46:17 UTC
Hawaii LOS                          25- June      03:47:02 UTC
Hawaii AOS (pass#2)                 25- June      04:21:08 UTC
Hawaii LOS                          25- June      05:33:33 UTC
Orbital maneuver burn #1            25- June      10:37:00 UTC
Hawaii AOS (pass#3)                 25- June      18:00:39 UTC
Hawaii LOS                          26- June      05:47:48 UTC
Hawaii End of Mission               26- June      05:47:48 UTC




Detailed pass support
USN will support COMS-1 for a total of 3 passes starting 24-June thru
26-June. Not all possible visibility times will be supported. Actual support details and
times for each pass are shown below.


Injection and Pass #1 and #2

Facility-Hawaii-Sensor-13m-To-Satellite-COMS-1-injection: Access Summary Report

       PASS       Start Time (UTCG)                Stop Time (UTCG)
      ------      ------------------------         ------------------------
         1      24 Jun 2010 19:46:17               25 Jun 2010 03:47:02
         2      25 Jun 2010 04:21:08               25 Jun 2010 05:33:33



Spacecraft Injection NORAD TLE:

COMS1-Inj
1 32415U 2010035A 10174.92828470 0.00006501 00000+0 22984-2 0 11
2 32415 1.9757 65.0678 7278065 177.6755 7.7806 2.27898974 16




                                         Pass #2
                              Pass #1




USN Hawaii coverage of COMS-1 Pass #1 and #2.




                                   Pass #1


Pass #3     (Post maneuver burn#1)

Facility-Hawaii-Sensor-13m-To-Satellite-COMS-1-post-burn#1: Access Summary Report


Pass        Start Time (UTCG)                  Stop Time (UTCG)
------     -----------------------           -----------------------
  3         25 JUNE 2010 18:00:39               26 JUNE 2010 05:47:48




Spacecraft post burn#1 TLE:

COMS1-AEF1
1 32415U 2010035A 10176.47569444 -.00000005 00000+0 -44114+0 0      17
2 32415 1.0345 64.8162 5434973 178.4006 194.4122 1.92527234         17




                                        Pass #3
                                                   End of Mission for USN-Hawaii




USN Hawaii coverage of COMS-1 pass #3

End of Mission support for USN



Document Created: 2010-06-01 09:11:39
Document Modified: 2010-06-01 09:11:39

© 2024 FCC.report