This document pretains to SAT-MOD-20101126-00269 for Modification on a Satellite Space Stations filing.

IBFS_SATMOD2010112600269_869012

February 11, 2011


Mr. Robert G. Nelson
Chief, Satellite Division, International Bureau
Federal Communications Commission
445 12th Street, S.W.
Washington, D.C. 20554

        Re:      Spectrum Five LLC
                 IBFS File No. SAT-MOD-20101126-00245
                 Call Signs S2667 and S2668

Dear Mr. Nelson:

Spectrum Five LLC (“Spectrum Five”) herein responds to the International Bureau’s
(“Bureau”) January 13, 2011 letter requesting additional information concerning the above-
referenced application in which Spectrum Five requests a declaratory ruling extending or
waiving the interim construction milestone associated with its authorization to provide Direct
Broadcast Satellite (“DBS”) service in the United States from a Netherlands-authorized
“tweener” satellite network at 114.5° W.L. Please find below the Bureau’s questions in bold
text and Spectrum Five’s responses.

If the construction contract submitted to the Commission on November 28, 2007 was
amended, please submit a complete copy of the current version of the contract, and a
listing of the items that changed between the version previously submitted and the
current version.

Spectrum Five’s construction contract with Space Systems/Loral, which was submitted to the
Commission on November 28, 2007, has been amended. Attachment A describes the
modifications that have been made to the contract. A list of the contract sections that have
changed from the original version of the contract is also included in Attachment A.1

Please provide the complete CDR package, including the documentation package
prepared for payload subsystem CDR and the resulting CDR Report and Action Item
list (preferably on CD-ROM).

Spectrum Five filed a certification from Space Systems/Loral, Inc. attesting to completion of
CDR on November 25, 2008.2 Attachment B contains a copy of the CDR documents
produced by Space Systems/Loral.3
1
         Information about the changes and a copy of the contract provisions that have changed are being filed
separately with a request for confidentiality.
2        See Letter from Todd M. Stansbury to Marlene H. Dortch, CDR Milestone Compliance Showing; File
Nos. SAT-LOI- 20050312-00062 and SAT-LOI-20050312-00063, Call Signs S2667 and S2668 (filed Nov. 28,
2008).
3        All CDR materials are being filed separately with a request for confidentiality.


Mr. Robert G. Nelson
February 11, 2011
Page 2



Please state the status of construction of the Spectrum 1A and 1B satellites. Are
Spectrum Five and Space Systems/Loral continuing to construct these satellites?

As noted above, Critical Design Review (“CDR”) for these satellites has been completed.
Construction by Space Systems/Loral is currently suspended.

If construction is not continuing, on what date did construction halt? Has Spectrum
Five negotiated with Space Systems/Loral, or any other manufacturer, to resume, at a
later date, construction of DBS satellites designed to operate at the 114.5° W.L. orbital
location, or to otherwise dispose of any purchased or fabricated hardware?

For the reasons stated in the pending petition for declaratory ruling, construction of the
satellites halted after completion of CDR, and Spectrum Five is finalizing funding to resume
construction pursuant to the contract with Space Systems/Loral.

If construction is continuing, what payments have been made pursuant to the satellite
construction contract submitted on November 28, 2007? Please identify – with specific
reference to the payment plan in Exhibit E to the contract – which contract milestone(s)
were completed and what payments were made.

Attachment C provides a list of the payments that have been made pursuant to the contract.
As described in Attachment A, Spectrum Five and Space Systems/Loral amended Exhibit E
to the contract on August 1, 2008. Spectrum Five has made payments for Milestone
Numbers 1 through 9 of the amended Exhibit E.

Spectrum Five respectfully requests that the International Bureau promptly place its above-
referenced request for extension or waiver of the interim construction milestone on public
notice.4 Prompt processing and grant of that pending request is the best means available to
bring much-needed competition to the U.S. DBS market from a new entrant operating from a
new orbital location.




4      See 25 C.F.R. § 25.151.


Mr. Robert G. Nelson
February 11, 2011
Page 3


Please do not hesitate to contact the undersigned if you have any questions. Spectrum Five
would welcome the opportunity to meet with Commission staff to discuss this important
matter.

Respectfully submitted,

/s/ David Wilson

David Wilson
President
SPECTRUM FIVE