Ex PARTE PRESENTATION NOTIFICATION LETTER submitted by TerreStar

exparte

2007-01-26

This document pretains to SAT-MOD-20061206-00144 for Modification on a Satellite Space Stations filing.

IBFS_SATMOD2006120600144_548368

                                                                     EX PARTE OR LATE FILED
                                                   LAW OFFICES
                           GOLDBERG, GODLES, WIENER & WRIGHT
                                   1229 NINETEENTH STREET, N.W.
                                    WASHINGTON, D.C. 20036—2413
HENRY GOLDBERG                                                                                   (202) 429—4900
JOSEPH A. GODLES                                                                                 TELECOPIER:
JONATHAN L. WIENER                                                                               (202) 429—4912
LAURA A. STEFANI
DEVENDRA ("DAVE") KUMAR                                                                             e—mail:
HENRIETTA WRIGHT                                                          Pm _ o.
                                                                          mppoq                general@g2w2.com
THOMAS G. GHERARDI, PC.                                                   HILED/AcQ
THOMAS S. TYCZ*
SENIOR POLICY ADVISOR
*NOT AN ATTORNEY
                                                  January 26, 2007

             Marlene H. Dortch, Secretary
            Federal Communications Commission
            445 12t" Street, S.W.
            Washington, D.C. 20554

                                            Re:   File No. SAT—MOD—20061206—00144
                                                  Ex Parte


             Dear Ms. Dortch:


                    This is to inform you that, on January 22, 2007, in connection with the above—
            referenced proceeding, Alexandra Field, Vice President of Regulatory Affairs, TerreStar
            Networks, Inc., Ted Kaplan of RKF Engineering Solutions LLC, Thomas Tycz of this
            firm, and the undersigned, met with Julius Knapp, Chief of the Office of Engineering
            and Technology and Ron Repasi and James Burtle of OET . The purpose of the meeting
            was to discuss TerreStar‘s need to select its operating frequencies as soon as possible and
            to reach agreement with New ICO Satellite Services G.P.. The materials that were
            provided and discussed are attached hereto.

                   Please direct any questions regarding this matter to the undersigned.




                                                         Henry Goldberg
                                                         Attorney for TerreStar Networks, Inc.

            Attachment

            cc:    Julius Knapp
                   Ron Repasi
                   James Burtle


Te   ror   el   S   t   a    f
                N E T W O R K S




                                                                    Band Selection Issues
                                                                         22 January, 2007




                Proprietary and Confidential — Use or distribution subject to restrictions on first page


                                                                                          To e ror efS t aor
           Band Selection and Channel Assignment                                                      *
                      for Base Stations

TerreStar Vendors can progress only so far with their R & D without
final band selection
 =   Blocks Selection —Which combination of the S—band blocks will TerreStar be assigned?
      @      A and C, B and D, A and D or B and C

 x   Transmit and Receive Spacing — What will the spacing be?

 —   Base Station impact
      «      Designs have already progressed significantly beyond the "from scratch" phase
      «      The development timeline is already pressed to meet the required system
             deployment date, any changes to the current design (channel spacing) will cause
             extra challenges in meeting the timeline.
      «_     The later the decisions are made, the greater the impact.

      «       Changes to the current assumptions will further delay the timelines




           Proprietary and Confidential — Use or distribution subject to restrictions on first page


                                                                                                    TerreStar
                 Base Station Development Timeline                                                               *\ n e Tw o R KS




«_       Based on a 15 Month Process


                Jan 07                                               Trial Equipment                           Jan 08
             Design Frozen                                               Available                     Volume Delivery

                        Feb      Mar    Apr—    May     Jun    Jul     Aug    Sep      Oct   Nov     Dec
     |       |             |       |       |      |       |     |       |      |        |      |       |
     |       |      |      |       |       |      |       |     |       [      [        |      |       |         1
     3 months                                   9 months                                      3 months


System Specified                       Software & Hardware Design                                  System
                                                                                              Verification
                                                                                                           1 month
                                                                                                            4————p

                                                                                                       Production
                                                                                                        Ramp Up




                    Proprietary and Confidential — Use or distribution subject to restrictions on first page


                          Handset Development Timelines —
                            Industry Historical Perspective                                               NOE T w O R K §




+    A typical time frame to development handset is between 11 and 19 months
      — First of its kind products can take 24 to 30 months (i.e. Apple iPhone, Motorola
         Razor)
«_   Development of some hardware components and chipsets has a dependency on the
     actual frequencies used
      — A delay in knowing the frequencies will very probably push out all delivery
        milestones




               Proprietary and Confidential — Use or distribution subject to restrictions on first page


                                  Why such a long development time?                                        Te    rof    S   t   a   r

                             Think Mobility from a handset perspective
        «_     Increasingly complex handset features and data services require more sophisticated
               software
        «_     ~85% of workload in 3/4G handsets is in software design
        +«     Software design is heavily impacted by chipset
               Chipset is impacted by frequencies used


              1       ATC                     2                2
              2       No coverage             1                1                                                Satellite
              3       Satellite               2                2
              4       ATC + SAT               4                8
              5       GSM                     2                2
              6        lATC+GsMm              4                3
              7       ATC + SAT + GSM         8               384
              s       |sAT+GsM                4                8
              9       WiFi                    2                2.
                      ATC + SAT + GSM
              10      + WiFi                  14             645120
              11      ATC + GSM + GSM          8              384
              12      GSM + WiFi               4                8
              13      ATC + SAT + WiFi         8              384
              14      SAT+ WiFi                4                a

J                                   x              &    &             &   &   —     &
    anuary 26, 2007          Proprietary and Confidential — Use or distribution subject to restrictions on first page


                                                                                             TerreStar

     Band Selection and Microwave Market Clearing                                                         *"***~
               loeltealis                        L

—«   TerreStar cannot properly plan or begin incumbent microwave
     clearing in support of satellite initial operation without band selection
      «   Use of 10 MHz downlink for satellite depends on actual frequencies used

«    TerreStar is delayed in microwave clearing for ATC deployment
      «   Clearing process is 10—13 month process and must be cleared prior to
          ATCisatellite operations
           «    Financial risk of TerreStar launching satellite and not being able to radiate due
                to delay in microwave clearing driven by delayed band selection
      @   Significant financial impact
           «    For example, TerreStar analysis shows that for Miami market there are 34
                interfered paths in A/B bands and 18 interfered paths in C/D. Early clearing
                activity that is subsequently reversed by band selection would be of significant
                financial impact to TerreStar




               Proprietary and Confidential — Use or distribution subject to restrictions on first page


                                                                                                               TerreStar
                  Microwave Clearing Tlmehne                                                                              J n er w o R x s


                        lten




«_        Based on 10—13 Month standard Process




                                                                                                                 Nov 2007
      J           Feb        M         A        M          Jun    Jul       Au          Se             Oct
          an       &              ar       P"        aYy    C                      9          P                  Satellite Launch

      |             |         |        |         |          |       |          |          |             |                   |
      l             |         |        |         |          |       |          |          |             |                   |
                1.5—2                                                               1.5—2                    1.5—2         .5
               months                       5—7 months                             months                   months       months
      <                 ><                                               > <                      ><                    > <——p>
     Kick off Meeting                                lati
                                           FRA Negotiations                    Equipment                    Equipment
                                                                                   Ordering                   Install
     Inventory submission
     verification




                        Proprietary and Confidential — Use or distribution subject to restrictions on first page


                                                                                                                                                        Te          r   r   eS   t   a    r
                                                                                                                                                                             NOE T w O R K s



      Band Selection and Channel Assignment


                                                        TerreStar AWS Frequency Spectrum

                                 C      P                «*&                                   &*&*"           $#§
                                                                                                       _




                                                                                                             AWS     AWB                   AWS              AoiS

                                                                                                               A      a                      F
                                                                                                             NDMHz   10MHz                 sOMbz            20MAz




                                                                                               dow Benarem




      nescmrr                                             see   moe                     nork                 uo ar             bmagnuson               se    Te         |
                                                                      snga meue                              fare              omenzone
TormBlar AWS—ATG—BAT Spactrom(                                        La: Ednc 410007                                                               A
Mod                                                                                                          ows p     60008 —Pg.1 of t            ~
                                                                                                                                                              cusrmen   |




                             Proprietary and Confidential — Use or distribution subject to restrictions on first page