L3Harris

1673-EX-ST-2020

Status: Pending


2020-10-26

Documents and Communications: [refresh]

DescriptionCategoryDate
Overview of ExperimentText Documents2020-10-26
E-Mail generated [Oct 27 2020]Correspondence2020-10-27
Incoming generated [Oct 27 2020]Correspondence2020-10-27
Incoming generated [Nov 2 2020]Correspondence2020-11-02
Grant E-mail Notification generated [Nov 6 2020]Correspondence2020-11-06
Application Form:
OET Special Temporary Authority Report
FEDERAL COMMUNICATIONS COMMISSION
APPLICATION FOR SPECIAL TEMPORARY AUTHORITY

Applicant Name
Name of Applicant:  L3Harris

Address
Attention: Samuel Steed
Street Address: 640 N 2200 W
P.O. Box:
City: Salt Lake City
State: UT
Zip Code: 84116
Country:
E-Mail Address: [email protected]

Best Contact
Give the following information of person who can best handle inquiries pertaining to this application:  
Last Name: Steed
First Name: Samuel
Title: Lead, Grade 5, Systems Engineer
Phone Number: 801-671-7774

Explanation
Please explain in the area below why an STA is necessary:
An office inside of the DoD is evaluating whether it would like to buy and field Banshee Radios for its use. We will be demonstrating in Omaha around Offut AFB the Banshee Radio. There will be a ground based banshee and an airborne based Banshee. Notification of the need for this demonstration was not given with enough lead time to be able to pursue a standard FCC license.

Purpose of Operation
Please explain the purpose of operation:  The Banshee radio will be sending telemetry and other data from air to air or from air to ground platforms.

Information
Callsign: WR9XGO
Class of Station: MO
Nature of Service: Experimental

Requested Period of Operation
Operation Start Date: 11/09/2020
Operation End Date: 04/09/2021

Manufacturer
List below transmitting equipment to be installed (if experimental, so state) if additional rows are required, please submit equipment list as an exhibit:  
Manufacturer Model Number No. Of Units Experimental
L3Harris Communication Systems-West 1007600000 2 Yes

Certification
Neither the applicant nor any other party to the application is subject to a denial of Federal benefits that includes FCC benefits pursuant to Section 5301 of the Anti-Drug Abuse Act of 1988, 21 U.S.C. Section 862, because of a conviction for possession or distribution of a controlled substance. The applicant hereby waives any claim to the use of any particular frequency or electromagnetic spectrum as against the regulatory power of the United States because of the prvious use of the same, whether by license or otherwise, and requests authorization in accordance with this application. (See Section 304 of the Communications Act of 1934, as amended.) The applicant acknowledges that all statements made in this application and attached exhibits are considered material representations, and that all the exhibits part hereof and are incorporated herein as if set out in full in this application; undersigned certifies that all statements in this application are true, complete and correct to the best of his/her knowledge and belief and are made in good faith. Applicant certifies that construction of the station would NOT be an action which is likely to have a significant environmental effect. See the Commission's Rules, 47 CFR1.1301-1.1319.
Signature of Applicant (Authorized person filing form): Samuel Steed
Title of Applicant (if any): Lead, Grade 5, Systems Engineer
Date: 2020-10-26 00:00:00.0

Station Location
City State Latitude Longitude Mobile Radius of Operation
Omaha Nebraska North  41  6  55 West  95  55  21 Omaha, NB 42.60
Datum:  NAD 83
Is a directional antenna (other than radar) used?   No
Exhibit submitted:   No
(a) Width of beam in degrees at the half-power point:  
(b) Orientation in horizontal plane:  
(c) Orientation in vertical plane:  
Will the antenna extend more than 6 meters above the ground, or if mounted on an existing building, will it extend more than 6 meters above the building, or will the proposed antenna be mounted on an existing structure other than a building?   No
(a) Overall height above ground to tip of antenna in meters:  
(b) Elevation of ground at antenna site above mean sea level in meters:  
(c) Distance to nearest aircraft landing area in kilometers:  
(d) List any natural formations of existing man-made structures (hills, trees, water tanks, towers, etc.) which, in the opinion of the applicant, would tend to shield the antenna from aircraft:
Action Frequency Station Class Output Power/ERP Mean Peak Frequency Tolerance (+/-) Emission Designator Modulating Signal
New 2000.00000000-2290.00000000 MHz MO 1.000000 W 1.000000 W M 0.01000000 % 60M0G7W DSSS
Action Frequency Station Class Output Power/ERP Mean Peak Frequency Tolerance (+/-) Emission Designator Modulating Signal
New 3100.00000000-3550.00000000 MHz MO 1.000000 W 1.000000 W M 0.01000000 % 60M0G7W DSSS

15948