Request for Extension of Time II

0398-EX-PL-2008 Text Documents

Bigelow Aerospace, LLC

2008-12-15ELS_95206

                                        December 15, 2008

 DAVID S. KEIR                                                                                   E-MAIL
(202) 416-6742                                                                             DKEIR@LSL-LAW.COM




 SUBMITTED ELECTRONICALLY

 Mr. James Burtle
 Chief, Experimental Licensing Branch
 Office of Engineering and Technology
 Federal Communications Commission
 445 12th Street, SW
 Washington, DC 20554

                 Re:   Ref. #7610 - Application of Bigelow Aerospace, LLC for
                       Experimental License (OET File No. 0398-EX-PL-2008)

 Dear Mr. Burtle:

         This letter is written on behalf of Bigelow Aerospace, LLC (“Bigelow Aerospace”) in
 further response to the October 17, 2008 correspondence from Leann Nguyen requesting
 additional information concerning the above-referenced application. In particular, the
 Experimental Licensing Branch (“Branch”) is seeking a demonstration, consistent with the
 requirements of the International Bureau and Part 25 of the Commission’s Rules, that the
 proposed operation will not cause harmful interference to geostationary orbit satellite (“GSO”)
 networks operating in the Ku-band. The Branch originally requested that Bigelow Aerospace
 provide such a showing by November 17, 2008, thirty days from the date of the email request.

          On November 12, 2008, Bigelow Aerospace sought an additional thirty (30) days, to and
 including December 17, 2008, within which to provide the requested demonstration. At that
 time, Bigelow Aerospace cited the complex interference showing required under Sections 25.146
 and 25.208 of the Commission’s Rules, and noted that it required additional time to complete the
 study. Because Bigelow Aerospace is seeking to employ the Ku-band spectrum on an
 experimental basis, and not for the type of commercial service anticipated for applicants under
 Section 25.146 of the Commission’s Rules, it is seeking to provide the information that the
 Branch has requested without engaging outside technical consultants. As a result, preparation of
 the required showing must be undertaken by Bigelow Aerospace’s engineering staff in addition
 to their current operational duties. For this reason, Bigelow Aerospace has not yet completed a
 full interference showing pursuant to Section 25.208, though it is continuing to work with


Mr. James Burtle
December 15, 2008
Page -2-



International Bureau staff to identify the most effective means to present this showing using
available modeling software.

       Accordingly, for the reasons outlined herein, Bigelow Aerospace respectfully requests
additional time within which to prepare a complete response to the Branch’s October 17, 2008
request, and asks that it be permitted to file its response on or before January 16, 2009.

       Should there be any questions concerning this request, please contact the undersigned
counsel.

                                                     Respectfully submitted,

                                                     s/ David S. Keir
                                                     David S. Keir
                                                       Counsel to Bigelow Aerospace, LLC


cc: Ms. Leann Nguyen, OET*
    Mike Gold, Bigelow Aerospace*
    Peter Blouke, Bigelow Aerospace*

    * = via email



Document Created: 2008-12-15 17:26:46
Document Modified: 2008-12-15 17:26:46

© 2025 FCC.report
This site is not affiliated with or endorsed by the FCC