                RaySat, Inc. – Supplemental Information in Support
               Of Request To Modify Experimental License WD2XTB
                             File No. 0135-EX-ML-2005

RaySat, Inc. submits the following information to supplement the above-referenced
request to modify experimental license WD2XTB:

1)     The sole requested modification to the experimental license is to add the
capability of carrying out a market study. No other modification to the license is
requested.

2)      The required number of terminals for the market study is 90. There are two
primary reasons that 90 terminals are required. First, use of 90 terminals is the minimum
number to provide a broad enough sample of users, conditions, and applications to result
in useful test data. Use of fewer than 90 terminals will not allow for a broad enough
cross-section of users and conditions to be of evaluative use. Second, there are a large
number of different participants slated for the study, including the U.S. military and other
U.S. government agencies, state and local emergency first responder agencies, VSAT
service vendors, and recreational vehicle equipment manufacturers. The variety of users
is required in order for the system to be tested in a broad range of environments and
under a variety of conditions. With the broad range of users, 90 terminals are required in
order to provide sufficient units to each participant.

4)       The market study is required to be carried out on a CONUS basis due to the need
to test the platform in a broad range of terrains, elevations, and weather conditions and
with a broad test base made up of users in different industries, who by definition will
operate in various parts of the country. Limiting the test to particular geographic areas
would significantly reduce the effectiveness of the test program.

5)      As Raysat indicated to the FCC upon OET’s review of the original experimental
license application, coordination with U.S. government radioastronomy and space
exploration users (including NASA and NSF) is not required, as RaySat is not operating
in the 14.0–14.2 or 14.45–14.5 bands utilized by these services. RaySat has reserved
sufficient capacity on the AMC-5 satellite throughout the experimental license period to
ensure that all operations will be outside of these bands.

3)     Raysat will retrieve all of the terminals from the study participants at the
conclusion of the market study.

4)     Raysat will recover its costs (including space segment airtime costs and other
allocable costs) from study participants, but will not charge or receive any profit.



Document Created: 2019-02-17 23:17:12
Document Modified: 2019-02-17 23:17:12

© 2024 FCC.report
This site is not affiliated with or endorsed by the FCC