Letter re RDBS Contr

LETTER submitted by EchoStar Satellite Operating Corporation

Letter

2015-02-24

This document pretains to SAT-ASG-20110224-00034 for Assignment on a Satellite Space Stations filing.

IBFS_SATASG2011022400034_1077509

February 24, 2015

Marlene H. Dortch
Secretary
Federal Communications Commission
445 12th Street, SW
Washington, D.C. 20554

Re:       17/24 GHz BSS Milestone Compliance
          File Nos. SAT-LOA-20020328-00050, SAT-LOA-20020328-00051, SAT-LOA-
          20020328-00052, SAT-LOA-20070105-00001, SAT-LOA-20070105-00003 & SAT-
          ASG-20110224-00034
          Call Signs S2440, S2441, S2442, S2723 & S2725

Dear Ms. Dortch:
EchoStar Satellite Operating Corporation (together with its affiliates, “EchoStar”) submits this
supplemental letter as a follow-up to discussions with International Bureau (“IB”) staff regarding
milestone showings and the above-referenced surrendered 17/24 GHz Broadcasting-Satellite
Service (“BSS”) licenses. 1 As this letter shows, the five contracts under review meet the FCC’s
contract milestone requirement. 2

As required under Section 25.164(c) of the FCC’s rules, 3 EchoStar submitted on a timely basis
copies of five binding, non-contingent contracts with Space Systems/Loral, Inc., dated between
March and July 2010, to construct 17/24 GHz BSS satellites. 4 Each contract meets the



1
 See Letter from Adam D. Krinsky, Counsel to EchoStar, to Marlene H. Dortch, Secretary, FCC, File
Nos. SAT-LOA-20020328-00050 et al. (Jan. 23, 2015).
2
 This letter focuses solely on the first milestone, a binding, non-contingent contract. Satisfaction of the
second milestone, critical design review, will be addressed in a subsequent filing, as appropriate.
3
    See 47 C.F.R. § 25.164(c).
4
 See Letter from Pantelis Michalopoulos, Counsel to EchoStar, to Marlene H. Dortch, Secretary, FCC,
File No. SAT-LOA-20070105-00001 (Mar. 15, 2010); Letter from Pantelis Michalopoulos, Counsel to
EchoStar, to Marlene H. Dortch, Secretary, FCC, File No. SAT-LOA-20070105-00003 (Mar. 18, 2010);
Letter from Pantelis Michalopoulos, Counsel to EchoStar, to Marlene H. Dortch, Secretary, FCC, File No.
SAT-LOA-20020328-00050 (Apr. 16, 2010); Letter from Pantelis Michalopoulos, Counsel to EchoStar
Corporation, to Marlene H. Dortch, Secretary, FCC, File No. SAT-LOA-20020328-00052 (July 28,
2010); Letter from Pantelis Michalopoulos, Counsel to EchoStar Corporation, to Marlene H. Dortch,
Secretary, FCC, File No. SAT-LOA-20020328-00051 (July 28, 2010) (collectively, “Contracts”).



                                                      1


Commission’s standard for a binding, non-contingent contract. 5 Specifically, each contract
contains no unresolved contingencies that could preclude satellite construction, specifies a
construction schedule consistent with the FCC milestones, and requires a substantial payment for
completion of each of the four FCC milestones – i.e., contract execution, critical design review
(“CDR”), construction commencement, and launch and operation. 6 Accordingly, the five
contracts clearly meet the requirements of Section 25.164(c) of the FCC’s rules.

In response to questions from IB staff, EchoStar demonstrates here that each contract contains a
schedule that meets the second milestone requirement, CDR, within two years of licensing.
Specifically, each contract requires: (i) that CDR “shall occur within 12 months of program
start,”7 (ii) that CDR “shall provide sufficient design maturity to initiate procurement of long
lead parts,” 8 and (iii) a substantial payment for CDR 11 months after the contract date and a
substantial payment for long lead orders 12 months after the contract date. 9

The Commission has previously established that procuring long lead parts is evidence of CDR
completion, because such parts are required to commence the next milestone phase, physical
construction of the spacecraft. 10 Each contract expressly requires completion of sufficient design
work to procure long lead parts 12 months after the contract date. Consequently, each contract
contains a schedule that includes the steps to meet the second milestone. 11 Although, as staff
correctly points out, each contract provides for additional design review following CDR, neither
the milestone rule under Section 25.164(c) nor Commission precedent precludes such subsequent

5
 See Amendment of the Commission’s Space Station Licensing Rules and Policies, 18 FCC Rcd 10760, ¶
184 (2003) (“2003 Satellite Licensing Reform Order”) (citing Tempo Enterprises Inc., Memorandum
Opinion and Order, 1 FCC Rcd 20, ¶ 7 (1986) (“Tempo”)).
6
  See Tempo ¶ 7 (“There is a contract, signed by both parties, which contains no unresolved contingencies
which could preclude substantial construction of the satellites . . . . Specific satellites and their design
characteristics are identified, and dates for the start and completion of construction are specified. The
payment terms and schedule are described sufficiently to demonstrate the parties’
investment/commitment to completion of the system. While the payments are not evenly spread through
the contract term, the initial payments are significant, and the majority of payments are due during the
middle phases, well before the end of the construction period. The major milestones in the construction
schedule are provided, and with the payment schedule, establish the certainty of the plan and the
reasonableness of its projection for timely completion.”); see also TMI Communications and Co., L.P.,
Memorandum Opinion and Order, 19 FCC Rcd 12603, ¶ 6 (2004) (“the construction contract must set
forth a specific construction schedule that is consistent with the licensee’s milestones”).
7
    See Contracts, Statement of Work (Exh. A), § 2.1.4.1.
8
    See id.
9
    See Contracts, Payment Plan (Attachment A).
10
  See 2003 Satellite Licensing Reform Order ¶ 191 (“Evidence of [CDR] compliance may include …
evidence that the licensee has ordered all the long lead items needed to begin physical construction of the
spacecraft.”).
11
     Each contract similarly satisfies the other milestone schedules as well.




                                                      2


design review. In fact the Commission previously allowed a licensee to modify its authorized
satellite system and to conduct additional design review for its modified system nearly two years
after completing CDR for the initially licensed system. 12 Thus, the Commission has allowed
additional design review well after the CDR milestone date. 13

Based upon the foregoing, EchoStar has met the necessary elements of the contract execution
milestone – including a schedule to meet the second milestone – for each of its above-referenced
17/24 GHz BSS licenses. Accordingly, the FCC should find the first milestone met and reduce
the associated bond amounts accordingly.

If you require additional information or have any questions, please contact the undersigned.

Sincerely,


/s/ Jennifer A. Manner
Jennifer A. Manner
Vice President, Regulatory Affairs

cc:     Troy Tanner (FCC)
        Jose Albuquerque (FCC)
        Karl Kensinger (FCC)
        Stephen Duall (FCC)
        Kathyrn Medley (FCC)




12
  See ICO Satellite Services G.P., 20 FCC Rcd 9797, ¶ 23 (IB 2005). In authorizing additional CDR
work after the initial CDR milestone date, the Commission found that its precedent “does not necessarily
preclude grant of applications for modification of space-station design filed after the two-year CDR
deadline.” Id. ¶ 26.
13
  In fact, it is quite common under satellite construction practices to have design review continue
throughout a substantial duration of the project. A prohibition against such review could negatively
impact the successful construction of a satellite.



                                                    3



Document Created: 2015-02-24 13:08:40
Document Modified: 2015-02-24 13:08:40

© 2024 FCC.report
This site is not affiliated with or endorsed by the FCC