Washington, DC 20008-3006



Subject:       Contract Intelsat 17 (IS – 17) Spacecraft; Status of Spacecraft Construction


Dear Mr. Froeliger:


This letter is provided to Intelsat LLC to summarize the current progress of construction of the
Intelsat 17 Spacecraft.

   1. The Spacecraft Critical Design Review was completed on 25 June 2009.

   2. The Spacecraft construction is well underway, and satellite thermal vacuum tests, including
      the post test data review, were successfully completed on 23 June 2010.

   3. Preparations for satellite dynamics tests are underway.

The Spacecraft is scheduled to ship to the launch base on 26 October 2010, on schedule for a
planned launch in November 2010.

The undersigned hereby certifies that all of the above statements are true and correct.

Sincerely,




Paradesia Damodharan
Senior Executive Director
Intelsat Programs



Document Created: 2010-07-07 11:21:57
Document Modified: 2010-07-07 11:21:57

© 2024 FCC.report
This site is not affiliated with or endorsed by the FCC