Application Form:
OET Special Temporary Authority Report
FEDERAL COMMUNICATIONS COMMISSION
APPLICATION FOR SPECIAL TEMPORARY AUTHORITY

Applicant Name
Name of Applicant:  Intel Corporation

Address
Attention: Robert Paxman
Street Address: 2111 NE 25th Ave, JF3-302
P.O. Box:
City: Hillsboro
State: OR
Zip Code: 97124
Country:
E-Mail Address: [email protected]

Best Contact
Give the following information of person who can best handle inquiries pertaining to this application:  
Last Name: Paxman
First Name: Robert
Title: Wireless Regulatory Engineer
Phone Number: 805-276-5358

Explanation
Please explain in the area below why an STA is necessary:
FCC Special Temporary Authority is requested for a demonstration of an indoor light show at the address of 1 AMB Drive Northwest, Atlanta, Georgia, 30313.

Purpose of Operation
Please explain the purpose of operation:  To gain temporary approval to perform rehearsals and an indoor light show at the specific venue and event listed above.

Information
Callsign: WN9XUL
Class of Station: FX MO
Nature of Service: Experimental

Requested Period of Operation
Operation Start Date: 02/03/2019
Operation End Date: 02/05/2019

Manufacturer
List below transmitting equipment to be installed (if experimental, so state) if additional rows are required, please submit equipment list as an exhibit:  
Manufacturer Model Number No. Of Units Experimental
Intel Corporation Anchor 35 Yes
Intel Corporation Shooting Star 300 Yes

Certification
Neither the applicant nor any other party to the application is subject to a denial of Federal benefits that includes FCC benefits pursuant to Section 5301 of the Anti-Drug Abuse Act of 1988, 21 U.S.C. Section 862, because of a conviction for possession or distribution of a controlled substance. The applicant hereby waives any claim to the use of any particular frequency or electromagnetic spectrum as against the regulatory power of the United States because of the prvious use of the same, whether by license or otherwise, and requests authorization in accordance with this application. (See Section 304 of the Communications Act of 1934, as amended.) The applicant acknowledges that all statements made in this application and attached exhibits are considered material representations, and that all the exhibits part hereof and are incorporated herein as if set out in full in this application; undersigned certifies that all statements in this application are true, complete and correct to the best of his/her knowledge and belief and are made in good faith. Applicant certifies that construction of the station would NOT be an action which is likely to have a significant environmental effect. See the Commission's Rules, 47 CFR1.1301-1.1319.
Signature of Applicant (Authorized person filing form): Robert W. Paxman
Title of Applicant (if any): Wireless Regulatory Engineer
Date: 2019-01-28 00:00:00.0

Station Location
City State Latitude Longitude Mobile Radius of Operation
Atlanta Georgia North  33  45  16 West  84  24  9 Within the structure at 1 AMB Drive Northwest 1.00
Datum:  NAD 83
Is a directional antenna (other than radar) used?   No
Exhibit submitted:   No
(a) Width of beam in degrees at the half-power point:  
(b) Orientation in horizontal plane:  
(c) Orientation in vertical plane:  
Will the antenna extend more than 6 meters above the ground, or if mounted on an existing building, will it extend more than 6 meters above the building, or will the proposed antenna be mounted on an existing structure other than a building?   Yes
(a) Overall height above ground to tip of antenna in meters:   80.00
(b) Elevation of ground at antenna site above mean sea level in meters:   94.00
(c) Distance to nearest aircraft landing area in kilometers:   11.00
(d) List any natural formations of existing man-made structures (hills, trees, water tanks, towers, etc.) which, in the opinion of the applicant, would tend to shield the antenna from aircraft: Anchors will be mounted inside building on ceiling pointed downward.
Action Frequency Station Class Output Power/ERP Mean Peak Frequency Tolerance (+/-) Emission Designator Modulating Signal
New 6234.60000000-6744.60000000 MHz FX 0.200000 mW 0.610000 mW P 0.00100000 % 553MG7D BPM-BPSK

City State Latitude Longitude Mobile Radius of Operation
Atlanta Georgia North  33  45  16 West  84  24  9 Inside the structure at 1 AMB Drive Northwest 1.00
Datum:  NAD 83
Is a directional antenna (other than radar) used?   No
Exhibit submitted:   No
(a) Width of beam in degrees at the half-power point:  
(b) Orientation in horizontal plane:  
(c) Orientation in vertical plane:  
Will the antenna extend more than 6 meters above the ground, or if mounted on an existing building, will it extend more than 6 meters above the building, or will the proposed antenna be mounted on an existing structure other than a building?   Yes
(a) Overall height above ground to tip of antenna in meters:   35.00
(b) Elevation of ground at antenna site above mean sea level in meters:   94.00
(c) Distance to nearest aircraft landing area in kilometers:   11.00
(d) List any natural formations of existing man-made structures (hills, trees, water tanks, towers, etc.) which, in the opinion of the applicant, would tend to shield the antenna from aircraft: Operation will remain inside the structure at 1 AMB Drive Northwest.
Action Frequency Station Class Output Power/ERP Mean Peak Frequency Tolerance (+/-) Emission Designator Modulating Signal
New 6234.60000000-6744.60000000 MHz MO 0.200000 mW 0.610000 mW P 0.00100000 % 548MG7D BPM-BPSK

19360