Attachment DA011637

This document pretains to SAT-AMD-20001103-00157 for Amended Filing on a Satellite Space Stations filing.

IBFS_SATAMD2000110300157_219704

                                    Federal Communications Commission                                   DA 01-1637

                                               Before the
                                    Federal Communications Commission
                                          Washington, D.C. 20554


In the Matter of Application of                               )
                                                              )
Mobile Communications Holdings, Inc.                          )    File No. 180-SAT-P/LA-97(26)
                                                              )
Concerning Use of the 1990-2025/2165-2200 MHz                 )    IBFS Nos. SAT-LOA-19970926-00150
and Associated Frequency Bands for a Mobile-                  )              SAT-AMD-20001103-00157
Satellite System                                              )


                                      ORDER AND AUTHORIZATION


         Adopted: July 17, 2001                                         Released: July 17, 2001

By the Chief, International Bureau and the Acting Chief, Office of Engineering and Technology:


                                           I.       INTRODUCTION

         1.       By this Order, we grant the request of Mobile Communications Holdings, Inc. (MCHI)
for the use of spectrum in the 2 GHz band for provision of Mobile-Satellite Service (MSS).1 This action
is a significant step in assigning this spectrum for use by MSS providers, and facilitates implementation
of MCHI’s proposed system’s technology and service offerings in the marketplace.

                                            II.      BACKGROUND

         2.      MCHI proposes to construct and launch a mobile-satellite system comprised of 26
satellites in non-geostationary satellite orbit (NGSO), using service links2 in the 2 GHz MSS band and
feeder links3 in the 15 GHz (uplink) and 7 GHz (downlink) bands. MCHI’s system is being designed to
serve the United States and Canada from the 1990-2025 MHz and 2165-2200 MHz bands immediately,


   1
         The term “2 GHz MSS Band” is used in this Order to refer to the 1990-2025 MHz (uplink) and 2165-2200
MHz (downlink) frequencies. These frequencies are allocated to the Mobile-Satellite Service (MSS) in the United
States. See Amendment of Section 2.106 of the Commission's Rules to Allocate Spectrum at 2 GHz for Use by the
Mobile-Satellite Service, ET Docket No. 95-18, First Report and Order and Further Notice of Proposed Rule
Making, 12 FCC Rcd 7388 (1997), aff’d on recon., Memorandum Opinion and Order and Third Notice of Proposed
Rule Making and Order, 13 FCC Rcd 23949 (1998), further proceedings, Second Report And Order and Second
Memorandum Opinion and Order, 15 FCC Rcd 12315 (2000) (2 GHz Allocation & Relocation Proceeding).
   2
         “Service links” are the radio links that transmit a user’s messages in both directions between a user’s earth
terminal and the system’s satellite(s).
   3
          “Feeder links” are the radio links that transmit a user’s messages in both directions between the system’s
satellite(s) and its gateway earth station(s), connecting the MSS network with the public switched telephone network.

                                                          1


                                     Federal Communications Commission                                     DA 01-1637

extending the use of these frequencies to all of International Telecommunication Union (ITU) Region 2
after January 2005, and, in ITU Regions 1 and 3, utilizing the 1990-2010 MHz and 2170-2200 MHz
bands.4 MCHI’s 2 GHz MSS system will operate in five orbital planes, four elliptical and one circular.5
        3.       MCHI submitted its 2 GHz MSS application on September 26, 1997.6 On March 19,
1998, we sought comment on MCHI’s application, along with other 2 GHz MSS applications.7 The
Commission subsequently adopted service rules for 2 GHz MSS systems.8 MCHI amended its
application to address the requirements adopted in the 2 GHz MSS Order.9

                                               III.     DISCUSSION

          4.     Under rules adopted in the Commission’s 2 GHz MSS Order, MCHI must demonstrate
that its system meets certain technical requirements. We address these requirements first. We then turn
to MCHI’s requests for service links in the 2 GHz MSS band and feeder links in the 15 GHz and 7 GHz
frequencies, followed by a review of MCHI’s licensing conditions, implementation milestones, and
orbital debris mitigation strategy. Finally, we dispose of various parties’ arguments against granting
MCHI’s application.




   4
         Application of Mobile Communications Holdings, Inc., File No. 180-SAT-P/LA-97(26), IBFS No. SAT-
LOA-19970926-00150 (MCHI Application), Exhibit 1 at 1. The Members of the ITU have divided the world into
three Regions. Generally, Region 1 includes Africa, Europe, Northern and Western portions of Asia; Region 2
includes the Americas and Greenland; and Region 3 includes Southern portions of Asia, Australia and the South
Pacific. See ITU Radio Regulations Article S5, Section I. In accordance with ITU Regulations, the 1990-2010 MHz
and 2170-2200 MHz bands are allocated to MSS worldwide. Id. Article S5, Section IV. In Region 2, the 2010-2025
MHz and the 2165-2170 MHz bands, which the ITU already has made available for MSS use in Canada and the
United States, will become available for MSS in the rest of Region 2 on January 1, 2002. Id. S5.389C & S5.389D.
   5
         Three of the elliptical orbits will consist of five satellites each, with a period of 178 minutes, apogee of
7513.4 kilometers, perigee of 674.3 kilometers and inclination angle of 116.565 degrees. The fourth elliptical orbit
will consist of five satellites with a period of 232 minutes, apogee of 7975.7 kilometers, and perigee of 4285.6
kilometers in the equatorial plane (zero degree inclination). The one circular orbit will consist of six satellites with a
period of 279 minutes at an altitude of 7747.3 kilometers in the equatorial plane (zero degree inclination). MCHI
Application, Exhibit 1 at 9-10.
   6
          Id. In this document, the term “applicant” and “application” refers to all parties, and their submissions,
seeking to operate 2 GHz MSS systems, whether they are applicants for U.S.-licensed systems or letter of intent
filers from non-U.S. licensed systems seeking to serve the U.S. market using 2 GHz MSS spectrum.
   7
        See Public Notice, Report No. SPB-119 (rel., March 19, 1998). In response to this Public Notice, 6
comments, 1 reply comment, and 2 responses were filed specifically addressing MCHI’s Application. A list of
pleadings is attached in Appendix A.
   8
        The Establishment of Policies and Service Rules for the Mobile Satellite Service in the 2 GHz Band, IB
Docket No. 99-81, Report and Order, 15 FCC Rcd 16127 (2000) (2 GHz MSS Order).
   9
        Amendment to Application of Mobile Communications Holdings, Inc., File No. SAT-AMD-20001103-
00157 (Conforming Amendment); see Public Notice, Report No. SAT-00061 (rel. November 29, 2000) (2 GHz MSS
Amendment PN). No petitions to deny or other objections or comments were filed on MCHI’s Conforming
Amendment in response to this Public Notice.


                                                            2


                                      Federal Communications Commission                        DA 01-1637

A.        Threshold Technical Requirements

          1.        Frequency Agility

        5.      Under the Commission’s service rules and policies, 2 GHz MSS systems must be capable
of operating across at least seventy percent of the United States’ 2 GHz MSS allocation in the 1990-2025
MHz and 2165-2200 MHz bands.10 The Commission also requires that 2 GHz MSS systems be capable
of operating without fixed frequency translations between the uplink and downlink frequencies.11
MCHI’s proposed 2 GHz MSS system meets these requirements.12

          2.        NGSO Coverage Requirements

        6.      Section 25.143(b)(2) of the Commission’s rules requires NGSO 2 GHz MSS systems to
provide continuous coverage throughout all 50 states, Puerto Rico and the U.S. Virgin Islands, i.e., that at
least one satellite is visible at an elevation angle of at least five degrees at all times within this
geographic area.13 In addition, at locations as far north as 70 degrees North Latitude and as far south as
55 degrees South Latitude, NGSO MSS systems must operate such that at least one satellite is visible at
an elevation angle of at least five degrees for eighteen hours of every day.14 MCHI’s proposed system
meets these requirements.15

B.        Service-Link Spectrum

        7.      The 2 GHz MSS Order adopted a hybrid band arrangement that divided the 2 GHz MSS
uplink (1990-2025 MHz) and downlink (2165-2200 MHz) bands into segments of equal bandwidth based
on the number of systems seeking assignments.16 The Commission determined that providing
3.5 megahertz in each direction for the nine then-pending system proponents would be sufficient to
commence operations.17 The Commission provided that, in the event not all system proponents proceed
toward authorization, the remaining system proponents would receive more than 3.5 megahertz of
spectrum in each direction upon authorization.18 In addition, the Commission reserved one additional
spectrum segment in each direction for expansion of system(s) by operator(s) meeting certain criteria for
service to unserved areas.19 The following formula expresses the amount of spectrum available for each
system in each direction of transmission:

     10
          2 GHz MSS Order, 15 FCC Rcd at 16152 ¶ 52.
     11
          Id. at ¶ 53.
     12
          MCHI Application, as amended by Conforming Amendment, Exhibit 1 at 1.
     13
          47 C.F.R. § 25.143(b)(2)(iii).
     14
          47 C.F.R. § 25.143(b)(2)(ii).
     15
          MCHI Application, as amended by Conforming Amendment, Exhibit 1 at 31.
     16
          2 GHz MSS Order, 15 FCC Rcd at 16138 ¶ 16.
     17
          Id. at 16139 ¶ 17.
     18
          Id.
     19
          Id. at 16146-47 ¶¶ 35-39.

                                                       3


                                     Federal Communications Commission                                   DA 01-1637

          35 megahertz ÷ (Number of System Proponents + One) = Size of Each Spectrum Segment20
There are currently eight 2 GHz MSS system proponents participating in this processing round.21 We
will not at this time, however, implement that portion of the Commission’s 2 GHz MSS Order that would
give each system proponent access to more than 3.5 megahertz of spectrum in each direction on a
primary basis. Subsequent to release of the 2 GHz MSS Order, the Commission has received new
proposals for use of the 2 GHz MSS bands.22 Delaying the designation of additional spectrum will give
the Commission the opportunity to consider these proposals. Therefore, in this Order, MCHI will
receive access to a spectrum segment of 3.5 megahertz, in each direction of transmission, on a primary
basis, i.e., a “Selected Assignment.”23 MCHI will choose its Selected Assignment such that the band
edge of the assignment is an integer multiple of 3.88 megahertz from the band edge of the 2 GHz MSS
band, which will allow the Commission to address the proposals before it.
         8.        MCHI must identify the specific frequencies of its Selected Assignment when the first
satellite in its system reaches its intended orbit, and notify the Commission in writing of its selection.24
Consistent with the 2 GHz MSS Order, MCHI may also elect to operate outside its Selected Assignment
on a secondary basis with respect to other 2 GHz MSS operators, subject to certain conditions.25

C.        Feeder Links

         9.     MCHI proposes feeder link operations in 300 megahertz of spectrum in the 15.4-15.7
GHz band (Earth-to-space) and 300 megahertz of spectrum in the 6775-7075 MHz band (space-to-
Earth).26 In the United States, the 15.4-15.7 GHz and 6775-7075 MHz bands for which MCHI seeks
authority are not currently allocated for commercial NGSO satellite service, and the 6775-7075 MHz
band is not allocated in the direction that MCHI proposes. However, the ITU has allocated the 15.43-
15.63 GHz (15 GHz),27 6700-7075 MHz (7 GHz),28 and 5091-5250 MHz (5 GHz)29 frequencies for feeder
     20
          Id. at 16138 ¶ 16.
     21
          See 2 GHz MSS Amendment PN, Report No. SAT-00061.
     22
         See Ex parte Letter of New ICO Global Communications (Holdings) Ltd., IB Docket No. 99-81 (dated
March 8, 2001) (ICO Ex Parte Letter); Petition for Rulemaking of the Cellular Telecommunications & Internet
Association (filed May 18, 2001) (CTIA Petition).
     23
         Systems must be implemented consistent with the plans for incumbent relocation adopted in the 2 GHz
Allocation & Relocation Proceeding, Second Report And Order and Second Memorandum Opinion and Order, 15
FCC Rcd 12315, including the phased plan for relocation in the 1990-2025 MHz band.
     24
         2 GHz MSS Order, 15 FCC Rcd at 16138 ¶ 16. A satellite’s intended orbit is the final orbit it will occupy
to provide commercial service. Id. n.75.
     25
         Id. at 16139-40 ¶ 19. The 1990-2025 MHz (Earth-to-space) and 2165-2200 MHz (space-to-Earth) bands
are immediately adjacent to the 2025-2110 MHz (Earth-to-space, space-to-space) and 2200-2290 MHz (space-to-
Earth, space-to-space) bands, respectively, where the Federal Government has extensive satellite network operations.
 To avoid the possibility of adjacent band interference, this potential interference situation needs to be considered by
both non-Government and Government satellite operators when implementing their respective satellite systems near
the band edges.
     26
          MCHI Application, Exhibit 1 at 23.
     27
      ITU Radio Regulations Footnote S5.511A (among other things, allocating the 15.43-15.63 GHz band to
NGSO MSS feeder uplinks, subject to coordination).

                                                           4


                                     Federal Communications Commission                                    DA 01-1637

link transmissions between earth stations and NGSO MSS satellites. Moreover, the Commission has
initiated a rulemaking proposing to amend the domestic Table of Frequency Allocations consistent with
the international allocation with regard to the 15 GHz, 7 GHz and 5 GHz frequency bands (the “5, 7, 15
GHz Allocation Rulemaking”).30 In the interim, we have granted waivers of Section 2.102(a) of the
Commission’s rules, which prohibits frequency assignments that differ from the Table of Frequency
Allocations,31 to allow NGSO MSS licensees to use portions of these internationally-allocated bands for
NGSO MSS feeder links.32
        10.      Consistent with these actions, we waive Section 2.102(a) of the Commission’s Rules to
permit the proposed operation as described below, pending completion of the 5, 7, 15 GHz Allocation
Rulemaking.33 For MCHI’s proposed feeder uplinks, we waive Section 2.102(a) to permit MCHI to
operate its feeder uplink transmissions in the 200 megahertz of spectrum in the 15.43-15.63 GHz band,
consistent with the international allocation. However, its request to use the 15.4-15.43 GHz and 15.63-
15.7 GHz bands is inconsistent with the international allocation and is denied.34
        11.     In its application, MCHI proposes to use the same amount of feeder downlink spectrum
as feeder uplink spectrum.35 Since we are permitting MCHI to operate its feeder uplink transmissions in
200 megahertz of spectrum, we waive Section 2.102(a) to permit MCHI to operate its feeder downlink
transmissions in 200 megahertz of internationally-allocated spectrum in the 6775-7075 MHz band. We
require MCHI to file a letter for inclusion in its license file designating the specific 200 megahertz of the
6775-7075 MHz band in which it intends to operate. MCHI must file this letter within 60 days after the
Commission adopts allocation rules for the 6775-7075 MHz band, in order to permit MCHI to evaluate
any sharing constraints that may be adopted in the ongoing proceeding.                        The National
Telecommunication and Information Administration (NTIA) has stated its concern about protecting
Government passive service operations in the 6650-6675.2 MHz band from NGSO MSS space station
transmissions in the 6700-7075 MHz band.36 As this is an active issue in the 5, 7, 15 GHz Allocation

   28
        ITU Radio Regulations Footnote S5.458B (allocating the 6700-7075 MHz band to NGSO MSS feeder
downlinks, subject to coordination).
   29
        ITU Radio Regulations Footnotes S5.444A (among other things, allocating the 5091-5150 MHz band for
assignment to NGSO MSS feeder uplinks until January 1, 2008, subject to coordination); S5.447A (allocating the
5150-5250 MHz band to NGSO MSS feeder uplinks, subject to coordination).
   30
         See Amendment of Parts 2, 25 and 97 of the Commission’s Rules with Regard to the Mobile-Satellite
Service Above 1 GHz, ET Docket No. 98-142, Notice of Proposed Rule Making, 13 FCC Rcd 17107 (1998).
   31
         47 C.F.R. § 2.102(a).
   32
         See, e.g., L/Q Licensee, Inc., Order and Authorization, 11 FCC Rcd 16410, 16413-14 ¶ 8 (Int’l Bur. 1996).
   33
         See WAIT Radio v. FCC, 418 F.2d 1153 (D.C. Cir. 1969).
   34
         Accord Comments of Constellation Communications, Inc. at 25.
   35
         Given that MCHI’s proposed 2 GHz MSS satellite “will be a ‘bent pipe’ transponding satellite that does not
perform any signal processing on the satellite itself” and the satellite’s transponders “will each be assigned a channel
on the feederlink,” this will require a symmetrical amount of feeder uplink and feeder downlink spectrum. MCHI
Application, as amended by Conforming Amendment, Exhibit 1 at 22-23.
   36
        See Letter from Associate Administrator, Office of Spectrum Management, NTIA, to Acting Chief, Office
of Engineering and Technology, FCC (May 7, 2001).


                                                           5


                                     Federal Communications Commission                                    DA 01-1637

Rulemaking, MCHI will be subject to any applicable rules that may be promulgated on this issue. Until
such time, we expect the Executive Branch and NGSO MSS entities to work together to address the
needs of both services.37
        12.     This authorization of feeder link spectrum is subject to any applicable restrictions or
modifications that may be promulgated in the 5, 7, 15 GHz Allocation Rulemaking. In addition, this
authorization should not be construed as a license for Earth-to-space transmission in the 15.43-15.63
GHz band. Such authority must be requested in the context of an earth station application filed pursuant
to Section 25.130 of the Commission’s rules.38 As stated in the 2 GHz MSS Order, MCHI must
coordinate with any other licensees authorized to use the same spectrum for feeder links.39 MCHI also
must coordinate its proposed NGSO satellite system operations with respect to licensed non-government
and authorized Federal Government terrestrial systems, as necessary, in accordance with Section 25.272
of the Commission’s rules.40
        13.      The 15.43-15.63 GHz band also is allocated to the aeronautical radionavigation services
(ARNS) on a primary basis in the United States,41 and throughout the world. To facilitate sharing of the
15.43-15.63 GHz band between ARNS stations and gateways transmitting to NGSO MSS satellites
worldwide, ITU Recommendation ITU-R S.1340 limits ARNS and gateway earth station equivalent
isotropically radiated power (e.i.r.p.) and establishes minimum coordination distances between ARNS
and gateway stations.42 We expect MCHI’s operations to comply with the ITU Recommendation ITU-R
S.1340 limits, and therefore, prior to operation, MCHI is required to coordinate its feeder link operations
in the 15.43-15.63 GHz band with NTIA’s Frequency Assignment Subcommittee of the Interdepartment
Radio Advisory Committee.

D.        Pre-operational Authority

        14.      Under Commission rules, the fifteen-year license term for a 2 GHz MSS system begins
upon a certification by the system operator that the first satellite in its system has begun operations
consistent with the terms and conditions specified in its authorization.43 The Commission indicated in
the 2 GHz MSS Order that it would “authorize system operators to conduct pre-operational testing in the
license grant, to the extent that applicants include such information in their applications.”44 MCHI did
     37
         See 47 C.F.R. § 2.106, footnote S5.458A (“In making assignments in the band 6700-7075 MHz to space
stations of the fixed-satellite service, administrations are urged to take all practicable steps to protect spectral line
observations of the radio astronomy service in the band 6650-6675.2 MHz from harmful interference from unwanted
emissions.”).
     38
          47 C.F.R. § 25.130.
     39
          See 2 GHz MSS Order, 15 FCC Rcd at 16159 ¶ 72 (citing 47 C.F.R. § 25.203(k)).
     40
          47 C.F.R. § 25.272.
     41
          47 C.F.R. § 2.106, footnote US260.
     42
         See ITU Recommendation ITU-R S.1340 (Sharing between feeder links for the mobile-satellite service and
the aeronautical radionavigation service in the Earth-to-space direction in the band 15.4-15.7 GHz).
     43
        2 GHz MSS Order, 15 FCC Rcd at 16175-76 ¶ 103; 47 C.F.R. § 25.121(a) (“Licenses for facilities
governed by this part will be issued for a period of 10 years, except that licenses and authorizations in the 2 GHz
Mobile-Satellite Service will be issued for a period of 15 years.”).
     44
          2 GHz MSS Order, 15 FCC Rcd at 16176 ¶ 103.

                                                           6


                                   Federal Communications Commission                              DA 01-1637

not request such authority. Accordingly, this authorization does not include authority for operations
except at the orbits and on the frequencies specified in the application, as amended. Authority for any
other radio transmissions in any frequency or satellite orbit will need to be obtained by filing a request
for a license modification or special temporary authorization, as appropriate.

E.        Regulatory Classification

         15.     MCHI states that it will provide its 2 GHz mobile-satellite services on a non-common
carrier basis.45 Under the Communications Act, Commission Rules, and consistent with our 2 GHz MSS
Order, we treat MCHI’s space station operations as non-common carrier.46 We will address the
regulatory classification of earth stations operating as part of MCHI’s system in connection with earth
station licensing.47

F.        Implementation Milestones

        16.     The 2 GHz MSS Order adopted milestones for implementation that apply to 2 GHz MSS
         48
systems.    Consistent with the 2 GHz MSS Order, therefore, MCHI must observe the following
milestone requirements:
                  Milestone                                          Deadline
                  Enter Non-contingent Satellite Manufacturing       12 months after authorization
                  Contract
                  Complete Critical Design Review (CDR)              24 months after authorization
                  Begin Physical Construction of All Satellites      30 months after authorization
                  Complete Construction and Launch First Two         42 months after authorization
                  Satellites in System
                  Certify Entire System Operational                  72 months after authorization

         17.     MCHI must describe the status of system construction and operation in its annual
reports, and file a certification with the Commission within ten days following each of the milestones
specified above.49




     45
          MCHI Application at 4.
     46
          47 U.S.C. §§ 153(44), 332(c)(5); 47 C.F.R. § 20.9(a)(10); 2 GHz MSS Order, 15 FCC Rcd at 16173 ¶ 95.
     47
        We also note that the Commission will address issues concerning protection for aeronautical
radionavigation in the 1559-1610 MHz band from the out-of-band emissions of 2 GHz MSS mobile earth terminals
(METs) in the pending Global Mobile Personal Communications by Satellite (GMPCS) rulemaking, and the 2 GHz
MSS METs will be subject to applicable rules and policies the Commission will adopt in that proceeding. 2 GHz
MSS Order, 15 FCC Rcd at 16196-97 ¶ 163 (citing Amendment of Parts 2 and 25 to Implement the Global Mobile
Personal Communications by Satellite (GMPCS) Memorandum of Understanding and Arrangements, IB Docket
No. 99-67, Notice of Proposed Rule Making, 14 FCC Rcd 5871 (1999)).
     48
          2 GHz MSS Order, 15 FCC Rcd at 16177-78 ¶ 106.


                                                       7


                                    Federal Communications Commission                                  DA 01-1637

G.         Orbital Debris Mitigation

        18.      Currently, the FCC addresses issues regarding orbital debris and satellite systems on a
case-by-case basis, under the general “public interest, convenience and necessity” standard in the
Communications Act.50 To facilitate our orbital debris analysis, under Section 25.143(b)(1) of our rules,
2 GHz MSS system proponents are required to “describe the design and operational strategies that they
will use, if any, to mitigate orbital debris.”51 This rule also requires 2 GHz MSS system proponents to
“submit a casualty risk assessment if planned post-mission disposal involves atmospheric re-entry of the
spacecraft.”52
         19.     In adopting this requirement, the Commission indicated that applicants may wish to
consult the National Aeronautics & Space Administration (NASA)/Department of Defense (DoD)
Guidelines on Debris Mitigation, as well as the ITU Recommendation on disposal of geostationary
satellites.53 The NASA/DoD Guidelines identify four main objectives: 1) controlling debris released
during normal operations; 2) minimizing debris generated by accidental explosions; 3) selecting safe
flight profiles and operational configurations; and 4) providing for post-mission disposal of space
structures.
         20.     Under the NASA/DoD Guidelines, these objectives are accomplished by a number of
          54
means. The first objective – controlling debris released during normal operations – is addressed by
minimizing the amount of debris released in a planned manner during normal operations. The second
objective – minimizing debris generated by accidental explosions – is addressed by limiting the risk to
other space systems from accidental explosions both during mission operations and after completion of
mission operations. For mission operations, this is accomplished through analysis of credible failure
modes and development of methods to limit the probability they will occur. Post-mission, this is
accomplished through depletion of all sources of stored energy on board the spacecraft when they are no
longer required for mission operations or post-mission disposal. The third objective – selecting a safe
flight profile and operational configuration – is addressed through estimating and limiting the probability
of collision with large objects during orbital lifetime, and the probability of disabling collisions with
small debris during mission operations.
         21.      The fourth objective in the NASA/DoD Guidelines – providing for post-mission disposal
of space structures – is met by planning for disposal of a spacecraft at the end of mission life to minimize
impact on future space operations. This is accomplished through one of two options relevant here. The
first option is atmospheric reentry, i.e., leaving the structure in an orbit in which it will remain in orbit for

     49
         See 47 C.F.R. § 25.143(e)(1) (requiring satellite space-station operators to file annual reports with the
Commission every October 15); Id. § 25.143(e)(3) (requiring satellite space-station operators to file a certification
with the Commission within 10 days of a system implementation milestone).
     50
           47 U.S.C. § 303.
     51
         47 C.F.R. § 25.143(b)(1), as amended by the 2 GHz MSS Order, 15 FCC Rcd at 16205. The Commission
also stated that it intends to commence a rulemaking proceeding proposing to explore orbital debris mitigation
issues. 2 GHz MSS Order, 15 FCC Rcd at 16188 ¶ 138.
     52
           47 C.F.R. § 25.143(b)(1), as amended by the 2 GHz MSS Order, 15 FCC Rcd at 16205.
     53
           See 2 GHz MSS Order, 15 FCC Rcd at 16118 ¶ 138.
     54
        See The Establishment of Policies and Service Rules for the Mobile Satellite Service in the 2 GHz Band, IB
Docket No. 99-81, 14 FCC Rcd 4843, 4901-03 (1999) (Appendix C).


                                                         8


                                    Federal Communications Commission                                    DA 01-1637

no longer than 25 years after mission completion. Under this option, it is also necessary to address the
casualty risk from any portions of the spacecraft that may survive atmospheric reentry. The second
option is maneuvering to a storage orbit. There are three suggested storage orbits. The first is between
low and middle Earth orbit, i.e., satellite perigee altitude above 2,000 kilometers and apogee altitude
below 19,700 kilometers. The second is between middle and geosynchronous Earth orbit, i.e., perigee
altitude above 20,700 kilometers and apogee altitude below 35,300 kilometers. The third is above
geosynchronous Earth orbit, i.e., perigee altitude above 36,100 kilometers (or approximately 300
kilometers above geosynchronous altitude). In addition to the NASA/DoD guidelines, and as the
Commission observed in the 2 GHz MSS Order,55 the ITU has developed a recommendation concerning
operations in the GSO.56
         22.    Each of the 2 GHz MSS systems submitted a narrative statement concerning orbital
debris mitigation. We note that, to the extent that the statements address debris mitigation issues
involving launch vehicle operations, we have neither reviewed nor concluded the plans disclosed are
appropriate.57 We also note that, to the extent debris mitigation plans for MSS systems change, the
system proponents should evaluate those changes to determine whether disclosure and/or prior approval
is required.58
         23.    In its Conforming Amendment, MCHI addressed orbital debris mitigation issues
pertinent to operations, including debris release and accidental explosions.59 However, MCHI did not
specifically address limiting the probability of collision with large, known objects during satellite orbital
lifetime. We expect MCHI and other 2 GHz MSS systems to develop appropriate operational plans and
procedures to minimize the possibility of collision with large, known objects.60 MCHI also addressed
end-of-mission orbital debris mitigation issues, including defining a system disposal strategy and
depletion of stored energy sources. Specifically, MCHI stated that “satellites will be moved to a sub-
GEO orbit whose perigee will exceed 2500 kilometers.”61 However, in order to permit assessment of
MCHI’s disposal plan and provide adequate information for potentially effected parties, we require
MCHI to supplement its narrative statement by providing greater specificity regarding the range of
storage orbit parameters selected for disposal of its satellites. This information should be submitted no

   55
         2 GHz MSS Order, 15 FCC Rcd at 16118 ¶ 138.
   56
          Recommendation ITU-R S.1003. The recommendation suggests, in pertinent part, that a geostationary
satellite at the end of its life should be transferred before complete exhaustion of its propellant, to a
“supersynchronous graveyard orbit that does not intersect the GSO,” with GSO defined as the mean earth radius of
42,164 kilometers plus or minus 300 kilometers. The recommendation also notes that what constitutes “an effective
graveyard orbit” requires further studies. In this regard, we note that orbital perturbations due to solar and lunar
gravitation, solar pressure, or other sources, may, over time, result in an inactive satellite’s orbit intersecting the
GSO, as defined by the ITU recommendation, even if the initial disposal altitude does not intersect the GSO.
   57
        The United States licensing authority for commercial launches is the Federal Aviation Administration. See
14 C.F.R. § 400 et seq.
   58
        See 47 C.F.R. §§ 1.65, 25.117(a). See also 2 GHz MSS Order, 15 FCC Rcd at 16179 ¶ 108 (system
modifications requiring prior FCC approval should be identified well in advance of the CDR milestone).
   59
         Conforming Amendment at 10-11.
   60
         See, e.g., Amendment to Pending Application of Iridium LLC, SAT-AMD-20001103-00156 (November 3,
2000) at Exhibit 1, p.2.
   61
         Conforming Amendment at 10. “GEO” means geosynchronous Earth orbit.


                                                          9


                                    Federal Communications Commission                                   DA 01-1637

later than six months prior to the CDR milestone. We also note that this Order does not authorize the
relocation of operational satellites to storage orbits at end-of-life. Such authorization will need to be
obtained through a request for modification of MCHI’s license.

H.        Other Issues

        24.      ICO Services Limited (ICO) and Iridium LLC (Iridium) commented that we should
require MCHI and all other domestic systems seeking access to 2 GHz MSS spectrum to demonstrate
financial qualifications to hold a 2 GHz MSS license.62 The Commission decided not to impose financial
qualifications for the current 2 GHz MSS processing round, and therefore, we need not address ICO’s
and Iridium’s requests any further.63
         25.     AT&T Wireless Services, Inc., Cingular Wireless LLC, Sprint PCS, and Verizon
Wireless (Wireless Carriers) in a recent joint letter requested the Commission to defer grant of the
pending 2 GHz MSS applications until (1) public comment is sought and received on the implications of
New ICO Global Communications (Holdings) Ltd.’s March 8, 2001 ex parte letter proposing amendment
of the 2 GHz MSS service rules to permit licensees to incorporate an “ancillary terrestrial component”
into their 2 GHz MSS networks; and (2) the Commission considers a petition for rule making submitted
by the Cellular Telecommunications & Internet Association (CTIA) requesting that the 2 GHz MSS
bands be reallocated for other uses, such as terrestrial wireless services.64 For the reasons set forth in the
ICO Order issued contemporaneously with this Order and Authorization, we deny the Wireless Carriers’
request to defer action on the 2 GHz MSS applications.65

                                        IV.      ORDERING CLAUSES

         26.      Accordingly, IT IS ORDERED that the Application File No. 180-SAT-P/LA-97(26);
IBFS Nos. SAT-LOA-19970926-00150 and SAT-AMD-20001103-00157 IS GRANTED to the extent
indicated herein and Mobile Communications Holdings, Inc. IS AUTHORIZED to construct, launch and
operate its proposed mobile-satellite system to provide service in the United States in the 1990-2025
MHz and 2165-2200 MHz frequency bands, in accordance with the technical specifications set forth in
its application, as amended, and consistent with our rules unless specifically waived herein, and subject
to the following conditions:




     62
        See Consolidated Comments of ICO Services Limited at 10-11; Consolidated Comments and Petition to
Deny of Iridium LLC at n.24; Consolidated Reply of Iridium LLC at 11-12.
     63
          2 GHz MSS Order, 15 FCC Rcd at 16150 ¶ 48.
     64
          Letter to Michael K. Powell, Chairman, Federal Communications Commission from Douglas Brandon,
AT&T Wireless Services, Inc., Brian F. Fontes, Cingular Wireless, LLC, Luisa L. Lancetti, Sprint Corporation, and
John T. Scott, III, Verizon Wireless, IB Docket No. 99-81 (dated June 13, 2001) (citing the ICO Ex Parte Letter and
CTIA Petition). Accord Ex parte Letter of CTIA, IB Docket No. 99-81 (dated July 12, 2001). But see Ex parte
Letter of Globalstar, L.P., IB Docket No. 99-81 (dated July 2, 2001) (objecting to the Wireless Carriers’ request); Ex
parte Letter of Celsat America, Inc., IB Docket No. 99-81 (dated June 25, 2001) (same).
     65
       See ICO Services Limited, Letter of Intent to Provide Mobile-Satellite Service in the 2 GHz Bands, Order,
DA 01-1635, at ¶¶ 29-31 (Int’l Bur./OET, rel. July 17, 2001).


                                                          10


                                 Federal Communications Commission                              DA 01-1637

            a. Mobile Communications Holdings, Inc. must choose a Selected Assignment in
               the 1990-2025 MHz and 2165-2200 MHz frequency bands upon launch of one
               satellite into its authorized satellite orbit, and commencement of operations by
               that satellite;
            b. The Selected Assignment shall give Mobile Communications Holdings, Inc.
               access to 3.5 megahertz in each direction of transmission on a primary basis;
            c. The Selected Assignment shall be chosen such that the band edge of the
               assignment is an integer multiple of 3.88 megahertz from the band edge of the
               2 GHz MSS band; and
            d. Operations in frequencies in these bands outside the Selected Assignment shall
               be on a secondary basis to operations of other 2 GHz MSS systems.
       27.    IT IS FURTHER ORDERED that Mobile Communications Holdings, Inc. IS
AUTHORIZED to operate its proposed mobile-satellite system in the 1990-2025 MHz and 2165-2200
MHz frequency bands outside the United States subject to the following conditions:
            a. In International Telecommunication Union (ITU) Regions 1 and 3, operations
               shall be limited to the 1990-2010 MHz and 2170-2200 MHz bands and shall
               comply with footnote S5.389F of the ITU Radio Regulations.66
            b. In ITU Region 2, operations shall comply with footnotes S5.389A, S5.389C,
               S5.389D, S5.389E, and S5.390 of the ITU Radio Regulations.67
            c. Mobile Communications Holdings, Inc. is obligated to comply with the
               applicable laws, regulations, rules, and licensing procedures for those countries
               it proposes to serve.
        28.      IT IS FURTHER ORDERED that Mobile Communications Holdings, Inc. IS
AUTHORIZED to construct, launch and operate its proposed mobile-satellite system capable of
operating in the 15.43-15.63 GHz band (Earth-to-space) and the 6775-7075 MHz band (space-to-Earth)
for feeder link operations, in accordance with the technical specifications set forth in its application, as
amended, and consistent with our rules unless specifically waived herein, and subject to the following
conditions:
            a. Section 2.102(a) of the Commission’s rules, 47 C.F.R. § 2.102(a), IS WAIVED
               to permit Mobile Communications Holdings, Inc. to operate its feeder uplink
               transmissions in 200 megahertz of spectrum in the 15.43-15.63 GHz band, and
               its feeder downlink transmissions in 200 megahertz of spectrum in the

  66
        ITU Radio Regulations Footnote S5.389F (placing limitations on MSS use of the 1980-2010 MHz and
2170-2200 MHz bands in Algeria, Benin, Cape Verde, Egypt, Mali, Syria and Tunisia).
  67
         ITU Radio Regulations Footnotes S5.389A (among other things, allocating the 1990-2010 MHz and 2170-
2200 MHz bands to MSS, subject to coordination, effective January 1, 2000); S5.389C (allocating the 2010-2025
MHz and 2165-2170 MHz bands to MSS in Region 2, subject to coordination, effective January 1, 2002); S5.389D
(permitting MSS use of the 2010-2025 MHz and 2165-2170 MHz bands in the United States and Canada, effective
January 1, 2000); S5.389E (placing limitations on MSS use of the 2010-2025 MHz and 2165-2170 MHz bands in
Region 2 with respect to other services’ operations in these bands in Regions 1 and 3); and S5.390 (placing
limitations on MSS use of the 2010-2025 MHz and 2165-2170 MHz bands in Argentina, Brazil, Chile, Columbia,
Cuba, Ecuador and Suriname).


                                                     11


                                 Federal Communications Commission                               DA 01-1637

                6775-7075 MHz band, in accordance with the terms of this Order, and subject to
                any applicable rules that may be promulgated in ET Docket No. 98-142,
                Amendment of Parts 2, 25 and 97 of the Commission’s Rules with Regard to the
                Mobile-Satellite Service Above 1 GHz.
            b. Within 60 days after the Commission adopts allocation rules to permit MSS
               feeder links in the 6775-7075 MHz band, Mobile Communications Holdings,
               Inc. shall file a letter for inclusion in its license file designating the specific 200
               megahertz of the 6775-7075 MHz band in which it intends to operate its feeder
               downlink transmissions.
            c. Mobile Communications Holdings, Inc. shall coordinate its feeder uplink
               operations in the 15.43-15.63 GHz band through the Frequency Assignment
               Subcommittee of the Interdepartment Radio Advisory Committee of the National
               Telecommunication and Information Administration.
        29.     IT IS FURTHER ORDERED that Mobile Communications Holdings, Inc.’s request to
operate feeder uplink transmissions in the 15.4-15.43 GHz and 15.63-15.7 GHz bands IS DENIED.
        30.     IT IS FURTHER ORDERED that this authorization shall be become NULL and VOID
with no further action required on the Commission’s part in the event the space stations are not
constructed, launched and placed into operation in accordance with the technical parameters and terms
and conditions of the authorization by the following dates:

         Milestone                                                                       Deadline
         Enter Non-contingent Satellite Manufacturing Contract                         July 17, 2002
         Complete Critical Design Review                                               July 17, 2003
         Begin Physical Construction of All Satellites                               January 17, 2004
         Complete Construction and Launch First Two Satellites in System             January 17, 2005
         Certify Entire System Operational                                             July 17, 2007

        31.     IT IS FURTHER ORDERED that Mobile Communications Holdings, Inc. will prepare
any necessary submissions to the ITU to initiate and complete the advance publication, international
coordination, and notification process for the space stations authorized by this Order, in accordance with
the ITU Radio Regulations. No protection from interference caused by radio stations authorized by other
Administrations is guaranteed unless coordination procedures are timely completed or, with respect to
individual Administrations, by successfully completing coordination agreements. Any radio station
authorization for which coordination has not been completed may be the subject of additional terms and
conditions as required to effect coordination of the frequency assignments of other Administrations.
47 C.F.R. § 25.111(b).
       32.    IT IS FURTHER ORDERED that this Order is subject to change by summary order of
the Commission on 30 days’ notice and does not confer any permanent right to use the orbit and
spectrum.
        33.      IT IS FURTHER ORDERED that Mobile Communications Holdings, Inc. may decline
this authorization as conditioned within 30 days of the date of the release of this Order and
Authorization. Failure to respond within that period will constitute formal acceptance of the
authorization as conditioned.

                                                     12


                                Federal Communications Commission                           DA 01-1637

      34.     This Order and Authorization is issued pursuant to Sections 0.241 and 0.261 of the
Commission’s rules on delegations of authority, 47 C.F.R. §§ 0.241, 0.261, and is effective upon release.

                                                FEDERAL COMMUNICATIONS COMMISSION




                                                Donald Abelson
                                                Chief, International Bureau




                                                Bruce A. Franca
                                                Acting Chief, Office of Engineering and Technology




                                                   13


                              Federal Communications Commission          DA 01-1637


                                         APPENDIX A

                       LIST OF PLEADINGS ADDRESSING
             MOBILE COMMUNICATIONS HOLDINGS, INC.’S APPLICATION


Filed May 4, 1998

Comments of Celsat America, Inc.
Comments of Constellation Communications, Inc. at 25
Consolidated Comments of ICO Services Limited at 10-11.
Consolidated Comments and Petition to Deny of Iridium LLC at n.24
Petitions to Deny and Comments of Mobile Communications Holdings, Inc.
Comments of Wireless Communications Association International, Inc.


Filed June 3, 1998

Consolidated Reply Comments of Mobile Communications Holdings, Inc.

Filed June 18, 1998

Consolidated Reply of Iridium LLC at 11-12
Consolidated Response of Mobile Communications Holdings, Inc.




                                                14



Document Created: 2001-07-19 16:25:59
Document Modified: 2001-07-19 16:25:59

© 2024 FCC.report
This site is not affiliated with or endorsed by the FCC